Utilities construction schedule for remaining work 19 10 2018 最终
Utilities construction schedule for remaining work 19 10 2018 最终
OASIS SURF.DRAN 5527 1046 19% 4481 4774 293 6% 2406 2075
IRR 36761 35263 96% 1498 5424 3926 72% 521 977
IRR (OASIS) 4185 2552 61% 1633 3527 1894 54% 200 1433
FUEL TRENCH 14285 12525 88% 1760 3942 2182 55% 495 1265
W.S (OASIS) 2246 1830 81% 416 1805 1389 77% 129 287
C.W (OASIS LINE) 2216 1798 81% 418 2005 1587 79% 0 418
11KV 13207 12038 91% 1169 4339 3170 73% 400 769
415V 22302 21349 96% 953 4579 3626 79% 362 591
415V (OASIS) 2680 857 32% 1823 2534 711 28% 588 1235
FBS 21909 20599 94% 1310 3471 2161 62% 320 990
TELECOM 17272 15326 89% 1946 4192 2246 54% 357 1589
TELE (OASIS) 2080 343 16% 1737 2080 343 16% 496 1241
S.W 32712 32429 99% 283 1416 1133 80% 161 122
TRAFFIC PIPE LINE 10065 3965 39% 6100 - 3965 - 3000 3100
TRAFFIC MH&HH&TCC&PB 764 540 71% 224 755 529 70% 100 124
All MH& HH Cover 4372 2615 60% 1757 - 2615 - 450 1000