You are on page 1of 4

Annexure 20.

Comparative table of the two Options at Ngomo Escarpment

Option 1 – Section II
Option 2 – Section IIA
(Nominal improvement of
Description (Bypass in Ngomo
Existing Road in Ngomo
Escarpment)
Escarpment)
Length (km) 28.1 20.435
Road Alignment Highly bendy and undulating in Bendy and gently undulating
Mountainous terrain in Mountainous terrain
Major Engineering Involves landslide locations Alignment intercepts number
Constraints Improvement of horizontal of small hills which involve
geometry in the Ngomo large cuts in bypass section.
escarpment section to the full Accessing the greenfield re-
standards requirement is not alignment will require
possible due to habitation along temporary access roads.
the road and mountain & valley
scenario adjacent to road. Will
need diversion during
construction.
Structures Minor Bridge – 1 No. Minor Bridge – 3 Nos.

Junctions Major Junctions – 1 No. Major junctions – 2 Nos.


Minor Junctions – 25 Nos. Minor Junctions – 1 No.
Available Right of Way Varying from 15 - 30m ROW New land acquisition for
(ROW)/Road Reserve Available bypass in the Ngomo
For the existing road in Ngomo escarpment section is
escarpment section additional required but should not be
land acquisition in the habitation difficult as there is minimal/no
areas/settlements would be bit habitation along this
difficult as it would impact the alignment
properties
Road Geometry Majority of the horizontal Curves Majority of the horizontal
are sharper and substandard Curves are sharper but much
not complying with the EAC lesser than compared to
standards. Option 1 and all curves are
Due to the more number of fulfilling the requirements of
curves and also more curves EAC standards.
with substandard geometry the Number of vertical curves are
operational efficiency of the lesser than Option-1.
road would be drastically
impacted.
Number of vertical curves also
more in this option.
Option 1 – Section II
Option 2 – Section IIA
(Nominal improvement of
Description (Bypass in Ngomo
Existing Road in Ngomo
Escarpment)
Escarpment)
 Horizontal Curves  Horizontal Curves
Horizontal Curves 1 Nos. Horizontal Nil
with radius >1500 Curves with
radius >1500
Horizontal Curves 1 Nos.
with radius >650m Horizontal 2 Nos.
to <=1500m Curves with
radius >650m
Horizontal Curves 11 Nos.
to <=1500m
with radius >200m
to <=650m Horizontal 16 Nos.
Curves with
Horizontal Curves 24 Nos.
radius >200m
with radius >90m
to <=650m
to <=200m
Horizontal 53 Nos.
Horizontal Curves 42 Nos.
Curves with
with radius >=30m
radius >90m to
to <=90m
<=200m
Substandard 46 Nos.
Horizontal 6 Nos.
curves with radius
Curves with
>30m to <=90m
radius >=35m
Substandard 78 Nos. to <=90m
curves with radius
Total = 77
>10m to <=30m
 Vertical Curves
Total = 203
No. of summit 24 Nos.
 Vertical Curves
curve
No. of summit 37 Nos.
No. of valley 24 Nos.
curve
curve
No. of valley curve 35 Nos.
Total = 48
Total = 72
Vertical Gradient Min - 0.5% Min - 0.5%
Max - 7.404% Max - 10.0%
Environmental Impacts Likely to involve unstable Hill Likely to involve Hill Cutting
Cutting however no major however no major
environmental impacts environmental impacts
envisaged. Due to closer envisaged except tree cutting
proximity of Rusizi river there
could be slightly more
environmental impact issues
compared to Option 2.
Social Impacts  Social Impact in Kamanyola  No Social Impact in
town Kamanyola town due to
 Safety and security issues proposed bypass
due to Rwanda Border in  Alignment is away from
Option 1 – Section II
Option 2 – Section IIA
(Nominal improvement of
Description (Bypass in Ngomo
Existing Road in Ngomo
Escarpment)
Escarpment)
close vicinity Rwanda Border hence
 Acquisition of land would be border related safety and
an issue in Ngomo security issues are avoided
escarpment due to habitation  Acquisition of agricultural
land in Ngomo escarpment
bypass section
Cost Impacts  Less cost compared to  More cost than Option 1
Option 2 due to New pavement &
 Estimated Civil Cost per km Major Earthworks in
(USD in Millions) – 2.63 Ngomo Bypass section
 Estimated Civil Cost per
km (USD in Millions) –
5.13
Merits & Demerits
Merits  Lesser Land Acquisition area  Alignment length is lesser
 Construction cost is less by 7.665 km
compared to Option 2  Horizontal geometry is fully
complying with the EAC
standards
 Travel time will be much
lesser compared to Option
1, hence Road User Cost
will be lesser
 Less social impacts
 Economic activities will be
boosted due to proper
alignment geometry, lesser
travel length & time
 Higher EIRR compared to
Option 1
 Safety and security issues
are avoided as the
alignment is away from
Rwanda border
 Since there is minimal/no
habitation along the
proposed bypass section
at Ngomo escarpment, no
hindrances are envisaged
during the construction. In
addition, as also no
diversion of traffic is
involved that would enable
the project completion
within stipulated timelines.
Option 1 – Section II
Option 2 – Section IIA
(Nominal improvement of
Description (Bypass in Ngomo
Existing Road in Ngomo
Escarpment)
Escarpment)
Demerits  Alignment length is more by  Construction cost more
7.665 km compared to Option 1
 Horizontal geometry has  Proposed structures along
more curves and also has the alignment are slightly
many substandard curves and higher compared to Option
due to which the operational 1
efficiency of the road is  Accessibility during
compromised and frequent construction is an issue
delays are much envisaged.
Eventually this option would
form a major bottleneck for the
movement of traffic from
Kalundu Port to Bukavu.
 Travel time will be more
 More social impacts
 Safety and security issues will
still persist due to close
proximity of Rwanda border
 Construction of drainage &
protection works and new
pavement/upgrading works
along the existing Ngomo
escarpment road would be
more cumbersome as
compared to Option 2 due to
the habitation and requirement
of traffic diversion. This will
also cause the delay in project
completion.

You might also like