You are on page 1of 4

Road Reserve Width

Formation Width (15m)

1.5m 1.5m 1m 3.5m 3.5m 1m 1.5m 1.5m


Nature Traffic Lane Traffic Lane Nature

Shoulder
Shoulder
Drain Drain
cum Strip Strip cum
Footpath Footpath
Urban Border Urban Border

RRW
RRW
SIGN

RRW
RRW
BOARD

RRW Pillar CL RRW Pillar


@ 100m c/c @ 100m c/c
2.0% 2.0%

RRW
3.0% 3.0% 4.0%

RRW
H H
1 1
GL GL

Existing Gravel Road Surface Wearing Course


Unlined Drain (Assumed as Subgrade top) Surface Course Unlined Drain
(Note 3) Base Course (Note 3)
Sub base Course
Subgrade

TCS - 1
2 LANE CARRIAGEWAY WITH FOOTHPATH CUM DRAIN IN URBAN SECTION

Road Reserve Width

Formation Width (14m)


RRW

RRW
2m 1.5m 3.5m 3.5m 1.5m 2m
Verge Shoulder Traffic Lane Traffic Lane Shoulder Verge
RRW

RRW
CL 1m
W-Beam (TL3) W-Beam (TL3)
Crash Barrier Crash Barrier

RRW Pillar RRW Pillar


RRW

RRW
@ 100m c/c 4.0% 3.0% 3.0% 4.0% @ 100m c/c
H H
1 1
GL GL

Existing Gravel Road Surface Wearing Course


Unlined Drain (Assumed as Subgrade top) Surface Course Unlined Drain NOTES:-
(Note 3) Base Course (Note 3)
1. All dimensions are in mm unless otherwise indicated.
Sub base Course
2. The referred TCS is also applicable for Realignment
Subgrade sections in which the New Construction is to be taken up.
3. Road side drainage shall be provided as per section 4.6 of AGRD 03 (2021)
TCS - 2 4. Provision of batter slope shall be as follows:
2 LANE CARRIAGEWAY WITH SAFETY BARRIER IN RURAL SECTION Cut Fill
Type of Batter
Desirable Maximum Maximum Desirable Maximum Maximum
Earth batter 3:1 2:1 6:1 4:1
Rock batter 0.5:1 0.25:1 - -

5. In-situ subgrade material to be compacted prior to


construction of road pavement layers.
6. Details for Pavement Composition shall be as per Pavement design.

R0 April, 2024 Initial Drawings


Revisions Date Description Checked by

CLIENT: SCALE:- PROJECT TITLE: DRAWING TITLE: DT Global Asia Pacific


In Joint Venture with Revisions
Consultancy Services for Preparation of Feasibility Study and Detailed Intercontinental Consultants & Technocrats Pvt.Ltd,
Not to Scale TYPICAL CROSS SECTION A-8, Green Park, New Delhi - 110016 DRAWING NO. :
PNG Engineering Designfor Mountainous Road Improvement and Resilience OPTION ANALYSIS REPORT Ph : 011 4086-3000, Fax 2685-5252
TCS-1 , TCS-2 ICT-DT-GAP/BUL-NAN /TCS/01/R0
S.Bhardwaj Vidyanand P. Robinson Varghese Marko Vrkljan
Prepared by Designed by Checked by Approved by Contarct No. : -----
Road Reserve Width

Formation Width (14m)

2m 1.5m 3.5m 3.5m 1.5m 2m


Verge Traffic Lane Traffic Lane Shoulder Verge

RRW

RRW
RRW

RRW
CL
RRW Pillar RRW Pillar
@ 100m c/c 4.0% 3.0% 3.0% 4.0% @ 100m c/c
RRW

RRW
H H
GL 1 1 GL

Wearing Course
Existing Gravel Road Surface Surface Course
Unlined Drain Base Course Unlined Drain
(Assumed as Subgrade top)
(Note 3) Sub base Course (Note 3)
Subgrade

TCS - 3
2 LANE CARRIAGEWAY WITH VERGE ROUNDING IN RURAL SECTION

Road Reserve Width

Formation Width (14m)

2m 1.5m 3.5m 3.5m 1.5m 2m


Verge Traffic Lane Traffic Lane Shoulder Verge
RRW

CL
SIGN
RRW

BOARD

1 1
N N
4.0% 3.0% 3.0% 4.0%
RRW

H H
1 1
0.5m 0.5m

Wearing Course
Unlined Drain Surface Course Unlined Drain NOTES:-
(Note 3) Base Course (Note 3) 1. All dimensions are in mm unless otherwise indicated.
Sub base Course 2. The referred TCS is also applicable for Realignment
Subgrade sections in which the New Construction is to be taken up.
3. Road side drainage shall be provided as per section 4.6 of AGRD 03 (2021)
TCS - 4 4. Provision of batter slope shall be as follows:
2 LANE CARRIAGEWAY IN SHALLOW CUT SECTION (<3.0) Cut Fill
Type of Batter
Desirable Maximum Maximum Desirable Maximum Maximum
Earth batter 3:1 2:1 6:1 4:1
Rock batter 0.5:1 0.25:1 - -

5. In-situ subgrade material to be compacted prior to


construction of road pavement layers.
6. Details for Pavement Composition shall be as per Pavement design.

R0 April, 2024 Initial Drawings


Revisions Date Description Checked by

CLIENT: SCALE:- PROJECT TITLE: DRAWING TITLE: DT Global Asia Pacific


In Joint Venture with Revisions
Consultancy Services for Preparation of Feasibility Study and Detailed Intercontinental Consultants & Technocrats Pvt.Ltd,
Not to Scale A-8, Green Park, New Delhi - 110016 DRAWING NO. :
PNG Engineering Designfor Mountainous Road Improvement and Resilience TYPICAL CROSS SECTION OPTION ANALYSIS REPORT Ph : 011 4086-3000, Fax 2685-5252
TCS-3 , TCS-4 ICT-DT-GAP/BUL-NAN /TCS/02/R0
S.Bhardwaj Vidyanand P. Robinson Varghese Marko Vrkljan
Prepared by Designed by Checked by Approved by Contarct No. : -----
Road Reserve Width
3m 3m
1 in 10 Formation Width (14m) 1 in 10

2m 1.5m 3.5m 3.5m 1.5m 2m


Verge Shoulder Traffic Lane Traffic Lane Shoulder Verge

RRW

RRW
Catch Drain SIGN Catch Drain
BOARD
(Note 3) (Note 3)
RRW

RRW
6.0m

6.0m
CL

4.0% 3.0% 3.0% 4.0%


RRW

RRW
2.5m 2.5m

Wearing Course
Stone Masonary/ Unlined Drain Unlined Drain Stone Masonary/
Surface Course
Cement Concrete Wall (Note 3) Base Course (Note 3) Cement Concrete Wall
Sub base Course
Subgrade

TCS - 5
2 LANE CARRIAGEWAY WITH BOTH SIDE BREAST WALL IN CUT SECTION (>10m)

Road Reserve Width

Formation Width (14m)

2m 1.5m 3.5m 3.5m 1.5m 2m


Verge Shoulder Traffic Lane Traffic Lane Shoulder Verge
RRW

RRW
CL
W-Beam (TL3) W-Beam (TL3)
Crash Barrier C Crash Barrier
RRW

RRW
Stone Masonry Wall/ 3.0% 3.0% Stone Masonry Wall/
4.0% 4.0%
Toe Wall / Retaining Wall Toe Wall / Retaining Wall
RRW Pillar RRW Pillar
RRW

RRW
@ 100m c/c @ 100m c/c

GL GL

Wearing Course
Existing Gravel Road Surface Surface Course NOTES:-
Unlined Drain Base Course Unlined Drain 1. All dimensions are in mm unless otherwise indicated.
(Note 3) Sub base Course (Note 3) 2. The referred TCS is also applicable for Realignment
Subgrade sections in which the New Construction is to be taken up.
3. Road side drainage shall be provided as per section 4.6 of AGRD 03 (2021)
TCS - 6 4. Provision of batter slope shall be as follows:

2 LANE CARRIAGEWAY WITH BOTH SIDE SM / RETAINING WALL IN FILL SECTION Type of Batter
Cut Fill
Desirable Maximum Maximum Desirable Maximum Maximum
Earth batter 3:1 2:1 6:1 4:1
Rock batter 0.5:1 0.25:1 - -

5. In-situ subgrade material to be compacted prior to


construction of road pavement layers.
6. Details for Pavement Composition shall be as per Pavement design.

R0 April, 2024 Initial Drawings


Revisions Date Description Checked by

CLIENT: SCALE:- PROJECT TITLE: DRAWING TITLE: DT Global Asia Pacific


In Joint Venture with Revisions
Consultancy Services for Preparation of Feasibility Study and Detailed Intercontinental Consultants & Technocrats Pvt.Ltd,
Not to Scale A-8, Green Park, New Delhi - 110016 DRAWING NO. :
PNG Engineering Designfor Mountainous Road Improvement and Resilience TYPICAL CROSS SECTION OPTION ANALYSIS REPORT Ph : 011 4086-3000, Fax 2685-5252
TCS-5 , TCS-6 ICT-DT-GAP/BUL-NAN /TCS/03/R0
S.Bhardwaj Vidyanand P. Robinson Varghese Marko Vrkljan
Prepared by Designed by Checked by Approved by Contarct No. : -----
Road Reserve Width
3m
1 in 10 Formation Width (14m)

2m 1.5m 3.5m 3.5m 1.5m 2m


Verge Shoulder Traffic Lane Traffic Lane Shoulder Verge
RRW

RRW
Catch Drain SIGN
BOARD
(Note 3)
RRW

RRW
6.0m

CL W-Beam (TL3)
Crash Barrier

4.0% 3.0% 3.0% Stone Masonry Wall/


4.0%
RRW

RRW
2.5m Toe Wall / Retaining Wall
RRW Pillar
@ 100m c/c

Stone Masonary/ Unlined Drain


Cement Concrete Wall (Note 3) GL

Existing Gravel Road Surface Wearing Course Unlined Drain


(Assumed as Subgrade top) Surface Course (Note 3)
Base Course
Sub base Course
Subgrade

TCS - 7
2 LANE CARRIAGEWAY WITH LEFT SIDE BREAST WALL
RIGHT SIDE STONE MASONRY WALL IN HILL / ROLLING SECTION

NOTES:-
1. All dimensions are in mm unless otherwise indicated.
2. The referred TCS is also applicable for Realignment
sections in which the New Construction is to be taken up.
3. Road side drainage shall be provided as per section 4.6 of AGRD 03 (2021)
4. Provision of batter slope shall be as follows:

Cut Fill
Type of Batter
Desirable Maximum Maximum Desirable Maximum Maximum
Earth batter 3:1 2:1 6:1 4:1
Rock batter 0.5:1 0.25:1 - -

5. In-situ subgrade material to be compacted prior to


construction of road pavement layers.
6. Details for Pavement Composition shall be as per Pavement design.

R0 April, 2024 Initial Drawings


Revisions Date Description Checked by

CLIENT: SCALE:- PROJECT TITLE: DRAWING TITLE: DT Global Asia Pacific


In Joint Venture with Revisions
Consultancy Services for Preparation of Feasibility Study and Detailed Intercontinental Consultants & Technocrats Pvt.Ltd,
Not to Scale A-8, Green Park, New Delhi - 110016 DRAWING NO. :
PNG Engineering Designfor Mountainous Road Improvement and Resilience TYPICAL CROSS SECTION OPTION ANALYSIS REPORT Ph : 011 4086-3000, Fax 2685-5252
TCS-7 ICT-DT-GAP/BUL-NAN /TCS/04/R0
S.Bhardwaj Vidyanand P. Robinson Varghese Marko Vrkljan
Prepared by Designed by Checked by Approved by Contarct No. : -----