1: WORK PLAN
Key Personnel
Environmental Specialist
Senior Survey Engineer
Senior Geo-Physicist
Task Duration (in Months)
Material Engineer
Senior Geologist
Utility Expert
Engineer
RESPONSIBILITIES Expert 1 2 3 4 5 6
STAGE-1 : INCEPTION REPORT AND QAP
P S S S S S S S S S S 101 Mobilization and Start-Up Meeting with the Client
P P P P P P P P S S P P P S 102 Study of All Available Reports, Data, Maps, Satellite Imageries etc.
S S S S P 204 Preliminary Topographic Survey Including Validating Reference Pillars / Bench Marks
Traffic Surveys Including Classified Volume Count, OD Survey, Axle Load, Turning movement, NMT,
S S 205
Willingness to Pay Survey, etc.
S S 206 Analysis of Traffic Data and Identification of Traffic Homogeneous Sections, Traffic Projections and Traffic Report
P P 218 Proposals for Service Roads, Junction Design and Wayside Amenities, etc.
P P 219 Preliminary Design of Toll Plaza, Weighing Stations, Parking Areas and Rest Areas
7-2
Team Leader cum Senior Tunnel
Engineer
Bridge/Structural Engineer
Tunnel Design Expert
Senior Geologist
Expert
Intermittent Task (As and When Required)
Senior Geo-Physicist
Material Engineer
S
Utility Expert
No.
Task
Secondary Responsibility
Description
7-3
1
2
3
4
Duration (in Months)
5
6
Key Personnel
Environmental Specialist
Senior Survey Engineer
Senior Geo-Physicist
Task Duration (in Months)
Material Engineer
Senior Geologist
Utility Expert
Engineer
Expert
RESPONSIBILITIES 1 2 3 4 5 6
P S S S P 226 Suggested Methods of Procurement and Packaging for BOT/PPP/Hybrid Annuity/EPC modes
S S P P P 303 Preparation of Clearance report to obtain clearances from forest, environment, tree cutting, railway and irrigation
S S P P P 306 Submission of Final LA & Clearances I Report incorporating Compliance of Client Comment
Geo-Technical Investigations and Sub-Soil Exploration for Tunnels, Viaducts/ Bridges and Structures and High
S S P P P 401
Embankments
Detailed Design of Road Geometry, Pavements, Vidaducts, CD Works, Bridges ,Grade Separators /
S P P 403
Underpasses etc.
Detailed Design of all Ancillary Road Works like Junctions, Service Roads, Toll Plazas, Drainage Measures,
S P 404
Traffic Safety Features, Road Signs / Markings and Way-Side Amenities, etc.
7-4
Key Personnel
Environmental Specialist
Senior Survey Engineer
Senior Geo-Physicist
Task Duration (in Months)
Material Engineer
Senior Geologist
Utility Expert
Engineer
Expert
RESPONSIBILITIES 1 2 3 4 5 6
P P P P S S S S P S S S S S 414 Draft Detailed Project Report and Drawings Along with Bidding Documents
P P P P S S S S P S S S S S 416 Final Detailed Project Report and Drawings Along with Bidding Documents
P S S P S S S 501 Preparation and Submission of Draft Technical Schedules For PPP / Hybrid Aunnuity / EPC Mode of Works
Submission of Technical Schedules and Other Relevant Procurement Documents Upon addressing Comments
P S S P S S S 504
and Observation of Client
S S P P 601 JMS Survey, preparation of 3D, LA report II with all information duly verified by CALA
S P S P 602 Preparation of Final Clearance Report after obtaining clearances from environment, forest, railway and irrigation
Preparation of Utility Report II containing final completion status, clearance, cost of shifting of utilities, drawings
S P S P P P 603
and approval of competent authority
S S P 701 Preparation of Land Acquisition Report III and Award Determination Report (3G)
Legend:
Continuous Task P Primary Responsibility
7-5
Team Leader cum Senior Tunnel
Engineer
Bridge/Structural Engineer
Tunnel Design Expert
Senior Geologist
Expert
Intermittent Task (As and When Required)
Senior Geo-Physicist
Material Engineer
S
Utility Expert
No.
Task
Secondary Responsibility
Description
7-6
1
2
3
4
Duration (in Months)
5
6
Key Personnel
Environmental Specialist
Senior Survey Engineer
Senior Geo-Physicist
Task Duration (in Months)
Material Engineer
Senior Geologist
Utility Expert
Engineer
Expert
RESPONSIBILITIES 1 2 3 4 5 6
DELIVERABLES
P P P P S S S S P S S S S S 1013 Draft Feasibility Study Report including Option Study Report including Draft 3(a) Report
Intermittent Task (As and When Required) S Secondary Responsibility Draft Feasibility Study Report
1. The bidding process assistance has been shown tentatively to be completed by end of 6 months which may vary as per Client's requirement Final LA & Clearances I Report
and programme.
Draft Detailed Project Report
2. The Client may consider to compensate separately the Consultant for the bidding process assistance services which may be decided during
negotiation stage meeting.
3. Monthly Progress Report shown here will be submitted on every 10th day of the following month which can be modified as per client
requirement. Draft Technical Schedules
Senior Geologist
Expert
Land Acquisition Expert
Senior Geo-Physicist
Material Engineer
Utility Expert
No.
Task
Description
7-8
1
2
3
4
Duration (in Months)
5
6
Project Clearances & LA IV Report