BILL OF QUANTITIES

WORK ITEM : OBRA CIVIL CONTRACTOR: CONSTRUCTORA NIVEL 17


PERIOD : Jul 25 to Ago 01 PAYMENT - ESTIMACION 6
PROJECT : BMC Monterrey ISSUE DATE : 2023.08.01
기 성 금 액 CONTENT OF PAYMENT
계약
구 분 Contract
전 회 up to PRE 금 회 This estimation 누 계 up to This 잔 여 Remaind 비 고
DESCRIPTION REMARK
금 액 MXN 금 액 amount % 금 액 amount % 금 액 amount % 금 액 amount %

기성 금액 WORKS DONE 2,401,162.29 454,084.50 99,645.85 553,730.35 1,847,431.94

ADICIONALES 120,621.00 86,809.70 86,809.70 33,811.30

선금금 공제 0.020% 50,000.00 25,000.00 5,000.00 30,000.00 20,000.00


RETENCION ANTICIPO

유보금 공제 5% 120,058.11 22,704.22 4,982.29 27,686.52 92,371.60


OTRAS RETENCIONES

6,031.05 4,340.49 4,340.49 1,690.57

기타공제 CONTRA CHARGES

합계 TOTAL AMOUNT 2,521,783.29 406,380.27 172,132.77 578,513.05 1,955,305.40

부가세 GST TAXES 403,485.33 65,020.84 27,541.24 92,562.09 312,848.86 CURRENCY: MXN

실지급액 NET PAYMENT 2,925,268.62 471,401.12 199,674.02 671,075.13 2,268,154.27

NOTES :

Concept Date
Contract Payment Remain
REALIZA REVISA AUTORIZA
Amount Amount % Amount %
Contract 2023.06.21 2,521,783.29 100.0%
ANTICIPO 2023.06.23 50,000.00 2.0%
ESTIMACION 1 2023.06.28 29,200.00 1.2%
ESTIMACION 2 2023.07.05 104,831.78 4.2%
/ / /
ESTIMACION 3 2023.07.10 142,430.69 5.6%
ESTIMACION 4 2023.07.19 70,716.81 2.8%
ESTIMACION 5 2023.07.25 59,201.00 2.3%
ESTIMACION 6 2023.08.01 172,132.77 6.8%

Total 2,521,783.29 628,513.05 24.9% 1,893,270.24 75.1%


BILL OF QUANTITIES

■ WORKS : TRABAJOS DE OBRA CIVIL ■ CONTRACT NO :


WORK ITEM : ■ PAYMENT NO. : ESTIMACION 6
■ COMPANY NAME : CONSTRUCTORA NIVEL 17 ■ ISSUE DATE : 2023.08.01
Currence / MXN

계 약 CONTRACT 전회 누계 'TIL PREVIOUS 금 회 THIS ESTIMATION 금회 누계 UP TO THIS 잔 여 REMAIN 비고


구 분 DESCRIPTION
Unit Q'ty U/P AMOUNT Q'ty AMOUNT % Q'ty AMOUNT % Q'ty AMOUNT % Q'ty AMOUNT % Remark

OBRA CIVIL

ZAPATA: Z-1

AFINE Y COMPACTACION DE FONDO DE EXCAVACION m2 647.15 $ 40.00 $ 25,886.00 538.18 $21,527.20 83.16% 96.12 $ 3,844.80 14.85% 634.30 $ 25,372.00 98.01% 12.85 $ 514.00 1.99%

PLANTILLA F'C:100 KG/CM2 A 5CM DE ESPESOR m2 479.15 $ 30.00 $ 14,374.50 360.14 $10,804.28 75.16% 96.12 $ 2,883.60 20.06% 456.26 $ 13,687.88 95.22% 22.89 $ 686.63 4.78%

CIMBRA DE MADERA m2 282.10 $ 170.00 $ 47,957.00 226.74 $38,544.95 80.37% 86.32 $ 14,674.40 30.60% 313.06 $ 53,219.35 110.97% - 30.96 -$ 5,262.35 -10.97%

ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 11383.68 $ 5.00 $ 56,918.40 11,114.29 $55,571.44 97.63% 2,116.00 $ 10,580.00 18.59% 13,230.29 $ 66,151.44 116.22% - 1,846.61 -$ 9,233.04 -16.22%
BILL OF QUANTITIES
ADICIONALES
■ WORKS : TRABAJOS DE OBRA CIVIL ■ CONTRACT NO :
WORK ITEM : ■ PAYMENT NO. : PAGO 1
■ COMPANY NAME : CONSTRUCTORA NIVEL 17 ■ ISSUE DATE : 2023.08.02
Currence / MXN

계 약 CONTRACT 전회 누계 'TIL PREVIOUS 금 회 THIS ESTIMATION 금회 누계 UP TO THIS 잔 여 REMAIN 비고


구 분 DESCRIPTION
Unit Q'ty U/P AMOUNT Q'ty AMOUNT % Q'ty AMOUNT % Q'ty AMOUNT % Q'ty AMOUNT % Remark

OBRA CIVIL

MURO PERIMETRAL Y BASCULA

TRAZO Y NIVELACION PARA ZAPATAS LOTE 1.00 $ 1,600.00 $ 1,600.00 0.70 $ 1,120.00 70.00% 0.70 $ 1,120.00 70.00% 0.30 $ 480.00 30.00%

AFINE Y COMPACTACION DE FONDO DE EXCAVACION PZA 25.00 $ 40.00 $ 1,000.00 17.50 $ 700.00 70.00% 17.50 $ 700.00 70.00% 7.50 $ 300.00 30.00%

ARMADO DE VARILLAS 3/8 20X20, CIMBRADO Y COLADO DE ZAPATAS PZA 25.00 $ 325.00 $ 8,125.00 17.50 $ 5,687.50 70.00% 17.50 $ 5,687.50 70.00% 7.50 $ 2,437.50 30.00%

ARMADO, CIMBRADO Y COLADO DE COLUMNAS ML 87.50 $ 230.00 $ 20,125.00 61.25 $ 14,087.50 70.00% 61.25 $ 14,087.50 70.00% 26.25 $ 6,037.50 30.00%
PROGRESS OF WORK
PHOTOGRAPHIC REPORT

OBRA : BMC MONTERREY ISSUE DATE : 2023.08.01


Contract Payment
Concept Date
Amount Amount %
Contract 2023.06.21 2,521,783.29 100.0%
ANTICIPO 2023.06.23 50,000.00 2.0%
ESTIMACION 1 2023.06.28 29,200.00 1.2%
ESTIMACION 2 2023.07.05 104,831.78 4.2%
ESTIMACION 3 2023.07.10 142,430.69 5.6%
ESTIMACION 4 2023.07.19 70,716.81 2.8%
ESTIMACION 5 2023.07.25 59,201.00 2.3%
ESTIMACION 6 2023.08.01 172,132.77 6.8%

Total 2,521,783.29 628,513.05 24.9%


Remain
Amount %

1,893,270.24 75.1%
Project BMC Department Construccion
Date of 2023.06.16 Orden para subcontratacion Orderer DONGKYU IM
Place OBRA Cell No 818 686 3492

CONSTRUCTORA NIVEL 17 Redinamica


No. Description Specification unit Q'ty
Unit price Amount Unit price Amount Unit price Amount
* Comparative quote amount from 3 Companies.
ZAPATA : Z-1 EA 70.00 35.00
AFINE Y COMPACTACION DE FONDO DE EXCAVACION m2 1,294.30 40.00 51,772.00 40.00 51,772.00 647.15
PLANTILLA F'C:100 KG/CM2 A 5CM DE ESPESOR m2 958.30 30.00 28,749.00 30.00 28,749.00 479.15
CIMBRA DE MADERA m2 564.20 170.00 95,914.00 170.00 95,914.00 282.10
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 22,767.36 5.00 113,836.80 5.00 113,836.80 11,383.68
COLADO DE CONCRETO PREMEZCLADO m3 437.26 80.00 34,980.40 80.00 34,980.40 218.63
- -
ZAPATA : Z-2 EA 87.00 43.50
AFINE Y CONPACTACION DE FONDO DE EXCAVACION m2 1,921.83 40.00 76,873.20 40.00 76,873.20 960.92
PLANTILLA F'C:100 KG/CM2 A 5CM DE ESPESOR m2 1,462.47 30.00 43,874.10 30.00 43,874.10 731.24
CIMBRA DE MADERA m2 791.70 170.00 134,589.00 170.00 134,589.00 395.85
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 34,610.69 5.00 173,053.44 5.00 173,053.44 17,305.34
COLADO DE CONCRETO PREMEZCLADO m3 692.74 80.00 55,419.00 80.00 55,419.00 346.37
- -
ZAPATA : Z-4 EA 10.00 5.00
AFINE Y CONPACTACION DE FONDO DE EXCAVACION m2 72.90 40.00 2,916.00 40.00 2,916.00 36.45
PLANTILLA F'C:100 KG/CM2 A 5CM DE ESPESOR m2 44.10 30.00 1,323.00 30.00 1,323.00 22.05
CIMBRA DE MADERA m2 24.00 170.00 4,080.00 170.00 4,080.00 12.00
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 1,004.64 5.00 5,023.20 5.00 5,023.20 502.32
COLADO DE CONCRETO PREMEZCLADO m3 9.00 80.00 720.00 80.00 720.00 4.50
- -
DADO : D-1 EA 69.00 34.50
AFINE Y CONPACTACION DE FONDO DE EXCAVACION m2 333.96 40.00 13,358.40 40.00 13,358.40 166.98
PLANTILLA F'C:100 KG/CM2 A 5CM DE ESPESOR m2 176.64 30.00 5,299.20 30.00 5,299.20 88.32
CIMBRA DE MADERA m2 165.60 170.00 28,152.00 170.00 28,152.00 82.80
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 6,703.49 5.00 33,517.44 5.00 33,517.44 3,351.74
COLADO DE CONCRETO PREMEZCLADO m3 41.40 80.00 3,312.00 80.00 3,312.00 20.70
RELLENO CON MATERIAL PRODUCTO DE LA EXCAVACION Y
COMPACTACION
m3 200.38 130.00 26,048.88 130.00 26,048.88 100.19

- -
PEDESTAL : P-1 EA 72.00 36.00
CIMBRA DE MADERA m2 322.56 170.00 54,835.20 170.00 54,835.20 161.28
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 9,075.02 5.00 45,375.12 5.00 45,375.12 4,537.51
COLADO DE CONCRETO PREMEZCLADO m3 62.24 80.00 4,979.52 80.00 4,979.52 31.12
RELLENO CON MATERIAL PRODUCTO DE LA EXCAVACION Y m3 2,729.12 130.00 354,786.12 130.00 354,786.12 1,364.56
COMPACTACION
- -
PEDESTAL : P-2 EA 99.00 49.50
CIMBRA DE MADERA m2 388.08 170.00 65,973.60 170.00 65,973.60 194.04
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 10,340.95 5.00 51,704.73 5.00 51,704.73 5,170.47
COLADO DE CONCRETO PREMEZCLADO m3 64.80 80.00 5,183.64 80.00 5,183.64 32.40
RELLENO CON MATERIAL PRODUCTO DE LA EXCAVACION Y
COMPACTACION
m3 4,483.17 130.00 582,811.52 130.00 582,811.52 2,241.58

- -
PEDESTAL : P-3 EA 10.00 5.00
CIMBRA DE MADERA m2 30.80 170.00 5,236.00 170.00 5,236.00 15.40
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 536.40 5.00 2,682.00 5.00 2,682.00 268.20
COLADO DE CONCRETO PREMEZCLADO m3 4.83 80.00 386.10 80.00 386.10 2.41
RELLENO CON MATERIAL PRODUCTO DE LA EXCAVACION Y
COMPACTACION
m3 149.45 130.00 19,427.85 130.00 19,427.85 74.72

- -
VIGA : TC-1 M 361.25 180.63
AFINE Y CONPACTACION DE FONDO DE EXCAVACION m2 325.13 40.00 13,005.00 40.00 13,005.00 162.56
PLANTILLA F'C:100 KG/CM2 A 5CM DE ESPESOR m2 180.63 30.00 5,418.75 30.00 5,418.75 90.31
CIMBRA DE MADERA m2 433.50 170.00 73,695.00 170.00 73,695.00 216.75
INSTALACION DE CHAFLAN m 361.25 10.00 3,612.50 10.00 3,612.50 180.63
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 13,416.83 5.00 67,084.13 5.00 67,084.13 6,708.41
COLADO DE CONCRETO PREMEZCLADO m3 65.03 80.00 5,202.00 80.00 5,202.00 32.51
RELLENO CON MATERIAL PRODUCTO DE LA EXCAVACION Y
COMPACTACION
m3 65.03 130.00 8,453.25 130.00 8,453.25 32.51

AFINE DE MUROS A BASE DE MORTERO m2 108.38 95.00 10,295.63 95.00 10,295.63 54.19
- -
MURO CONTENCION : MC-1 M 86.10 43.05
AFINE Y CONPACTACION DE FONDO DE EXCAVACION m2 154.98 40.00 6,199.20 40.00 6,199.20 77.49
PLANTILLA F'C:100 KG/CM2 A 5CM DE ESPESOR m2 86.10 30.00 2,583.00 30.00 2,583.00 43.05
CIMBRA DE MADERA m2 284.13 170.00 48,302.10 170.00 48,302.10 142.07
INSTALACION DE CHAFLAN m 86.10 10.00 861.00 10.00 861.00 43.05
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 2,388.07 5.00 11,940.35 5.00 11,940.35 1,194.03
COLADO DE CONCRETO PREMEZCLADO m3 210.95 80.00 16,875.60 80.00 16,875.60 105.47
RELLENO CON MATERIAL PRODUCTO DE LA EXCAVACION Y
COMPACTACION
m3 127.86 130.00 16,621.61 130.00 16,621.61 63.93

impermeavilizante m2 111.93 35.00 3,917.55 35.00 3,917.55 55.97


AFINE DE MUROS A BASE DE MORTERO m2 103.32 95.00 9,815.40 95.00 9,815.40 51.66
- -
MURO CONTENCION : MC-2 M 62.80 31.40
AFINE Y CONPACTACION DE FONDO DE EXCAVACION m2 106.76 40.00 4,270.40 40.00 4,270.40 53.38
PLANTILLA F'C:100 KG/CM2 A 5CM DE ESPESOR m2 56.52 30.00 1,695.60 30.00 1,695.60 28.26
CIMBRA DE MADERA m2 188.40 170.00 32,028.00 170.00 32,028.00 94.20
INSTALACION DE CHAFLAN m 125.60 10.00 1,256.00 10.00 1,256.00 62.80
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 1,300.34 5.00 6,501.68 5.00 6,501.68 650.17
COLADO DE CONCRETO PREMEZCLADO m3 138.16 80.00 11,052.80 80.00 11,052.80 69.08
RELLENO CON MATERIAL PRODUCTO DE LA EXCAVACION Y m3 84.78 130.00 11,021.40 130.00 11,021.40 42.39
COMPACTACION
AFINE DE MUROS A BASE DE MORTERO m2 62.80 95.00 5,966.00 95.00 5,966.00 31.40
- -
MURO CONTENCION : MC-3 M 118.65 59.33
AFINE Y CONPACTACION DE FONDO DE EXCAVACION m2 201.71 40.00 8,068.20 40.00 8,068.20 100.85
PLANTILLA F'C:100 KG/CM2 A 5CM DE ESPESOR m2 106.79 30.00 3,203.55 30.00 3,203.55 53.39
CIMBRA DE MADERA m2 320.36 170.00 54,460.35 170.00 54,460.35 160.18
INSTALACION DE CHAFLAN m 237.30 10.00 2,373.00 10.00 2,373.00 118.65
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 3,008.96 5.00 15,044.82 5.00 15,044.82 1,504.48
COLADO DE CONCRETO PREMEZCLADO m3 261.03 80.00 20,882.40 80.00 20,882.40 130.52
RELLENO CON MATERIAL PRODUCTO DE LA EXCAVACION Y
COMPACTACION
m3 160.18 130.00 20,823.08 130.00 20,823.08 80.09

impermeavilizante m2 94.92 35.00 3,322.20 35.00 3,322.20 47.46


AFINE DE MUROS A BASE DE MORTERO m2 121.02 95.00 11,497.19 95.00 11,497.19 60.51
- -
Dock Leveler Pit EA 4.00 2.00
PLANTILLA F'C:100 KG/CM2 A 5CM DE ESPESOR m2 29.37 30.00 880.99 30.00 880.99 14.68
CIMBRA DE MADERA m2 50.75 170.00 8,626.75 170.00 8,626.75 25.37
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 1,491.43 5.00 7,457.17 5.00 7,457.17 745.72
COLADO DE CONCRETO PREMEZCLADO m3 16.08 80.00 1,286.14 80.00 1,286.14 8.04
- -
Rampa (Dock area) M2 86.78 43.39
AFINE Y CONPACTACION DE FONDO DE EXCAVACION m2 86.78 40.00 3,471.20 40.00 3,471.20 43.39
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 1,815.09 5.00 9,075.45 5.00 9,075.45 907.55

COLADO DE RAMPA, ACABADO INCLUYE ANTIDERRAPANTE m2 86.78 45.00 3,905.10 45.00 3,905.10 43.39

- -
Rampa (Comp. Room/Factory Entrance) M2 36.96 18.48
AFINE Y CONPACTACION DE FONDO DE EXCAVACION m2 36.96 40.00 1,478.40 40.00 1,478.40 18.48
ARMADO Y COLOCACION DE VARILLA DE REFUERZO kg 773.06 5.00 3,865.28 5.00 3,865.28 386.53

COLADO DE RAMPA, ACABADO INCLUYE ANTIDERRAPANTE m2 36.96 45.00 1,663.20 45.00 1,663.20 18.48

- -
GOUTH DE COLUMNA ea 250.00 150.00 37,500.00 150.00 37,500.00 125.00
- - 0.00
PISO H:300 M2 6,850.67 3,425.34

ARMADO Y COLOCACION DE VARILLA DE REFUERZO DE PISO kg 57,545.63 4.50 258,955.33 4.50 258,955.33 28,772.81

- -
PISO H:200 M2 7,665.90 3,832.95

ARMADO Y COLOCACION DE VARILLA DE REFUERZO DE PISO kg 80,169.98 4.50 360,764.92 4.50 360,764.92 40,084.99

- -
PISO H:150 M2 7,665.90 3,832.95
COLOCACION DE MALLA ELECTROSOLDADA m2 7,665.90 13.00 99,656.70 13.00 99,656.70 3,832.95
- - 0.00
PISO DE MEZZANINE M2 6,612.67 - - 3,306.34
COLOCACION DE MALLA ELECTROSOLDADA m2 6,612.67 13.00 85,964.71 13.00 85,964.71 3,306.34
- -
COLOCACION BLOCK CARA DE PIEDRA H: 0~3M m2 429.73 140.00 60,161.92 140.00 60,161.92 214.86
CERRAMIENTO 20CM X 20CM ml 537.16 $ 150.00 $ 80,574.00 $ 150.00 $ 80,574.00 268.58
CASTILLO 20CM X 20CM ml 50.00 $ 150.00 $ 7,500.00 $ 150.00 $ 7,500.00 25.00
SARPEO Y AFINE DE MORTERO H: 0~3M m2 429.73 130.00 55,864.64 130.00 55,864.64 214.86
- -
VIALIDAD DE CONCRETO H:250 M2 7,874.90 3,937.45
COLOCACION DE MALLA ELECTROSOLDADA m2 7,874.90 13.00 102,373.70 13.00 102,373.70 3,937.45
- -
CORDON m 1,253.48 130.00 162,952.40 130.00 162,952.40 626.74
BANQUETA DE CONCRETO m2 910.62 170.00 154,805.40 170.00 154,805.40 455.31
- -
OFICIAL día 300.00 $ 800.00 $ 240,000.00 $ 800.00 $ 240,000.00 150.00
AYUDANTE día 600.00 $ 600.00 $ 360,000.00 $ 600.00 $ 360,000.00 300.00
MUCHACHA (LIMPIEZA) día 100.00 $ 500.00 $ 50,000.00 $ 500.00 $ 50,000.00 50.00

$ 4,802,324.57 $ 4,802,324.57
1.- Estos precios son para los proyectos de MMEXC WINNER EXECUTION TIME Attached document
2.- Se deberá entregar alta y baja de Siroc

Supplier 3.- Personal que trabaje en Altura deberá de contar con IMSS se les pedirá el SUA y el Alta del personal durante los proyectos CONSTRUCTORA
Redinamica 26 de Septiembre al 30 de Abril
conditions NIVEL 17
4.- Pago Quincenal
5.- Anticipo $50,000 por contratista

Residente Gerente
Remark Reviewed by
BMC MONTERREY
CONSTRUCTORA NIVEL 17
CATALOGO DE MURO PERIMETRAL Y BASCULA

No. Description Specification unit Q'ty Unit price Amount

1.1 TRAZO Y NIVELACION PARA ZAPATAS LOTE 1 $1,600.00 $1,600.00

1.2 AFINE Y COMPACTACION DE FONDO DE EXCAVACION PZA 25 $40.00 $1,000.00

ARMADO DE VARILLAS 3/8 20X20, CIMBRADO Y COLADO DE


1.4
ZAPATAS PZA 25 $325.00 $8,125.00

1.5 ARMADO, CIMBRADO Y COLADO DE COLUMNAS ML 87.5 $230.00 $20,125.00

1.6 RELLENO Y COMPACTACION PARA ZAPATAS 1X1 M3 37.14 $150.00 $5,571.00

COLOCACION DE DALA PARA BARDA PERIMETRAL, INCLUYE


1.7
EXCAVACION Y PERFILADO ML 145 $210.00 $30,450.00

COLOCACION DE MOLDURAS EN COLUMNAS, INCLUYE


1.8
ARMADO Y CIMBRADO PZA 25 $550.00 $13,750.00

FABRICACION DE BASCULA, INCLUYE HERRAMIENTA Y MANO


1.9
DE OBRA LOTE 1 $40,000.00 $40,000.00

SUBTOTAL $120,621.00
IVA $19,299.36
TOTAL $139,920.36
DATOS FISCALES

CONSTRUCTORA NIVEL 17 SA DE CV
RFC: CND170328NX6
RIGIMEN FISCAL: 601
DIRECCIÓN : CALLE 1RA. AVENIDA, NO. 545 INT B CP 29000
CHP, MEX.

DATOS BANCARIOS
BANREGIO
CUENTA: 054904780017
CLABE: 058580549047800173