MEETINGS FOR WEEKLY WORK OF 06/08 TO 12/08

ALL COLUMNS DHOULD BE CASTED


SILO BACKFILING WILL BE DONE

10 NOS OF COPLA WILL BE FIXED WITH INSERT PLATE

G GRID 4 NOS OF COLUMN WILL BE CASTED WITHIN 08/08


MAIN SHED 38 FOOTINGS WILL BE CASTED

40 NOS OF COLUMNS WILL BE CASTED

50% OF PB STAGING WILL BE DONE


RMB1 50% OF PB CASTING WILL BE DONE

5 NOS OF COLUMN ABOVE PB WILL BE CASTED

ALL FOOTINGS WILL BE CASTED


RMB5 12 NOS OF COLUMN

16 NOS OF CAP FIXING WILL BE DONE

ST2 SLAB CASTING


SLURRY TANK
ST5 SLAB SHUTTERING + R/F WORK WILL BE DONE

50% OF PB STAGING WILL BE DONE


COALBIN 40M BEAM BOTTOM WILL BE LAID

20M R/F FIXING WILL BE DONE


RAFT CASTING WILL BE DONE

GASIFIER 8 COLUMN WILL BE CASTED

TANK EXCAVATION SHOULD'BE STARTED

ALL FOOTINGS WILL BE CASTED


BALL MILL
20 NOS OF COLUMN WILL BE CASTED