Professional Documents
Culture Documents
ENG PHEARUM
(201906279)
To
on
Dissertation Supervisor
大连理工大学
Dalian University of Technology
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
大连理工大学学位论文独创性声明
作者郑重声明:所呈交的学位论文,是本人在导师的指导下进行研究
工作所取得的成果。尽我所知,除文中已经注明引用内容和致谢的地方
外,本论文不包含其他个人或集体已经发表的研究成果,也不包含其他已
申请学位或其他用途使用过的成果。与我一同工作的同志对本研究所做的
贡献均已在论文中做了明确的说明并表示了谢意。
若有不实之处,本人愿意承担相关法律责任。
作 者 签 名: 日期:2023 年 07 月 12 日
Dissertation submitted for Master Degree of Dalian University of Technology
Dissertation Title: Numerical Analysis of Columns Shortening on the Response of High- rise
Concrete Buildings.
I
Dissertation submitted for Master Degree of Dalian University of Technology
Abstract
In a high-rise building, the axial deformation of columns cannot be ignored and must
be considered as particular deliberation is required for design and construction. A vertical
member undergoes both elastic and inelastic deformation due to creep and shrinkage. Elastic
deformation occurs instantaneously due to dead loads and live loads applied to the structure,
while deformation due to creep and shrinkage occurs over many years. Most of the vertical
deformation in a high-rise building, however, takes place during its construction.
Due to the difference in axial stiffness and load distribution area on vertical members,
difference shortening inevitably develops. The accurate prediction of vertical elements (i.e,
columns, walls) shortening is required to determine their effects on other structural and
nonstructural elements, which are usually overestimated by linear elastic analysis. Its
adequacy was assessed by comparison of the results for a tall concrete building with those
obtained with commercial software incorporating a nonlinear staged construction analysis
package.
This research presents a set of guidelines so that the effect could be considered
approximately, especially at the preliminary design stage and during the construction phase.
In addition, this study it’s assumed, construction stages analysis considers the creep and
shrinkage effects of a 54-story building consisting of an exterior and interior wall.
In addition, it is carried out using the numerical computation method and the
numerical model will be validated using the results of structural modeling design and
analysis. In order to limit the scope of the research, the study focuses on a high-rise building
with high-strength reinforced concrete columns and core walls where differential axial
shortening problems can be aggravated. The displacement of vertical members is evaluated
and compared with results from nonlinear analysis (construction stages).
As the result, the differential axial shortening between successive floors must be
considered in the façade. As well as, the percentage difference in base reaction between the
nonlinear staged construction analysis case (long-term axial shortening) and load combination
(self-weight + super-imposed dead load + 50% of live load) is approximately 0.00% which is
confirming that all loads have been already considered in nonlinear staged construction
analysis.
Moreover, the differential axial shortening between the core wall and the peripheral
columns must be considered in the design, the proportion of the deformation due to creep and
shrinkage that contribute to the total amount of deformation is 65.80%-75.19% for the column
and 70.40% - 82.10% for the shear wall. Therefore, deformation due to creep and shrinkage
must be considered.
II
Dissertation submitted for Master Degree of Dalian University of Technology
Keywords: High-rise building; deformation; Creep and shrinkage effects; Stage construction
analysis; Load-time history; Analysis for column shortening.
Tabble of Contents
Abstract................................................................................................................................................
Chapter 1. Introduction................................................................................................................
2.1 Introduction..........................................................................................................................
2.2 High-rise Building...............................................................................................................
2.2.1 Procedure of Performance-based Design.......................................................- 9 -
2.2.1.1 Basis of Design..............................................................................................- 10 -
2.2.1.2 Geotechnical Investigation Report...................................................................- 10 -
2.2.1.3 Site-specific Probabilistic seismic Hazard Assessment Report....................- 11 -
2.2.1.4 Wind Tunnel.................................................................................................- 11 -
2.3 Theoretical Background of Elastic Deformation in Concrete............................................
2.3.1 Creep Deformation in Concrete...................................................................- 11 -
2.3.2 Factor affecting Creep of Concrete..............................................................- 12 -
2.3.3 Aggregate.....................................................................................................- 12 -
2.3.4 Cement........................................................................................................- 13 -
2.3.5 Water to Cementitious Ratio.......................................................................- 13 -
2.3.6 Chemical Admixtures..................................................................................- 13 -
2.4 Stress-Strength Ratio at Loading.......................................................................................
2.4.1 Age at Loading............................................................................................- 14 -
2.4.2 Size Effect...................................................................................................- 14 -
2.4.1 Curing Conditions.......................................................................................- 15 -
2.4.2 Relative Humidity.......................................................................................- 15 -
III
Dissertation submitted for Master Degree of Dalian University of Technology
3.1 Introduction........................................................................................................................
3.2 Other Factors influencing in High-rise Buildings..............................................................
3.2.1 Current trends in concrete construction......................................................- 26 -
IV
Dissertation submitted for Master Degree of Dalian University of Technology
References - 63 -
Appendix A Collected accumulative long-term (LT) axial shortening for columns and walls
after 50 years..................................................................................................................................
Appendix B Differential long-term axial shortening between successive floors after 50 years
(Façade design)..............................................................................................................................
Appendix C....................................................................................................................................
Appendix D....................................................................................................................................
Publications during Masters Study................................................................................................
Acknowledgment...........................................................................................................................
VI
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Chapter 1. Introduction
1.1 Background of the Master's Thesis Topic
The idea of a tall building has always been an exciting one for mankind. Towards the
end of the 19th century, the construction of the tall building started in Chicago due to new
inventions such as the elevator and the telephone [1]. Since the first appearance of high-rise
buildings, there has been a transformation in their design and construction. The trends in the
tall building have been discussed by Parker and Wood (2013). According to the council on
tall building and urban habitat, buildings of 14 stories or 50 meters in height and are could be
considered as "Tall buildings"; buildings of 3000 meters and 600 meters height and above are
classified as "super-tall buildings" and "megamall buildings" respectively [2]. The council has
accordingly indicated the following ranges of building height:
200-300 m: tall building
300-600 m: super-tall buildings
> 600 m: mega tall buildings
In 2016, over 100 super-tall buildings and 2 mega tall buildings were fully completed
and occupied globally.
(a)
1
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Number of 200m + buildings Number of 200m + buildings, minimum Projected 200m + buildings completion range,
minimum
Number of supertalls (300m +) Number of supertalls (300m +), Projected supertalls (300m +) completion range,
minimum minimum
Number of megamalls (600m +) Number of megamalls (600m +), Projected megamalls (600m +) completion, minimum
minimum
2
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
meters or higher completed ear year since 1960 (Fig 1.2) shows a steady build-up during the
1990s, followed by exponential growth from the mid-2000s onwards. Although there has been
a very definite drop-in skyscraper activity in most western countries recently due to the global
numbers completed during 2012 compared to the year previously), in the longer term, this is
generally being offset by activity in Asia-and China specifically: now expect the global
number of a tall building completed in Fig 1.2. Tall buildings completed each year over 200
meters, 300 meters, and 600 meters since 1960.
The inset shows the total number of completed buildings by decade, revealing
exponential growth [2]. 2013-2014 building completion are predicted from a project in the
advanced constructor; total after 2001 consider the destruction of the world trade center
towers 1 and 2. Each year to keep climbing for the foreseeable future. It’s also worth noting
that although there was a dip in the number of building completions in 2012 relative to the
year previous, 2012 still saw the third-highest number of tall building completions over 200
meters in history.
The detailed statistics are quite staggering. At the time of writing (January 2013),
some 56 of the current 100 tallest building buildings in the world have been completed since
the end of 2005. In addition, a further 24 buildings are expected to enter the list by the end of
2013, which will translate into a 68 percent change in the “world’s 100 Tallest” in just eight
years (this change takes into account those building completed since 2005, but subsequently
pushed out of the list by newer, taller buildings). To translate statistics into the actual building
Fig 1.3 shows the current 20 tallest buildings in the world. Of these, eleven have been
completed since the end of 2005-55 percent.
3
Fig. 1.3 Diagram of the world’s tallest 20 building according to the CTBUH height
criterion of “height to architectural top” [2]
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
The tall building is indisputably getting taller, in terms both of the tallest and of the
global average height. As the graph on the average height of the world’s 100 tallest buildings
over the past eight decades (Fig 1.4 overleaf) shows, the average height has more than
doubled in that time and increased by 13 percent in the period 2000-2010 alone. At the
“world’s tallest” (see Fig 1.5 overleaf) any building surpassed its predecessor by more than 68
meters, but Buji Khalifa achieved a leap of an unprecedented 320 meters over the previous
world’s tallest, Taipei 101. The total height of the Burj Khalifa is just five meters shy of the
equivalent height of putting the Empire State Building on top of Petronas Towers (both
formerly the “world’s tallest” buildings).
Trend 3: A change in location
The predominant location of the tallest buildings in the world has been changing
rapidly. whereas as recently as 1990, 80 of the “world’s 100 tallest” were located in North
America, now that Fig is only 23, with the shift predominantly to Asia (45, with 31 in China
alone), and the middle east (27, with 20 in Dubai alone).
4
Fig.1.3.1b Structural material of the world’s tallest buildings.
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
5
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
70
60
50
40
20
1930
1990
2000
2010
2012
1940
1950
1960
1980
1970
100
80
60
40
20
0
1930
1990
2000
2010
2012
1940
1950
1960
1970
1980
Office Mixed-use
Hotel Residential
6
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
100
80
60
40
20
1930
1990
2000
2010
2012
1940
1950
1960
1970
1980
Mixed Residential
Fig.1.3.5 100 tallest building by structural material, 1930-2012 .
Trend 5: A change in structural material: The revolution in structural material has also been
very significant over the past few decades. The proportion of all-steel structure building in the
‘100 tallest’ list has fallen from 90 percent as recently as 1970 to just 17 percent, shifting in
favor of concrete or composite structures as shown in Fig. 1.3.5.
7
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
partitions and the façade of buildings or column cladding and thus reducing the functionality
of the structure.
1.3 Research objectives
Today, the prediction of shortening and shortening effectiveness is most effectively
achieved using advanced structural analysis software. However, it is vital to understand the
behavior of the software and the types of analysis options available as compared with the
physical behavior of the actual building. It is also helpful and recommended to estimate the
anticipated shortening amounts and validate the results from the analysis software.
The leading cause of vertical shortening in a tall building is the compression of
vertical elements under the load they carry. This is known as elastic shortening. In reinforced
concrete buildings, creep, and shrinkage of the concrete cause additional shortening of
vertical elements beyond the elastic shortening. Foundation settlement and deflection of
structural transfer technically are not shortening of vertical elements. Their effects should be
considered where appropriate.
1.4 Scope of Research
This research is carried out using the numerical computational method. The numerical
model will be validated using the results of structural modeling design and analysis. In order
to limit the scope of the research, the study focuses on high-rise buildings with high-strength
reinforced concrete columns and reinforced concrete shear cores where the differential axial
shortening problem can be aggravated. The system of high-rise buildings resists the lateral
Cross section
Elastic
strain
Load effect
Creep strain
Shrinkage
strain Differential shortening
Thermal strain
strain
and gravity load. This research will verify a comprehensive method to quantify the
differential axial shortening of t a high-rise building with reinforced concrete columns as
shown in Fig. 1.4.
Chapter 2. Literature Review
2.1 Introduction
Tall buildings present unique challenges in terms of both design and construction.
Their sheer scale demands that particular attention is paid simultaneously to strategic and
detailed issues. Tall building design and construction require an integrated approach, with the
need for various engineering disciplines to coexist efficiently from the beginning of the
project. This multi-disciplinary approach extends to consideration of how the building will be
constructed and thus ideally involves an integrated team (including construction and design
professionals) at the earliest stage of the project.
The definition of “tall” of a building is not absolute. It’s understood here as when the
geometry of the building, for example, overall height or height-to-minimum-plan dimension,
significantly influences aspects of the design. These aspects are:
One definition is that if the building aspect ratio, height divided by the lowest overall
lateral dimension, is more than 5:1, then the building may be considered tall. For consistency,
this document will refer to tall buildings in preference to other common terms including
‘skyscraper’, ‘high-rise’, or ‘tower’, except for sections describing historical context. The
term ‘tall’ may also be sub-divided as follows:
10
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
11
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Allowable bearing capacity (factor to increase in capacity for transient loads and stress
peaks)
Sub-grade modulus (vertical and lateral)
Pile foundation
→ Ultimate end bearing pressure vs. pile length
→ Ultimate skin friction pressure vs. pile length
→ Allowable bearing capacity
→ Allowable pullout capacity
→ Basement wall pressure
12
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
and the environment. Drying creep is the additional creep due to moisture movement between
the specimen and the environment. Fig. 2.3.1 shows the relation of deformation of concrete
after loading application with time.
Elastic shortening
2.3.3 Aggregate
Aggregates play an important role in the creep of concrete. Aggregate provides a
restraining effect on creep [6]. Generally, higher aggregate content results in lower creep. It
proposed an equation to indicate the relation between aggregate content and creep shown
below:
(2.3)
13
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
(2.4)
where:
cp is the creep of neat cement paste
c is the creep of concrete
g is the aggregate content
µ is Poisson’s ratio of concrete
µα is Poisson’s ratio of aggregate
E is the modulus of elasticity of concrete
Eα is the modulus of elasticity of aggregate
According to the study by Neville [6], for concrete specimens loaded at 14 days with a
stress-strength ratio of 0.5 stored in 90% relative humidity condition, a linear relationship was
obtained and after 28 days of loading for basic creep. The magnitude was
based on the age of initial loading and the change of modulus of elasticity of concrete with
time after loading application. A similar observation was made by Polivka [7] for both basic
creep and drying creep of concrete.
2.3.4 Cement
Cement paste is the base of the creep phenomenon, so cement has a great influence on
the creep of concrete. According to Neville [6], it was observed that creep was inversely
proportional to the rate of hardening of the cement. It was logical that the higher rate of
hardening of cement, the more hydrated cement, and the restraining effect on creep.
Typically, the concrete with rapid-hardening portland (type III) cement results in lower creep
than the concrete with standard portland (type I) cement for both dry-stored and wet-stored
conditions [8], which was due to the higher strength of type II portland cement concrete at the
age of loading compared with type I cement concrete.
14
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
trend was found, and the ultimate specific creep with a w/c ratio of o.4 was approximately
10% higher than with a w/c ratio of 0.3.
2.3.6 Chemical Admixtures
Mineral admixture, including ground granulated blast furnace slag (GGBFS), fly ash,
and silica fume, are widely used as a partial replacement for Portland cement in high-
performance concrete. It is a glassy material with cementitious property formed when molten
blast-furnace slag is rapidly cooled, such as by immersion in water, and slag mainly consists
of silicates and aluminosilicate of calcium [10]. Fly ash is a by-product of coal combustion with
both pozzolanic and cementitious properties [11].
2.4 Stress-Strength Ratio at Loading
According to a wide range of investigations [6], creep is proportional to the applied
stress and inversely proportional to the strength at the time of application of load. Although
some other research indicated a higher upper limit of stress-strength ratio to 0.75 or 0.80,
generally the upper limit was approximately 0.60. In the study by Jones and Richart [16], the
measured creep of concrete specimens was proportional with a stress-strength ratio up to 0.6,
and beyond this limit creep increased more quickly than the increase of applied stress.
Similar behavior of concrete was observed for concrete specimens with different
stress-strength ratios and different initial applications of load [12]. According to the study by
L’Hermite and Mamilla [13], the linear relation was obtained for concrete stored in water
initially at 7 days, 35 days, 70 days, 1 year, and 5.5 years. In the study by Haranki [14], the
linear limit was 0.5 for high-performance concrete after the loading of 91 days. The linear
limit for creep in compression is 40% of concrete compressive strength [15].
2.4.1 Age at Loading
The same concrete loaded at different ages undergoes a different growth in strength,
so for the constant applied stress, creep depends on the age at loading. The strength of the
younger concrete is lower, and the creep is higher, and the older concrete has the opposite
characteristics. In the study by Yashin [17], it was found that when the strength gain of concrete
was smaller the creep was higher. Another study confirmed this behavior, and for the same
concrete, 18% higher creep was obtained for the concrete loaded at 1 day than 3 days after the
loading of 28 days [7].
Loading age effect on creep was also observed by Bryant [18] for both unsealed and
sealed specimens, and the earlier loading the higher creep. In the study by Khan [19], the effect
of age of loading on creep for normal concrete, medium concrete, and high-strength concrete
was investigated. It was found that the creep of high-strength concrete was more sensitive to
the early age of loading than that of normal and medium concrete.
15
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
16
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
(2.5)
This equation is applicable for both 1-3 days steam cured concrete and 7-days moist-cured
concrete.
where:
t is days after loading
vt is the creep coefficient after t days of loading
(2.6)
in which:
γta is a correction factor for loading age, which is defined as:
(2.7)
for loading ages later than 7 days for moist cured concrete
(2.8)
for loading ages later than 1-3 days for steam-cured concrete
γλ is the correction factor ambient relative humidity, which is defined as:
for (2.9)
where the relative humidity is the percent
17
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
γvs is the correction factor average thickness of member or volume-to-surface ratio. When
the average thickness of the member is other than 150 mm or the volume-to-surface
ratio is other than 38 mm.
2.5.2 ACI-Modified by Huo (2001)
This model is the same as ACI 209-90 [24], and an additional modification factor for
compressive strength is considered:
(2.10)
where:
is a correction factor for the compressive strength of concrete
(2.11)
'
f c is 28-day compressive strength.
2.6 Shrinkage of Concrete
2.6.1 Introduction
Shrinkage is the decrease in the volume of hardened concrete with time. Shrinkage of
hardened concrete is divided into drying shrinkage and carbonation shrinkage [5]. Drying
shrinkage is caused by moisture loss in the concrete. Autogenous shrinkage (or basic
shrinkage or chemical shrinkage) is due to the hydration of cement. Autogenous shrinkage
typically is negligible in concrete with a higher water performance concrete [27].
Carbonation shrinkage results from the carbonation of cement hydration products in
the presence of carbon dioxide. Bazant (2000) found that good concrete carbonation occurs
only in the surface layer with a thickness of serval millimeters, so the carbonation shrinkage
in negligible. This was confirmed by Person [29] and Malhotra [30]. For high-performance
concrete used for prestressed bridge girders, carbonation shrinkage is negligible compared
with drying shrinkage and autogenous shrinkage.
2.6.1 Factor Affecting Shrinkage of Concrete
Shrinkage of concrete is influenced by an intrinsic and extrinsic factor similar to
creep. The intrinsic factor contains the proportions and properties of mixtures. Extrinsic factor
consists of the size of the concrete, age of concrete exposure to the ambient condition, curing
conditions, ambient temperature, and relative humidity after exposure.
2.6.2 Aggregate
Aggregate has a significant effect on the shrinkage of concrete. Aggregate provides
the restraining effect of shrinkage [6], and the more aggregate the higher the restraining effect
18
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
and the lower shrinkage. Pickett [31] proposed an equation to describe the effect of aggregate
content on the shrinkage of concrete:
19
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
20
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
It was indicated that steam curing increased the initial shrinkage of concrete
significantly, and decreased the rate of shrinkage at later ages. According to the study, it was
found that concretes with 14-day moist curing had smaller shrinkage under drying conditions
compared with concretes with 7-day moist curing, which was due to the higher maturity of
concrete under 14-days moist curing [14].
(2.13)
shrinkage after 7 days for moist cured concrete
(2.14)
shrinkage after 1-3 days for steam-cured concrete
where:
t is days after the end of the initial wet curing
(εsh)u is the ultimate shrinkage strain, and the average value suggested for
(2.15)
γsh is a correction factor for conditions other than the standard concrete composition
which is defined as:
(2.16)
in which:
21
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
(2.17)
where λ, is the relative humidity in percent
(2.18)
where λ, is the relative humidity in percent
γvs is a correction factor for the average thickness of member or volume-to-surface
ratio. when the average thickness of the member is other than 150 mm or the volume-to-
surface ratio is other than 38 mm, two methods are offered.
(a) Average Thickness Method
For the average thickness of members less than 150 mm, the factors are given in Tab
2.2.5.1 in ACI 209R-92[5]. For the average thickness of members greater than 15mm and up to
about 300-380 mm, the equation is given:
, (2.19)
during the first year after loading.
(2.20)
where h, is the average thickness of the member in inches and it’s for ultimate value.
(b) Volume-surface ratio method
For members with volume-to-surface area other than 38 mm, the equations are given:
(2.21)
where v/s, is the volume-surface ratio in inches.
γs is a correction factor for the slump, and equations are given as:
(2.22)
where, s, is the observed slump in inches.
γp is a correction factor for fine aggregate percentage, which is defined as:
(2.23)
where ρ ≤ 50 is percent.
(2.24)
where ρ>50 is percent.
where ρ is the ratio of the fine aggregate to the total aggregate by weight expressed as a
percentage.
γc is a correction factor for cement content, which is defined as:
(2.25)
where α is the air content in percent.
22
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
(2.26)
γst,s is a correction factor for the compressive strength of concrete:
(2.27)
2.8 Modulus of Elasticity of Concrete
2.8.1 Introduction
The modulus of elasticity is an important property of hardened concrete. Concrete is a
composite material, including aggregate and cement paste. The modulus of elasticity of
concrete highly depends on the properties and proportions of the mixture materials’ standard
C469 provides the method to measure the static modulus of elasticity of concrete is
compression. The elastic modulus of concrete has a significant effect on the behavior of
prestressed bridge girders, such as camber.
2.8.2 Factor affecting modulus of Elasticity of Concrete
The modulus of elasticity of concrete is greatly influenced by the material properties
and mineral admixtures, and the effect of other factors is not significant.
(2.29)
which, (Composite hard material when Em < Ep ).
where:
E is the modulus of elasticity of the composite material; Em is the modulus of elasticity
of the matrix phase; Ep is the modulus of elasticity of the particle phase; g = the fractional
volume of the particles.
Aggregate plays an important role in the modulus of elasticity of concrete. Typically,
higher aggregate content and higher modulus of elasticity of aggregate result in higher elastic
23
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
moduli of concrete. Those conclusions were confirmed, and empirical equations were
proposed [49].
The relation of stress and strain for aggregate, cement paste, and concrete are shown in
Fig 2.8.3.A reasonable explanation for the curved shape of concrete was given. The rate of
increase of induced strain at the interface of aggregate and cement paste was much higher
than the rate of applied stress development beyond a certain range [35].
Further explanation of the effect of the bound of aggregate and cement paste on the
elastic modulus of concrete was also provided. The difference in modulus of elasticity
Fig. 2.8.3 Stress-strain relations for aggregate, cement paste and concrete.
between aggregate and cement paste plays an important role in the modulus of elasticity of
concrete. In high-performance concrete, the difference in modulus of elasticity between
aggregate and cement and higher modulus of elasticity of concrete. In high-performance
concrete, the linear part in a stress and strain curve as high as 85% of ultimate strength or
even higher was observed.
24
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Fly ash has also a slight influence on the modulus of elasticity of concrete, including
class fly ash (Lane, 1982) and class C fly ash (Yildirim, 2011). Silica fume increases the
elastic moduli of concrete within certain content.
According to the study by Alfes [51], it was indicated 10% silica fume as the
replacement of Portland cement increased the elastic moduli of concrete by 12% at 28 days,
but 20% silica fume increased it by 7% at 28 days compared with concrete without silica
fume. In the study by Mazloom (2004), the effect of four levels of replacement of Portland
cement with silica fume including 0%, 6%, 10%, and 15% on the modulus of elasticity of
concrete was investigated. It was found that elastic moduli increased within 10% at 7 days
and 28 days with an increase in silica fume content.
2.6.5 Prediction of Elastic modulus of Elasticity of Concrete
Typically, the relation between the modulus of elasticity of concrete and
corresponding compressive strength is provided, which is not due to a direct relation between
elastic moduli and compressive strength, but because of the convenience of measurement of
compressive strength.
(2.30)
where:
Ec is the density of concrete.
25
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
In this, each member is considered for the calculation with its stress history and hence
it’s a laborious method for optimization or design when the number of vertical elements is
large. Moragspitiya et al. [54] used an SAP analysis package and considered the time-varying
material properties, construction sequences by using compression-only gas elements and
relaxation due to reinforcement in the analysis of 164-story reinforcement concrete high-rise
building structure with a belt and outrigger system.
This method was hence more comprehensive than many others. However, the discrete-
time steps used do not provide the flexibility of varying the time interval which is the main
factor affecting the accuracy of time-dependent deformation predictions, which is equivalent
to the effect of mesh size in a finite element method analysis.
Practicing engineers predict differential axial shortening using different methods but
these are not comprehensive. Most of these represent discrete models of a concrete member or
subframe analysis of a building representing a few stages of the construction process and field
monitoring conducted for a limited time period. These are unable to capture the time-
dependent load path changes due to structural complexities.
Further, the use of concrete-filled tube columns for the exterior columns may
aggravate the problem of axial shortening when the shear core is constructed with reinforced
concrete as common in practice. The few studies on the axial shortening of these types of
structures include the Taipei 101 building which used concrete-filled steel tubes for its eight
mega columns [57] and the studies done on the proposed use of concrete-filled tubes for the
perimeter columns of one of the tallest building in Korea, the tower palace III in Seoul in
which they later abandoned the use of these columns [56].
However, a holistic approach for predicting differential axial shortening in high-rise
buildings with concrete-filled tube columns considering all the influencing factors has not yet
been established.
27
Fig. 3.1 Typical sequencing of site operation.
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
differential axial shortening. Also, the self-climbing formwork systems enable the shear core
to be constructed several floors ahead of the frame as can be seen in Fig. 3.1.
3.2.3 Current engineering practices to minimize effects
The current engineering practices on minimizing the effect of differential axial
shortening in high-rise buildings are three-fold as follows:
(1) Proactive strategies to optimize building layout to minimize differential axial
shortening:
Stress balancing in the vertical load-bearing elements (by selecting the appropriate
column size)
Adjustment to reinforcement percentages
Varying concrete strengths in vertical members
(2) Compensation for differential axial shortening during construction
Several compensations techniques are available to minimize slab tilt during the service
of the structure, occurring due to the anticipated differential shortening of the columns and
walls. Absolute compensation. The absolute compensation is an idealized method, where the
differential shortening is exactly adjusted at each floor using the predicted shortening at each
level. The amount of correction for a vertical member at each level might have different
values leading to many complications such as different lengths of formwork and steel member
requirements. Due to the costly correction procedure, the absolute compensation technique
cannot be used during construction.
Uniform compensations
To minimize the number of different correction values in the compensation process
encountered in the previous method, the amount of the correction for each floor is averaged
over the number of floors in a building in this technique. Due to this averaging, however,
there are differences between the predicted shortening values and the correction values after
compensation. Therefore, as a result, the uniform compensation may not effectively eliminate
the predicted differential shortenings after compensation [58].
Lumped compensation
In this method, the lengths of vertical members are increased at the lumped level by
the cumulative correction for a few floors. With the lumped correction method, there are
differences between the predicted shortening values and the correction values after
compensation except at the lumped floor. The differences become gradually larger as the
number of floors to be lumped in a group is increased. On the other hand, the efficiency of the
lumped compensation method depends on the number of floors lumped together.
Park [58] proposed an optimization method for lump compensation using a simulated
annealing algorithm. In this by specifying, the limits on the magnitudes of the compensation
28
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
errors in each floor level as well as in each group as constraints in the optimization problem,
the magnitude of the differential shortening or the degree of the slab tilt in the floor levels
below the lump corrected is controlled.
The optimum values for the number of lumped groups, the number of floors in each
group, and the average correction value for each group are given as outputs of this method.
Currently, the moving average method which is another form of lumped compensation
optimization method was introduced to decide on the average correction value and the number
of floors to be lumped with much simpler than the earlier measure to reduce adverse effects of
differential axial shortening [58]:
Shim packing at the contact surfaces between the outrigger and the perimeter columns.
However, this is not effective to prevent the serviceability issues arising due to axial
shortenings such as tilting of floor plates, distortion, and damage to nonstructural
components and services [59].
The allowance was made for additional stresses induced by differential axial
shortening in load-bearing members.
Use of prestressed slabs
20mm limit for the facades attached to the floor [60], but it not only
affects the facades but also other services and floor plates. This 20mm limit can
increase or decrease depending on many other factors.
In Burj Kalifa, Dubai the tallest building in the world, several measures were taken to
reduce the differential axial shortening. At the design stage, some columns were over-
designed for stress balancing, and during construction, both horizontal and vertical
compensations were implemented and a typical constant floor-to-floor height increase was
incorporated, while each successive center hex core jump was “re-centered” [61] However, an
accurate prediction of axial shortening at the design stage is paramount for the success of
these.
29
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
between these long-term strains and the various properties of concrete. Among them are
several popular models with an increasing number of factors to be considered such as the B3
[26]
model and simple but popular models like the ACI-209, EC2 (BSI 2004), and GL2000 [62]
method.
The time-dependent strain components of concrete considered in these material
models are as given as shown in Tab. 3.1. As mentioned earlier these different models require
a variety of factors to be considered in calculating the creep and shrinkage of concrete.
These include the properties of the individual elements such as the cross-sectional
area, and exposed perimeter, the environmental conditions such as the humidity and
temperature which prominently affect the deformations through drying, and the properties of
the concrete mix such as the cement type, slump, and water/cement ratio. The factors
considered and their range for the successful prediction of creep and shrinkage are tabulated
as shown in Tab. 3-1 and 3.2.
30
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Relative Humidity × √ √ √ √
Environment
al conditions
Concrete temperature × √ × × ×
Cement type √ √ × × √
Cement content × × √ √ ×
Concrete mix Aggregate cement
× × √ √ ×
properties ratio (a/c)
Water cement ratio
× × × √ ×
(w/c)
Aggregate stiffness × × × × √
Slump × × √ × ×
Several researchers have measured the axial shortening of high-rise buildings using
these techniques as recorded in literature. Russel and Corley [63] used precise leveling
31
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
techniques and mechanical strain gauges to measure the vertical deformations of Water Tower
place which is a 75-story reinforced concrete building of 252m in height in Chicago. Axial
shortening of selected columns was measured at six levels of the building for three years.
For all strain gauge readings, measurements of air temperature and the surface
temperature had to be taken. Also, according to them, for the precise leveling techniques, the
reading could only be taken once the formwork had been removed and targets have been
attached. Also, the accuracy is reduced due to the difficulty of taking readings under site
conditions.
Arumugusaamy and Swamy instrumented a sixty-story and an eight-story building to
obtain axial shortening measurements for up to ten years of service, which is one of the very
few studies done for such a long period [64]. Their study indicated the design stress of steel in
some columns was exceeded only in 10 years due to the relaxation of concrete with time.
Bakoss et al. instrumented a medium-rise reinforced building at the new south Wales
University of Technology using vibrating wire gauges [65]. These were installed at three levels
of the building while another set of measurements was taken in parallel using precise leveling.
Brelsford [66] used electronic strain gauges and the total station. He concluded the total station
setup can be successfully used to measure the absolute difference in the shortening of
columns and shear walls at a certain floor level. However, this method becomes problematic
when the construction progresses and the finishes are done.
(3.4)
where, level N
(load increment),i
Ect is the elastic modulus
Pi is applied to load
hj is the height of each floor
N is the level of floor
i is load increment
At is time-dependent transformed area
of column cross section
Ect is time-dependent modulus of
Fig. 3.4 Schematic of a multi-stories differential shortening.
elasticity of concrete
32
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
33
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
The future effect on the façade element where the differential displacement between
successive floors in long-term stages must be considered in the façade joints design
and tolerance, especially for brittle façade materials.
If the slop values of the slabs due to differential vertical displacement exceed the
(1/240), a compensation of the long-term differential displacements between columns
and the central core should be considered in the shutter leveling during construction as
shown in Fig. 4.1b.
35
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
The Fig. 4.1.2a is the progress of the column shortening project using etabs. First step
is to create a group of members, loads and boundary elements in order to set the construction
stage. And then each construction stage should be defined by assigning the group information
depend on the construction schedule.
Next to define the time-dependent material properties such as creep, shrinkage, and
Grouping
Wind load
Generate load combinations
We can obtain the member force for each gravity load, creep, and drying shrinkage
through this analysis and creates a load combination including a wind and seismic load. Now,
36
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
it’s possible to do a design that reflects the column shortening using these load combinations.
The shortening of each vertical member can be obtained from the analysis result, and we can
calculate amount of correction using these shortening values.
Material
4.2 Case Study
Time-dependent material Time-dependent material
In order (Creep
to evaluate the theoretical results of the considered
& Shrinkage) ACI 209R-92
(Compressive strength) method, a
[5]
case study of a 306m high vertically asymmetric building was to compare the site readings of
column shortening taken during the tower construction. Th building is 54 floors as shown
typically as shown in Fig. 4.2a, 4.2b, 4.2c and 4.2d.
Time-dependent material link
(Creep & shrinkage + material link +member)
37
38
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
39
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
40
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
For lateral load analysis, either the stiffnesses presented in tab. 4.3.1 can be used.
These use values that approximate the stiffness for reinforced concrete building systems
loaded to near or beyond the yield level and have been shown to produce reasonable
correlation with both experimental and detail analytical results [67]. For earthquake-induced
loading, use tab. 4.3.1.
41
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
U=0.9D+1.0W W
U=0.9D+1.0E E
SLS=D+ (Lr or S or R) Lr or S or R
U=D+0.75L+0.75(Lr or S or R) Lr or S or R
U=0.9D+1.0W W
U=0.9D+1.0E E
stage of construction. Hence, the stresses and displacements distribution in the part of the
completed structure at any stage due to the partial dead load of members installed at that stage
does not depend on the geometry, properties, or the presence of members com-posing the rest
A large additional member force is created.
Deformation
Deformation by construction conventional stage analysis. by conventional Analysis.
43
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
In case of the project,10 days period is considered as a construction cycle period (floor
/ 10 days) and the main core wall has been assumed to be preceded in the construction of
slabs by 3 floors which is normal practice in high-rise building construction as shown in Fig.
4.5.1b.
44
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Stage 4 Stage 5
Fig. 4.5.1a Construction process of high-rise building.
60
50
40
Core wall
30
20 Self-weight of floor
10 plate
Finishes
Story
S5 (50 days)
E α G Unit Weight
Type v
(MPa) (1/C) (MPa) kN/m3 (MPa)
C35 27800 0.2 0.0000099 11583.33 24 35
(4.6.1)
where:
vu is the ultimate creep coefficient, and the average value suggested
(4.6.1)
(4.6.2)
where:
t is days after the end of the initial wet curing.
(εsh)u is the ultimate shrinkage strain, and the average value suggested for:
(4.6.3)
47
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
ground 2 (from the 36th floor up to roof floor). Results are plotted for axial shortening directly
after Top out (after applying 100% of structure self-weight and super-imposed dead load) and
for axial shortening after 50 years. Finally, total long-term axial shortening equation as shown
below:
49
Tab. 5.2 Axial Shortening after 50 years
Total Deformation (mm) of Column
Column
E2-A1 E2-A2 F2-B1 F2-B2 G2-Y4
Story Story label ∆z (mm) ∆z (mm) ∆z (mm) ∆z (mm) ∆z (mm)
54 FL53ROOF
Numerical Analysis of 75.332
Columns 75.332
Shortening on the Response of 75.835
High-Rise Concrete Buildings
53 FL52PH 78.803 78.803 78.731 79.34
52 FL51MECH 80.225 80.225 80.328 80.733
51 FL50 81.965 81.965 82.145 82.476
50 FL49 83.567 83.567 83.719 84.097
49 FL48 84.987 84.987 84.933 85.516
48 FL47 86.233 86.233 86.015 86.748
47 FL46 87.321 87.321 86.804 87.802
46 FL45 88.266 88.266 87.235 88.666
45 FL44 89.142 89.142 87.454 89.532
44 FL43 89.591 89.591 87.541 89.972
43 FL42 89.776 89.776 87.404 90.15
42 FL41 89.738 89.738 87.071 90.103
41 FL40 90.015 90.015 86.988 90.375
40 FL39 90.052 90.052 86.689 90.404
39 FL38 89.867 89.867 86.188 90.212
38 FL37 89.455 89.455 85.473 89.787
37 FL36 88.799 88.799 84.532 89.115
36 FL35ROOF 88.556 88.556 84.123 88.891 56.086
35 FL34 88.087 88.087 83.11 88.391 56.458
34 FL33MECH 89.358 89.358 83.63 89.653 57.807
33 FL32MECH 88.547 88.547 81.637 88.834 57.622
32 FL31 88.197 88.197 81.04 88.508 58.131
31 FL30 87.737 87.737 80.496 88.004 58.495
30 FL29 86.918 86.918 79.613 87.127 58.67
29 FL28 85.95 85.95 78.609 86.103 58.794
28 FL27 84.825 84.825 77.484 84.93 58.872
27 FL26 83.561 83.561 76.256 83.615 58.715
26 FL25 82.141 82.141 74.916 82.148 58.419
25 FL24 80.515 80.515 73.424 80.495 57.981
24 FL23 78.762 78.762 71.837 78.714 57.49
23 FL22 76.883 76.883 70.16 76.811 56.903
22 FL21 74.995 74.995 68.512 74.9 56.221
21 FL20REFUGE 73.676 73.676 67.252 73.556 55.804
20 FL19 72.251 72.251 65.913 72.108 55.309
19 FL18 70.736 70.736 64.506 70.571 54.747
18 FL17 69.135 69.135 63.035 68.948 54.124
17 FL16 67.453 67.453 61.506 67.245 53.443
16 FL15 65.697 65.697 59.925 65.469 52.715
15 FL14 63.881 63.881 58.303 63.634 51.95
14 FL13 62.027 62.027 56.66 61.762 51.169
13 FL12 60.179 60.179 55.038 59.9 50.414
12 FL11 59.103 59.103
50 54.106 58.818 50.41
11 FL10 51.927 51.927 47.946 51.651 46.278
10 FL09 46.858 46.858 43.268 46.494 42.419
9 FL08 44.2 44.2 40.835 43.75 40.471
8 FL07 41.421 41.421 38.274 40.92 38.507
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
From the analysis results, deformation due to the creep and shrinkage effects, as
shown in Tab. 5.2, contribute 65.8%-75.19% of the total deformation of the column.
Fig. 5.2 show the distribution graph of the vertical displacement by stories for the
column, respectively. As the number of stories increases in conventional analysis in which
construction stages are considered, the maximum vertical displacement of the column of
90.404 mm at the 40 story.
51
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Shortening (mm)
Shortening (mm)
Fig. 5.2b Columns E2-A2, axial shortening after 50 years.
52
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Shortening (mm)
Shortening (mm)
53
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Shortening (mm)
Fig. 5.2e Columns G2-Y4, axial shortening after 50 years.
Finally, we get the total long-term axial shortening of columns (E2-A1) due to elastic
shortening, creep, and shrinkage after 50 years.
Axial shortening
after
50
ELyears
only
CR only
SH only
Fig. 5.2f Columns E2-A1, ∆EL, ∆CR, ∆SH, and total (∆EL+∆CR+∆SH) shortening after 50 years.
54
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Axial shortening
after
50 years
EL only
CR + SH
Shortening (mm)
Fig. 5.2g Columns E2-A1, ∆EL,∆CR+∆SH, and total (∆EL+∆CR+∆SH) after 50 years.
56
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
0 BASE 0 0 0 0
Graph - Wall “C01”
Shortening (mm)
Shortening (mm)
Fig. 5.3b Wall C02,axial shortening after 50 years.
57
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Graph - Wall
“N02”
Shortening (mm)
Fig. 5.3c Wall N02, axial shortening after 50 years.
Graph - Wall “E01”
Shortening (mm)
58
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
From the analysis results, deformation due to the creep and shrinkage effects, as
shown in Tab. 5.2, contribute 70.4%-82.1% of the total deformation of the shear wall.
Fig. 5.2 show the distribution graph of the vertical displacement by stories for the
column, respectively. As the number of stories increases in conventional analysis in which
construction stages are considered, the maximum vertical displacement of the shear wall of
68.445% mm at the 40 story.
Graph - Wall “C01”
Axial shortening
after 50 years
EL only
CR only
SH only
Shortening (mm)
Fig. 5.3.2a Wall”C01”, ∆EL, ∆CR, ∆SH, and Total (∆EL+∆CR+∆SH) shortening after 50 years.
Axial shortening
after 50 years
EL only
CR+SH only
Shortening (mm)
Fig. 5.3.2b Wal-C0,∆EL, ∆CR+∆SH, and Total (∆EL+∆CR+∆SH) shortening after 50 years.
59
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
For the practical design of the building, fintel et al. suggest that the maximum value of
the differential settlement moments be assumed at 50% of the moments that would occur
without relaxation due to creep. These moments should then be used with appropriate load
factors in combination with the effects of other loads. The 50% reduction accounts only for
creep relaxation during the period of settlement. Beyond this time a further creeping out of
settlement moments takes place [3].
The differential between the accumulative long-term shortening values sorted in
previous Tabs for columns and walls at each floor must be considered in slab design.
Appendix A shows the collected accumulative long-term axial shortening for columns and
walls after 50 years.
The total value of long-term axial shortening at the target time does not always occur
due to stresses relaxation of the concrete members, the environmental changes during the
entire life of the building, and the code-based creep and shrinkage values may be
conservative, so it is recommended to use 50% only of the calculated long-term shortening in
the design purposes to obtain a reasonable increase in the reinforcement.
60
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
In post-tension (PT) slab design, the post-tension consultant shall provide adequate
tendons to achieve the code requirements regarding the stresses at the full-service load stage
and the sustained load stage considering the effect of long-term axial shortening in the used
service and sustained load combinations.
The induced stresses from the differential shortening can be reduced by using a
different approach as shown in the following:
As noticed in previous Tables for columns and walls, the value of differential
shortening between the main core and peripheral columns is increasing with going higher (at
upper floors) and this increase in the value of the differential shortening may induce high
stresses at upper slabs which will lead to increasing slab thicknesses and/or reinforcement
values at upper floors, however, the induced high stresses can be slightly eliminated by
subtracting the value of shortening already occurred before the date of pouring the specific
slab. This will not be workable for lower floors where the subtracted value will be very minor
and will not help in reducing the stresses. This approach may be applicable for at least 50-
story high-rise buildings to give the expected difference.
61
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Shrinkage
Creep
Elastic
62
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Aggregate characteristics
Degrees of compaction
Length of initial curing
Initial curing Curing temperature
Curing humidity
Concrete temperature
Member geometry and Environment
Concrete water content
environment (creep and shrinkage)
Geometry Size and shape
Concrete age at load application
During load period
Loading history
Number of load cycles
Loading (creep only) Duration of unloading period
Type of stress and distribution
Stress conditions across the section
Stress/strength ratio
So, compensate the long-term axial shortening in shuttering level is not necessary
because the differential between long-term axial shortening of the main core and the edge
column is less than code limit (i.e., islop < ilimit ).
63
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Chapter 6. Conclusions
From this research, it presents the calculated column shortening of a 54-story building.
The conclusions of this study are summarized as follows:
(1) The differential axial shortening between the central core wall and the peripheral
columns must be considered in the design. In case of a wall, the lateral load is an important
factor in determining the cross-section. Therefore, the ratio of compressive strength to axial
force is generally about 15 to 20%, which is very small. In case of the column, however,
gravity load is the most important factor, and the ratio of axial force compressive strength is
about 40-50%. As a result, a greater vertical strain occurs in the column than in the wall.
(2) The differential axial shortening between successive floors must be considered in
the façade design because it can lead to the unintended sloping/tilting/rotating of the
building’s concrete floor, which can subsequently result in unintended stresses and
misalignment of the interfacing building systems, partitions, cladding.
(3) The material properties of the in-situ concrete are verified by laboratory tests. A
computer program that adopted three-time functions of shrinkage based on ACI and PCA is
developed for the calculation of column shortening.
(4) The underestimation in axial shortening deformation of a concrete member is
mainly caused by the inappropriate use of elastic modulus. The time development equation of
elastic modulus recommends by current standards ignores the adverse influence of loading
history applied on concrete, and the step-by-step loading history with shorter time steps has a
more negative impact on elastic modulus, which makes it around 5%-11% lower than the
predicted values.
(5) The proportion of the deformation due to creep and shrinkage that contribute to
the total amount of deformation is 65.8% - 75.19% for the column and 70.4% - 82.1% for the
shear wall. Therefore, for concrete buildings, deformation due to creep and shrinkage must be
considered.
64
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
References
[1] Ali M.M., and Moon K.S (2007); Hallebrand and Jakobsson, 2016. “Structural
development in tall buildings:"
[2] Lee Y, Kim JK, Seol HC, Yang JK, Kim KJ. 3D numerical analysis of column
shortening and shore safety under construction of high-rise building. Engineering
Structures. 2017 Nov 1;150:242-55.
[3] Sami S. Matar and William J. Faschan. "A structural Engineer's Approach to
differential Vertical Shortening in Tall Buildings"
[4] ACI 209.2R-08. "Guide for modeling and Calculating Shrinkage and Creep in
Hardened Concrete".
[5] Ruben Correia, Paulo Silva Lobo; "Simplified Assessment of the effects of Columns
Shortening on the Response of Tall Concrete Buildings".
[6] Mark Fintel, S.K. Ghosh, and Hal lyengar.,1987. "Column Shortening in Tall
Structures-Prediction and Compression".
[7] Smith, B.S., Coull, A., 1991. "Tall building Structures: Analysis and Design". John
Willey & Sons, Inc., New York.
[8] Kurc, O., Lulec, A., 2011. "A comparative study on Different Analysis Approaches
for Estimating the Axial Loads on Columns and Structural Wall at Tall Buildings. The
Structural Design of tall and special Building".
[9] M. Asce and E-Doo Kim, Chang-Koon Choi “Multistory Frames Under Sequential
Gravity Loads” Journal of Structural Engineering, ASCE, Vol 111 No.11, Nov 1985.
[10] Hye-Kyo Chung, Chang-Koon Choi, Dong-Guen Lee and E.L. Wilson “Simplified
Building Analysis with Sequential Dead Loads-CFM” Journal of Structural
Engineering, ASCE,Vol 118, No.4, April 1992.
[11] A. R. Mari, P. J. S. Cruz; and P. Roca “Nonlinear Time-Dependent Analysis of
Segmentally Constructed Structures” Journal of Structural Engineering, ASCE, Vol
124, No.3, March 1998,
[12] W. Jayasena, M. T. R. Jayasinghe, “Effects of Axial Shortening of Columns on
Design and Construction of Tall Reinforced Concrete Buildings” Practice Periodical
on Structural Design and Construction, ASCE, Vol 9, No.2, May 2004.
[13] Hyo-Gyoung Kwak, “Time-dependent analysis of RC frame structures considering
construction sequences” Building and Environment, ELSEVIER, Vol 41, No.10, Oct
2006.
[14] Alexander, S. (2001). Axial shortening of concrete columns and walls. Concrete
(London), 35(3), 36-38.
65
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
[15] Kim YH, Trejo D, Hueste MBD, et al. (2011) Experimental study on creep and
durability of high-early-strength self-consolidating concrete for precast elements. ACI
Materials Journal 108(2).
[16] Kim H, Cho S. Column shortening of concrete cores and composite columns in a tall
building. The structural design of tall and special buildings. 2005 Jun;14(2):175-90.
[17] Blanc, C.M., Sánchez, A.O. and Navarro, I.F., 2021. Analytical characterization of
axial shortening due to creep of reinforced concrete columns in tall
buildings. Engineering Structures, 228, p.111584.
[18] Wang, L., Zhao, X. and Yan, C., 2020. Time-dependent vertical shortening prediction
for super-tall buildings by using a modified B3 model to consider moisture
distribution. Engineering Structures, 209, p.109994.
[19] Matar, Sami S., and William J. Faschan. "A structural engineer's approach to
differential vertical shortening in tall buildings." International Journal of High-Rise
Buildings 6, no. 1 (2017): 73-82.
[20] Dilger, W.H. and Wang, C., 2000. Creep and shrinkage of high-performance
concrete. Special Publication, 194, pp.361-380.
[21] Rhodes, James A., and D. J. Carreira. "Prediction of creep, shrinkage, and temperature
effects in concrete structures." (1982).
[22] Kim WS, Cho HW, Oh JK, Yom KS. Measured and predicted column shortening of a
tall reinforced concrete building. Korean concrete institute. 1999 Jun;11(3):161-70.
66
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
67
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
22 FL21 69 69 75 75 79 79
21 FL20REFUGE 68 67 74 74 77 77
20 FL19 66 66 72 72 76 76
19 FL18 65 65 71 71 74 74
18 FL17 63 63 69 69 72 73
17 FL16 62 62 67 67 71 71
16 FL15 60 60 66 65 69 69
15 FL14 59 58 64 64 67 67
14 FL13 57 57 62 62 65 65
13 FL12 55 55 60 60 63 63
12 FL11 54 54 59 59 62 62
11 FL10 48 48 52 52 54 55
10 FL09 44 43 47 46 49 49
9 FL08 41 41 44 44 46 46
8 FL07 39 38 41 41 43 43
7 FL06 35 34 37 36 39 39
6 FL05 30 30 32 31 34 33
5 FL04 23 23 25 24 26 26
4 FL03 19 19 20 20 21 22
3 FL02 15 15 16 16 17 17
2 FL01 11 11 12 11 12 12
1 FL00GFL 5 5 5 5 5 5
0 BASE 0 0 0 0 0 0
41 FL40 68 64 61 68 69 62
40 FL39 68 65 61 68 69 62
39 FL38 68 65 61 68 69 62
38 FL37 68 66 62 68 69 63
37 FL36 69 66 61 68 69 63
36 FL35ROOF 68 66 62 67 69 64
35 FL34 68 67 62 66 69 65
34 FL33MECH 68 67 63 67 69 65
33 FL32MECH 70 68 64 69 71 66
32 FL31 68 67 63 67 69 65
31 FL30 68 67 63 67 69 65
30 FL29 68 67 63 67 69 65
29 FL28 67 67 63 67 68 65
28 FL27 67 67 63 67 68 65
27 FL26 66 66 62 66 68 65
26 FL25 66 66 62 66 67 64
25 FL24 65 65 62 65 66 64
24 FL23 64 65 61 65 66 63
23 FL22 63 64 61 64 65 63
22 FL21 63 63 60 63 64 62
21 FL20REFUGE 62 63 59 62 63 62
20 FL19 61 62 59 61 62 61
19 FL18 60 61 58 61 62 60
18 FL17 59 60 58 60 61 59
17 FL16 58 59 57 59 60 59
16 FL15 57 58 56 58 59 58
15 FL14 57 58 55 57 58 57
14 FL13 56 57 55 57 57 56
13 FL12 55 56 54 56 56 56
12 FL11 54 55 54 55 55 55
11 FL10 50 51 50 50 50 51
10 FL09 44 45 45 45 45 45
9 FL08 42 43 42 42 42 43
8 FL07 39 39 39 39 39 40
7 FL06 34 35 35 35 35 36
6 FL05 30 30 31 30 31 31
5 FL04 23 23 24 24 24 24
4 FL03 19 20 20 20 20 21
3 FL02 15 16 16 16 16 17
2 FL01 11 11 12 12 12 13
1 FL00GFL 5 5 5 5 5 6
0 BASE 0 0 0 0 0 0
70
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
72
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
15 FL14 2 2 2 2 2 2
14 FL13 2 2 2 2 2 2
13 FL12 1 1 1 1 1 1
12 FL11 6 6 7 7 8 7
11 FL10 5 5 5 5 5 5
10 FL09 2 2 3 3 3 3
9 FL08 3 3 3 3 3 3
8 FL07 4 4 5 5 5 5
7 FL06 5 5 5 5 5 5
6 FL05 7 7 7 7 7 7
5 FL04 4 4 4 4 5 4
4 FL03 4 4 4 4 5 5
3 FL02 4 4 5 4 5 5
2 FL01 6 6 6 6 7 7
1 FL00GFL 5 5 5 5 5 5
0 BASE 0 0 0 0 0 0
35 FL34 1 1 1 1 1 3
34 FL33MECH 1 1 2 2 0 2
33 FL32MECH 0 0 0 0 1 1
32 FL31 0 1 0 0 0 1
31 FL30 1 1 0 1 0 1
30 FL29 1 1 1 1 0 1
29 FL28 1 1 1 1 0 1
28 FL27 1 1 1 1 0 0
27 FL26 1 1 1 1 0 0
26 FL25 1 2 1 1 0 0
25 FL24 2 2 1 1 0 1
24 FL23 2 2 1 1 1 1
23 FL22 2 2 1 1 1 1
22 FL21 1 1 1 1 0 1
21 FL20REFUGE 1 1 1 1 0 1
20 FL19 1 2 1 1 1 1
19 FL18 1 2 1 1 1 1
18 FL17 2 2 1 1 1 1
17 FL16 2 2 1 1 1 1
16 FL15 2 2 1 1 1 2
15 FL14 2 2 1 1 1 2
14 FL13 2 2 1 1 1 2
13 FL12 1 1 0 0 0 1
12 FL11 7 4 5 5 4 7
11 FL10 5 5 4 5 4 4
10 FL09 3 3 2 2 2 2
9 FL08 3 3 2 2 2 2
8 FL07 4 5 4 4 4 4
7 FL06 5 5 4 5 4 4
6 FL05 7 7 6 7 7 7
5 FL04 4 4 4 4 4 4
4 FL03 4 5 4 4 4 4
3 FL02 5 5 4 4 4 5
2 FL01 7 7 6 6 6 7
1 FL00GFL 5 6 5 5 5 6
0 BASE 0 0 0 0 0 0
74
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
75
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Slump 70 mm
Water-cement ratio Air content ≤ 6%
Mixture proportions Fine aggregate
composite 50%
Aggregate characteristics percentage
Degrees of compaction 279 to 446
Cement content
kg/m3
and shrinkage)
Moist cured 7 days
Length of initial curing
Steam cured 1 to 3 days
Moist cured 23.2 ± 2 oC
Initial curing Curing temperature
Steam cured ≤ 100 oC
Relative
Curing humidity ≥ 95 oC
humidity
Concrete
Concrete temperature 23.2 ± 2 oC
temperature
Environment
Member geometry Ambient relative
Concrete water content 40%
and environment humidity
(creep and Volume-surface V / S = 38 mm
shrinkage) ratio or
Geometry Size and shape
minimum 150 mm
thickness
Concrete age at load Moist cured 7 days
application Steam cured 1 to 3 days
Loading During of loading period Sustained load Sustained load
history Duration of unloading
- -
period
Loading (creep
Number of load cycles - -
only)
Type of stress and
Axial
distribution across the Compressive
Stress compression
section
conditions
Stress / strength
Stress/strength ration ≤ 0.50
ration
76
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Curing temperature
Curing humidity
Member geometry Concrete temperature
Environment
and environment Concrete water content
(creep and
Geometry Size and shape
shrinkage)
Concrete age at load
application
Loading During of loading period
history Duration of unloading
Loading (creep period
only) Number of load cycles
Type of stress and
Stress distribution across the
conditions section
Stress/strength ration
77
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
78
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
Acknowledgment
I would like to thank Khan Theany for the continuous blessings upon me. I want to thank
my family, especially my parents, for supporting me morally and spiritually far away from
home throughout my master's study and every step of my life.
I want to express my sincere gratitude to my respected supervisor Prof. Dr. Wang Licheng,
for his continuous and unconditional support during my Master's study and related research
work. His guidance, patience, motivation, and immense knowledge helped me throughout my
research and writing of this thesis. I could not have imagined having a better advisor and
mentor for my Master's study.
My sincere thanks also go to all my friends, fellow lab mates, juniors, and seniors for their
assistance, valuable time in discussions and suggestions and, all the fun we have had together
in the last three years. I am also thankful to the People’s Republic of China for providing me
with this opportunity for a master's study in DUT.
Thanks to everyone from 220 for all your encouragement and support. Room 220 will stay
in my heart forever.
ENG Phearum
79
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
80
Numerical Analysis of Columns Shortening on the Response of High-Rise Concrete Buildings
大连理工大学学位论文版权使用授权书
本人完全了解学校有关学位论文知识产权的规定,在校攻读学位期间论
文工作的知识产权属于大连理工大学,允许论文被查阅和借阅。学校有权
保留论文并向国家有关部门或机构送交论文的复印件和电子版,可以将本
学位论文的全部或部分内容编入有关数据库进行检索,可以采用影印、缩
印、或扫描等复制手段保存和汇编本学位论文。
作 者 签 名 : 日期: 2023 年 07 月 12 日
导 师 签 名 : 日期: 2023 年 07 月 12 日
81