PROJECT NAME: Construction of SPARK 380/115 kV BSP

ELEMENT 5.19.3
JOB SAFETY PRACTICES

DEPARTMENT/DIVISION PE-199 Mechanical DATE 25/09/2019


EMPLOYEE JOB TITLE Welder LOCATION Abqaiq
Helmet, Safety Glass, Welding Mask, Coverall,
Personal Protective
JOB/ TASK TITLE Welding and Cutting Welding Gloves, Safety Shoes, visible vest,
Equipment
Harness with 2 lanyards, apron & ear plug
STEPS HAZARDS
IN EACH STEP, WHAT COULD CONTROL REQUIRED TO MINIMIZE/ ELIMINATE
LIST ALL STEPS IN PERFORMING THIS COMMENTS OF JOB OBSERVATION
STEPS # CAUSE INJURY, LOSS DAMAGE, HAZARD
TASK
INTRRUPTION, OR POLUTION?
 Struck by vehicle  Materials must be secured to prevent it
 Fall of materials due to from falling while traveling
unsecured materials and  Flagman must be present on forklift at
improper loading to all time to guide the movement of the
Preparation of materials (Shifting vehicle by forklift equipment and prevent anyone to go
1. of Materials from store to work  Struck by forklift near the area. Accepted
place by used of vehicle/forklift)  Slip, trip and fall  Arrange materials properly as per
 Back injury due to carrying standard
heavy load  Do not block the access
 Do not carry heavy materials by your
own, ask for help.
2. Welding Cutting & Grinding  Welding Machine &  Inspect welding plant before using
Welding leads.  Inspect lead for any broken insulation.
 Electric Shock  Grounding of welding plant wet surface
 Suffocation/Heat standard fitting and cable
Exhaustion, burns,  ELCB and breaker installed and are fit
 Presence of HC Fumes in for service welding machine
the Vicinity  First Aid Box Available and equipped Accepted
 Fire  Access Controlled & Barricaded.
 Spreading Cables on  Welder/Fabricator must have
ground. knowledge how to operate fire
 Sparking & Grinding extinguishers.
particles naked flames  Proper sign boards are placed.
Page 1 of 3 Rev.2 [08-April-2019] Projects Business Unit
PROJECT NAME: Construction of SPARK 380/115 kV BSP
ELEMENT 5.19.3
JOB SAFETY PRACTICES

 High Nose  Check area must be properly ventilated


as per check list
 High noise sign boards are placed.
 Use of ear Plugs. Area Barricaded
 Use face shield & Appropriate PPE's
 Fire retardant guard placed with
grinding/Cutting machine
 Appropriate fire extinguishers available.
 Welder/Fabricator must have
knowledge how to operate fire Accepted
extinguishers

 Fall from Height  Workers must be trained in working


 Incomplete Scaffold height prior to work in elevated area.
 Workers are not trained in  Wear full body harness with double
working at height lanyards and secure 100% tie off.
Working at Height Accepted
3.  Unsafe erection of  Scaffold must be inspected, Green tag
(Use of scaffold)
Scaffolding will indicated scaffold is safe to use.

 Area must be clean and materials must


be arrange.
 Excess Materials should be return to
 Poor housekeeping that
store.
Housekeeping can cause trip, slip and fall. Accepted
4.  Removed scrap materials at site and
 Scattered Scrap materials
place it on scrap storage area.

Page 2 of 3 Rev.2 [08-April-2019] Projects Business Unit


PROJECT NAME: Construction of SPARK 380/115 kV BSP
ELEMENT 5.19.3
JOB SAFETY PRACTICES

Emergency Response and Arrangements


 The injured person should be given first aid immediately.
 First aid box shall be made available with required medicines in adequate quantity.
 Emergency response team should be available at site.
 All personnel on site should be aware on site evacuation procedure, location of muster point.
 Emergency Numbers shall be posted at different locations.
 One vehicle shall be made available for meeting emergency needs.
 All employees shall be explained about the provisions of first aid, assembly point and contact number, etc.
JSP Prepared By: Mr. Haitham Abouelella Signature: Date: 29/09/2019

JSP Accepted By: Mr. Mohamed Abdellatif Signature: Date: 29/09/2019

JSP Approved By (SEC / Site): Mr. Ronald Marteja Signature: Date: 29/09/2019

JSP Approved By (SEC- PD): Mr. Abdul Majeed Signature: Date: 29/09/2019

Page 3 of 3 Rev.2 [08-April-2019] Projects Business Unit