PROJECT NAME: Construction of SPARK 380/115 kV BSP

ELEMENT 5.19.3
JOB SAFETY PRACTICES

DEPARTMENT/DIVISION PE-199 Civil DATE 09/10/2019


EMPLOYEE JOB TITLE Mason LOCATION Abqaiq
Helmet, Safety Glass, Mask, Coverall, Gloves,
Personal Protective
JOB/ TASK TITLE Finishing Works Safety Shoes, visible vest & Harness with 2
Equipment
lanyards
STEPS HAZARDS
IN EACH STEP, WHAT COULD CONTROL REQUIRED TO MINIMIZE/ ELIMINATE
LIST ALL STEPS IN PERFORMING THIS COMMENTS OF JOB OBSERVATION
STEPS # CAUSE INJURY, LOSS DAMAGE, HAZARD
TASK
INTRRUPTION, OR POLUTION?
 Struck by vehicle  Materials must be secured to prevent it
 Fall of materials due to from falling while traveling
unsecured materials and  Flagman must be present on forklift at
improper loading to all time to guide the movement of the
Preparation of materials (Shifting vehicle by forklift equipment and prevent anyone to go
1. of Materials from store to work  Struck by forklift near the area. Accepted
place by used of vehicle/forklift)  Slip, trip and fall  Arrange materials properly as per
 Back injury due to carrying standard
heavy load  Do not block the access
 Do not carry heavy materials by your
own, ask for help.
2. Surface preparation by used of  Incompetent person to do Accepted
grinding machine the task that leads to  Provide appropriate PPE (Face-shield,
accident safety Glass, Gloves, etc.), only
 Improper body posture competent person will do the task.
while working that can  No Unauthorized and incompetent
cause back injury, etc. person is allowed.
 Hand injury  Grinding area must be barricaded with
 Machine failure signage.
 Fire Extinguisher must be available at
all times.
 Power tools must be inspected and
color coded to ensure equipment is in

Page 1 of 3 Rev.2 [08-April-2019] Projects Business Unit


PROJECT NAME: Construction of SPARK 380/115 kV BSP
ELEMENT 5.19.3
JOB SAFETY PRACTICES

 Accumulation of dust good working condition.


inside the building  Provide exhaust fan to ensure dust free
inside the building.

 Incompetent person to do  Only competent person are allowed to


the task do the job.
 Hand injury  Wear all required PPE (Mask & Gloves,
 Simultaneous activity in etc.,) to avoid any injury and illnesses.
one area.  Proper Supervision of Foreman and
 Following unsafe Supervisor
Accepted
3 Cement Application procedures that can  Activity must be isolated, barricaded
injured workers. and provide proper signage’s
 Inhaling of particles from  Follow proper procedures to prevent
cement, it can cause any accident that can lead to injury and
damage to lungs and lead damage to property.
to cancer illnesses.  Refer to MSDS

 Workers must be trained in working


 Fall from Height
height prior to work in elevated area.
 Incomplete Scaffold
 Wear full body harness with double
Working at Height  Workers are not trained in Accepted
4. lanyards and secure 100% tie off.
(Use of scaffold) working at height
 Scaffold must be inspected, Green tag
 Unsafe erection of
will indicated scaffold is safe to use.
Scaffolding
5. Housekeeping  Poor housekeeping that  Area must be clean and materials must Accepted
can cause trip, slip and fall. be arrange.
 Scattered Scrap materials  Excess Materials should be return to
store.
 Removed scrap materials at site and
place it on scrap storage area.

Page 2 of 3 Rev.2 [08-April-2019] Projects Business Unit


PROJECT NAME: Construction of SPARK 380/115 kV BSP
ELEMENT 5.19.3
JOB SAFETY PRACTICES

Emergency Response and Arrangements


 The injured person should be given first aid immediately.
 First aid box shall be made available with required medicines in adequate quantity.
 Emergency response team should be available at site.
 All personnel on site should be aware on site evacuation procedure, location of muster point.
 Emergency Numbers shall be posted at different locations.
 One vehicle shall be made available for meeting emergency needs.
 All employees shall be explained about the provisions of first aid, assembly point and contact number, etc.
JSP Prepared By: Mr. Haitham Abouelella Signature: Date: 09/10/2019

JSP Accepted By: Mr. Mohamed Abdellatif Signature: Date: 09/10/2019

JSP Approved By (SEC / Site): Mr. Ronald Marteja Signature: Date: 09/10/2019

JSP Approved By (SEC- PD): Mr. Abdul Majeed Signature: Date: 09/10/2019

Page 3 of 3 Rev.2 [08-April-2019] Projects Business Unit