Professional Documents
Culture Documents
05 - WORK METHOD STATEMENT-ICT Works
05 - WORK METHOD STATEMENT-ICT Works
(WMS)
PROJECT TITLE:
CLIENT
………………………………………………… …………………………………………………………..
Name : Name :
Date : Date :
INDEX
1.0 OBJECTIVE
2.0 CLIENT INFORMATION
3.0 METHOD OF STATEMENT (METHODOLOGY)
3.1 PURPOSE
3.2 SCOPE OF WORK
3.3 REFERENCES
3.4 RESPONSIBILITY
3.5 MANPOWER
3.6 TOOL & EQUIPMENT
3.7 MATERIALS
3.8 WORK PROCEDURES
3.8.1 PRE-INSTALLATION ACTIVITY
3.8.2 SURVEYING ACTIVITIES
3.8.3 INSTALLATION STEP
3.9 TESTING AND COMMISSIONING
3.9.1 COMMISIONING PRE-REQUISITES
3.9.2 TESTING AND COMMISSIONING
WORK METHOD STATEMENT
(WMS)
1.0 OBJECTIVE
This work method statement covers the demolition works for DESIGN AND BUILD FOR THE
PROPOSED NEW ESCALATOR SHAFT PIT FOUNDATION AND OTHER ASSOCIATED WORKS AT
CONTACT PIER AND SATELLITE BUILDING, KL INTERNATIONAL AIRPORT TERMINAL 1, SEPANG,
SELANGOR DARUL EHSAN
This work method statement provides information concerning method of application to ensure compliance
with contract requirements and drawings besides to perform safe working environment and compliance
with safety requirements.
Remarks:
3.1 PURPOSE
The purpose of this method statement is to define the procedure for the installation of ICT system
including the passive and active equipment and peripherals as per approved drawings, all in
accordance with the requirement specified in relevance specification, procedures and drawings,
considering safety and quality of work activities.
3.3 REFERENCES
Approved Materials Submittal for ICT Passive and Active System
Approved related Shop Drawings
WORK METHOD STATEMENT
(WMS)
Manufactured Recommendation
Submitted QA/QC Plan
Submitted HSE Plan
Approved Early Mobilization Logistic Plan
3.4 RESPONSIBILITY
Construction Manager
Overall responsible for the implementation of method statement and ensure that his team
of Engineer and foreman are aware of this method statement.
Ensuring that all constraint on operation have been identified and precautions are taken.
Ensure all resources are available to carry out the works as planned, without any delay.
Site Engineer
Responsible in carrying out the works as per the approved method statement and
specifications.
Ensuring that the work area is safe and clear
Conduct tool box talk & explain briefly to all operatives involves about method statement &
risk assessment.
Responsible for implementing the approved HSE plan on site.
Ensure all manpower is wearing appropriate PPE such as safety shoe, helmets, gloves,
googles and protected as safety plan.
QA/QC Engineer
Ensure that work is done accordance with the approved method statement and project
specification.
Responsible for implementing the approved QA/QC plan on site.
Ensure that inspection are done in accordance with the ITP’s & offer works for engineer’s
inspection.
Ensures that all test equipment including surveying equipment is calibrated and suitable
for use on site.
Safety Engineer
Monitor the safety tool box meetings being conducted by the site engineer.
Monitor the implementation of the approved HSE plan on site.
Monitor the site to ensure all manpower is wearing appropriate PPE
To strictly monitor the workers so as to be assured that all safety regulation & procedures
are implemented.
WORK METHOD STATEMENT
(WMS)
Site Foreman
Supervise & execute the installation accordance to the approved shop drawings & method
statement.
Coordinate with the discipline engineer for site execution and during the final inspection.
Coordinate with the crew on implementation of safety procedures at the site.
3.5 MANPOWER
Site Engineer
System Engineer
Safety Officer
QA/QC Engineer
Site Foreman
Technician
Labours
3.7 MATERIALS
Fibre and Copper Cables
Patch Panels, Cable Managers, Modules and Connectors
Equipment Racks and PDU
Brackets
Active Equipment such as Network Switches, Router, Firewall, Application Server, Access
Points.
WORK METHOD STATEMENT
(WMS)
To carry out commissioning activity for ICT system below mentioned procedure is recommended to
be followed in sequential manner. Responsibility of concerned persons is also indicated against
each activity.
Prior to any testing and commissioning the following documentation will be available.
Pre-Commissioning test sheets
Snag list duly signed off as complete sufficiently as not impede commissioning. Note that it
is necessary to have all snag complete prior to commissioning commencing.
This procedure is for testing and commissioning.
All relevant drawings
Any documentation required as part of the safety procedure.
All relevant material submittals
Testing and commissioning reports.
3.9.1 Commissioning Prerequisites
The standard pre commissioning checks comprise of the following aspects.
Visual inspection to ensure that all field devices are installed as per the
requirements.
WORK METHOD STATEMENT
(WMS)
Active and passive components (network switches and the corresponding cabling
infrastructure) are installed and commissioned, including patching (Installation &
Labelling of patch cords in telephone rooms) & necessary configuration.
All instrument / test kits should have valid calibration certificate. Copies to be
produces during test.
Permanent power is available.
3.9.2 Testing and Commissioning
Check for the communication of all devices.
Test the wireless coverage.