Professional Documents
Culture Documents
Work Method Statement-Temporary Cooler
Work Method Statement-Temporary Cooler
(WMS)
JOB TITLE:
CLIENT
SCOPE OF WORK:
TEMPORARY COOLER
………………………………………………… …………………………………………………………..
Name : KHAIRUL AQIL BIN MOHD YUSOF Name :
Date : 05.08. 2022 Date :
INDEX
WORK METHOD STATEMENT
(WMS)
1.0 OBJECTIVE
3.1 INSTALLATION
4.0 SAFETY MEASUREMENT
6.0 APPENDIX
1.0 OBJECTIVE:
WORK METHOD STATEMENT
(WMS)
This work method statement covers the temporary evaporative cooler for Proposed
Improvement of Existing Air-Conditioning and Mechanical Ventilation (ACMV) System
Including Installation and Commissioning of New Chilled Water Control Valves,
Replacement of Air Handling Units and Associated Works at Kl International Airport,
Sepang, Selangor Darul Ehsan.
This work method statement provides information concerning method of application to ensure
compliance with contract requirements and drawings besides to perform safe working
environment and compliance with safety requirements.
DESIGNATION NUMBER
Project Engineer 0
Site Coordinator 1
Site Supervisor 1
General Worker 2
7.2 INSTALLATION
7.2.1 The temporary air cooler unit is to be delivered by lorry to a designated location.
7.2.2 The temporary air cooler will be tested for performance before being assigned to its
designated service area.
7.2.3 The area effected after AHU shutdown is located and the nearest power supply is
to be identified accordingly.
7.2.4 The portable DB is to be inspected before plug in to the power supply.
7.2.5 The temporary air cooler's water compartment is filled with water from the nearest
toilet.
7.2.6 To avoid electric shock and water drip on the floor, the temporary air cooler should
be wiped clean of any water drip.
7.2.7 Place a portable tray under the temporary air cooler to avoid any water leakage
dripping on to the floor
7.2.8 The temporary air cooler is to be plug in to the portable DB and if the any
crossover cable from the power source, the cable is to be taped tidily to the floor to
avoid any trip and fall incident.
7.2.9 The temporary is then switched on to maintain the temperature throughout the area
while improvement work is commencing.
7.2.10 After the improvement work is finished, the temporary air cooler is to be turned off
and allocated to the next location.
7.2.11 The procedure from 3.1.1 to 3.1.10 is repeated for the next location.
1) Photograph Report
2) Physical S-curve
3)
6.0 APPENDIX
List down the necessary document and attached together with method statement.
1) Product Data Sheet
2) Inspection Checklist
3) HIRARC
WORK METHOD STATEMENT
(WMS)
INSPECTION CHECKLIST
TRADE: TEMPORARY AIR COOLER DATE:
AREA: TIME:
PRELIMINARY INSPECTION
NO. DESCRIPTION OK NOT OK REMARK
1. To identify nearest power supply
2. To inform relevant party for power supply usage
3. To identify suitable location on the area for air
cooler placement.
EQUIPMENT INSPECTION
NO. DESCRIPTION OK NOT OK REMARK
1. The Air Cooler is in good condition
2. The Portable DB is Working properly
3. Display on temporary air cooler can be see
clearly
4. Water is filled in the water compartment
5. No sign of water drip on Air Cooler
OVERALL REMARK: