a L3 CO1 [6M]
A company owns two flour mills viz. A and B, which have different
2 production capacities for high, medium and low-quality flour. The
company has entered a contract to supply flour to a firm every month
with at least 8, 12 and 24 quintals of high, medium and low quality
respectively. It costs the company Rs.2000 and Rs.1500 per day to run
b L2 CO1 [6M]
mill A and B respectively. On a day, mill A produces 6, 2 and 4 quintals
of high, medium and low-quality flour, mill B produces 2, 4 and 12
quintals of high, medium and low quality flour respectively. How many
days per month should each mill be operated in order to meet the
contract order most economically? Formulate the LPP.
OR
3 a Solve the following problem graphically L3 CO1 [8M]
Max Z= -X1+2X2
subject to X1-X2≤-1
-0.5X1+X2≤2,
X1,X2≥0
b Explain the process of simplex method to find LPP? L3 CO1 [4M]
Find out the IBFS by Vogel’s Approximation Method
Distribution centers
Plants 1 2 3 4
a L3 CO2 [6M]
1 2 3 11 7
2 1 0 6 1
3 5 8 15 9
Four new machines M1,M2,M3,and M4 are to be installed in a machine
shop. There are 5 vacant places A,B,C,D and E available. Because of
4 limited space, machine M2 cannot be placed at C and M3 cannot be
placed at A. Cij, the assignment cost of machine ‘i’ to place ‘j’ in
rupees is shown below.
b A B C D E L3 CO2 [6M]
M1 4 6 10 5 6
M2 7 4 - 5 4
M3 - 6 9 6 2
M4 9 3 7 2 3
Find the optimal assignment schedule
OR
Solve the following cost minimizing transportation problem and find
out IBFS by VAM
a L3 CO2 [6M]
OR
1 a For the following data, draw network. Find the critical path, slack time L3 CO5 [12M]
1 after calculating the earliest expected time and the latest allowable time