1. A chemical firm produces automobile cleaner “A” and polisher “B” realizes a profit CO L
1 3
of Rs.10 on each unit of “A” and Rs.30 on each unit of “B”. Both products require
processing through the same machines M 1 and M2. But “A” requires 4hrs on M 1 and
8hrs on machine M2 where as “B” requires 6hrs per unit on machine M 1 and 4hrs
per unit on machine M2. The available capacities are 12hrs of M 1 and 16hrs of
machine M2. Assuming that demand exists for both the products, how many units
of product “A” and product “B” should be produced to realize the optimum profit.
Solve graphically.
2. Solve the following LPP with big M Simplex method. CO L
1 3
Minimize Z=-6x-4y
S/t 2x+3y≤30; 3x+2y≤ 24; x+y≥3 and x,y ≥0

3. Solve the following LPP using two-phase simplexmethod. CO L


1 2
Minimize, Z =2x1+x2
Subject to, 3x1 + x2 = 3; 4x1 +3x3 > 6; x1+ 2x2 < 4;x1, x2, > 0

4. a) Describe the scope of OR. CO L


1 1
b) Summarize North West Corner Rule used in Transportation Problems. C02 L
1
5. A steel company has three open hearth furnaces and five rolling mills.The CO L
2 3
transportation costs (rupees) for shipping steel from furnaces to rolling mills are
given below. Determine the optimum shipping schedule and the total cost of
transportation.

Mills→ M1 M2 M3 M4 M5 Supply
Furnaces

F1 4 2 3 2 6 8
F2 5 4 5 2 1 12
F3 6 5 4 7 7 14
Demand 4 4 6 8 8
6. A manager has 4 jobs on hand to be assigned to 3 of his clerical staff. Clerical staff CO L
2 3
differs in efficiency. The efficiency is a measure of time taken by them to do various
jobs. The manager wants to assign the duty to his staff, so that the total time taken
by the staff should be minimum. The matrix given below shows the time taken by
each person to do a particular job. Help the manager in assigning the jobs to the
personnel.

Jobs Men (time taken to do job in hrs.)


X Y Z
A 10 27 16
B 14 28 7
C 36 21 16
D 19 31 21