Professional Documents
Culture Documents
Allowance
User Manual 2021
Copyright
This manual is intended for use as a working document for users of RIB product
families. The procedures described in this document and the products belonging to
them are the property of RIB Software GmbH.
We reserve the right to change the information in this document without prior no-
tice, and the contents pose no obligation to the RIB Software GmbH. The software
described in this document is provided in conjunction with a licence agreement.
All information is given without warranty. Reproduction or transfer of this document,
or parts of it, is only permitted with the explicit written permission of RIB Software
GmbH.
With respect to liability for the software described here, please refer to our soft-
ware contract conditions.
Copyright RIB Software GmbH
Published by:
Table of content
Before you begin... ................................................................................. 5
2 Allowance configuration...................................................................... 11
2.1 Basic data (configuration/properties)...................................................... 11
2.2 Cost Portions .......................................................................................... 15
3 Allowance method................................................................................ 16
3.1 Calculation of the unit prices .................................................................. 16
3.2 Allowance method with allowance area.................................................. 17
3.2.1 Areawise allowance without area balancing........................................... 17
3.2.2 Areawise allowance with area balancing................................................ 20
3.2.3 Major BoQ areas in the area-wide allowance......................................... 22
3.2.4 Function in both allowance procedures .................................................. 25
3.2.5 Table of markups and DCMs in the two-step allowance ........................ 28
3.2.6 Table of markups and DCMs in the single-step allowance..................... 31
3.2.7 Displays in both allowance methods ...................................................... 33
3.2.8 Allowance by cost portions ..................................................................... 42
3.2.9 Allowance with markup splitting.............................................................. 43
3.3 Allowance method with classifications.................................................... 45
3.3.1 Create classification for allowances via catalog classifications .............. 45
3.3.2 Using the classification catalog for allowances ...................................... 46
3.3.3 Assigning classification elements ........................................................... 46
4 Print ....................................................................................................... 47
4.1 Print options............................................................................................ 47
4.1.1 Cost Codes in Allowances Sheet ........................................................... 47
4.1.2 Allowances Sheet ................................................................................... 47
Icon Meaning
Safety instructions
must be read. They contain warnings which must not be ignored.
Notes
contain important information such as exceptions or special cases.
Working steps
are instructions that should be followed in the given sequence.
Tips
facilitate your work.
Examples
relate to work steps or serve to clarify relationships.
Troubleshooting
deals with a problem and its solution.
Please send any suggestions and wishes regarding our documentation and online
help to the respective hotline.
This dialog box appears if you have changed the default values for markup
rates.
Here, select how the new values for G&A, R+P and AM should be copied in exist-
ing data:
Do not adopt
The new default values are not adopted in existing data.
Example:
If only the values for G&A have been changed, only the values for GC are trans-
ferred to the allowance.
If other values, e.g. values for G&A, were previously changed with the option Not
apply, they will not be changed in the allowance.
Overwrite all
All existing values are overwritten with the new default values.
Click OK to confirm the selection.
name
Shows the name of the estimate document.
You can define any number of allowance variants in a project, one of which is
selected for the price calculation.
Add
Click on this button to generate a new allowance (see 'Create New Allowance').
Open
Click on this button to open the allowance selected in the Allowance window for
editing (you can also do this by double-clicking on an allowance). See "Allowance
Method" for more on how to edit the allowance.
Copy
Click on this button to copy the selected allowance. The copy is inserted in the list
as an unnamed allowance.
Delete
Click on this button to delete the selected allowance.
WARNING
You cannot undo this action!
properties
Click on this button to open the Allowance Properties dialog box. You can edit the
properties of the selected allowances in this dialog box. See "Basic Data" (Config-
uration/Properties).
Print
Click on this button to open the dialog box for printing the selected allowance.
See also
2 Direct cost markups and price calculation [} 50]
2 Determining the direct cost markups (DCM) [} 52]
2 Print [} 47]
a) In the System Options you can determine which allowance methods are
offered here (Estimate - Allowances - Allowance Methods).
b) Simple Allowance is always part of the licence for the estimate.
c) However, Areawise Allowance is part of a separate licence.
Creating an allowance
1. Select the estimate document in the structure of the project alternative.
2. Activate the Allowances property.
3. Click Add.
Since the creation of an allowance requires an evaluation of the cost details,
the program displays a message to this effect.
Click OK to confirm this.
4. If you have set in the System Options that several allowance methods should
be available for selection, the New Allowance dialog box is displayed. Here, se-
lect the allowance method.
– simple allowance
– allowance areawise
If only one allowance method is available, a new allowance is immediately cre-
ated using the available method.
Select the desired method.
5. Click OK.
The selection is inserted with the description Unnamed Allowance in the win-
dow of defined allowances.
You can change the name of the allowance by selecting it and pressing <F2>. De-
lete the existing text and enter the desired description.
Features
The following allowance feature must be considered when displaying the cost
totals (DJC and GC):
▪ The costs total which is shown on a hierarchy is not the complete costs total of
this hierarchy. It is only the total of the direct costs of this hierarchy and all sub-
ordinated shares which were not displayed explicitly!
▪ This type of representation is important for the entry of the markups!
Entered markups have an effect only on the amounts shown in the same line.
This means, for example:
– The major cost code is generally surcharged at 10% AGB. This applies to
Cost Code 2 itself and all subordinate cost codes that are not explicitly
shown in this dialog.
– Only the cost items 21 and 24 from this range with (with 8%).
▪ The total of all costs shown in the column is the project grand total.
▪ You can also select multiple cost codes at once to delete them from under-
neath the major cost code level.
2 Allowance configuration
In the allowance configuration in the Master project, you can set the defaults for a
new allowance in the project.
Open the Allowance Configuration document in Configurations in the project struc-
ture.
Basic Data is displayed.
When you create a new project, the allowance configuration set here is copied into
the new project.
In the System Options you can set whether the allowance configuration should
be visible in the project or not (Estimate - Allowance - Basic Data).
Name
The Allowance Configuration entry is shown here in the Allowance Configuration.
This entry cannot be changed.
The name of the allowance is shown here in the Properties of the allowance. You
can change the name here, if required.
Type
Only for the Properties of the Allowance window.
Shows the allowance type according to your selection when creating the allowance
In the Job Estimate, main tables (positions) as well as in the element tables, the al-
lowance values for GC, AM, R&P, G&A can be displayed. This applies to the fol-
lowing allowance types:
In the total job cost evaluation, the values for GC, G&A, R&P and AM can be out-
put in the format blocks of the item list (item and approach line). To do this, activate
in the Print Options, tab Values, section Planned G&A/Planned AM, the option
Analog Allowance.
▪ Single-step Allowance
Only for the Properties of the Allowance window.
Here, you can specify whether the allowance is single-step or two-step. The dif-
ference between the single-step and the two-step allowance is described in
'Determining the direct cost markups (DCM)'.
If the type of the area-wide allowance has been selected, then it can still be set
so that the DCMs for GC and G&A/R+P/AM are combined, i.e. so that it be-
haves like the single-step allowance in post-processing (see "Interventions in
the unit rates and balancing of the deficits"). However, this selection can still be
made individually in the open allowance; here, it is only a suggestion.
Details on this can be found under "Combined or separate post-processing of
the DCMs".
▪ Recalculate direct job costs after adding or deleting a cost code
This function recalculates the DJCs if you add or delete a cost code. If you de-
activate this function, no recalculation occurs.
▪ DCM based on WQ/AQ Quantity
The allowance procedures can calculate the DCMs based on BoQ or AQ
quantities (see "Unequal markups for G&A/R+P" in the two-step allowance).
However, this selection can still be made individually in the allowance; here, it
is only a suggestion.
▪ Conversion from G&&A, R&&P, AM
You can select various options from a selection list. The numerical values are
only symbolic in purpose.
– GA + AM + R+P: 8+3+2 = 8.00+2.00+3.00 = 13.00
– G&A+AM+RP: 8+3+2 = 8.00+3.00+ 2.22 = 13.22
– G&A+AM+RP: 8+3+2 = 13 / (100 - 13) = 14.94
– GA + AM + R+P: 8+3+2 = 8.70+3.09+2.04 = 13.83
– G&A+RP+AM: 8+2+3 = 11.11+3.00+0.33 = 14.44
– GA + AM + R+P: 8+3+2 = 8.00+3.00+2.27 = 13.27
– GA + AM + R+P: 8+3+2 = 8.00+3.24+2.27 = 13.51
– GA + AM + R+P: 8+3+2 = 8.00+3.34+2.27 = 13.61
– GA + AM + R+P: 8+3+2 = 8.00+3.24+2.22 = 13.46
Here, see also "Calculation of the amounts for G&A, R+P and AM, as well as
the DCM".
▪ Treat DW/T+M items like
Here you can select how the costs of the daywork items are included in the al-
lowance and with which DCMs (direct cost markups) the prices of the daywork
items are calculated. You can select the following options from a selection list:
– Standard item
Daywork item is treated like a standard item.
– Awarded Alternative Item
Daywork item is treated like an awarded alternative item.
– Optional Item with IT
Daywork item is treated like an optional item with IT.
Markups
The following fields are available to you here for the Allowance Configuration and
the Properties of the allowance:
▪ Factor GA
This %-rate is proposed as a markup for general and administration costs.
▪ Factor AM
This %-rate is proposed as additional markup.
▪ Factor R+P
This %-rate is proposed as a markup for risk and profit.
You can change these values for the currently selected allowance (variant) in
the Properties of the allowance.
OK and Cancel are not available to you in the Allowance Configuration. The val-
ues of the allowance configuration are accepted when you close the window.
See also
2 Unequal markups for GA/R+P in the two-step allowance [} 61]
2 Determining the direct cost markups (DCM) [} 52]
2 Interventions in the unit rates and balancing of the deficits [} 56]
2 Combined or separate post-processing of the DCMs [} 67]
2 GA + AM + R+P: 8+3+2 = 8.00+2.00+3.00 = 13.00 [} 78]
2 G&A+AM+RP: 8+3+2 = 8.00+3.00+ 2.22 = 13.22 [} 78]
2 G&A+AM+RP: 8+3+2 = 13 / (100 - 13) = 14.94 [} 77]
2 GA + AM + R+P: 8+3+2 = 8.70+3.09+2.04 = 13.83 [} 77]
2 G&A+RP+AM: 8+2+3 = 11.11+3.00+0.33 = 14.44 [} 77]
2 GA + AM + R+P: 8+3+2 = 8.00+3.00+2.27 = 13.27 [} 76]
2 GA + AM + R+P: 8+3+2 = 8.00+3.24+2.27 = 13.51 [} 76]
2 GA + AM + R+P: 8+3+2 = 8.00+3.34+2.27 = 13.61 [} 76]
2 GA + AM + R+P: 8+3+2 = 8.00+3.24+2.22 = 13.46 [} 73]
2 Calculation of the amounts for GAs, R+P and AM, as well as the DCM [} 73]
2 Allowance with markup splitting [} 43]
3 Allowance method
The following descriptions require knowledge of "Direct cost markups and price
calculation" as well as "Determining the direct cost markups (DCMs)". In some
places, references are made to the corresponding sections of the theoretical ex-
planations.
You can edit the allowance via Allowances in the properties of the estimate docu-
ments. There, select the created allocation that you want to edit and click Open (al-
ternatively: double-click on an entry).
An allowance section is a set of BoQ items. Each allowance section in a main BoQ
can receive different final markups. The allowance sections are defined by ranges
of reference numbers. Following allowance methods are available:
▪ Areawise allowance without area balancing
▪ Areawise allowance with area balancing
▪ Areawise estimate by markup
In addition to these standard procedures, you can link BoQ items to flags of an
classification catalog and thus use the following allowance methods:
▪ Allowance areawise without Area Balancing via Classifications
▪ Allowance areawise with Area Balancing via Classifications
▪ Estimate-by-Markup areawise via Classifications
See also
2 Direct cost markups and price calculation [} 50]
2 Determining the direct cost markups (DCM) [} 52]
If changes are made in the cost estimate, then the unit rates are first calculated
and displayed there due to the present state of the DCM. These DCMs do not
change at first, i.e. the displayed prices do not correspond to the final state, at
least for the estimate using the grand total, since changes in the cost estimate
in turn result in new DCMs. However, the DCMs are only updated if either the
allowance is reopened or recalculated or if the tender is printed. In the latter
case, the activated allowance is automatically calculated before the unit rates
are calculated.
See also
2 Direct cost markups and price calculation [} 50]
2 Determining the direct cost markups (DCM) [} 52]
See also
2 Basic information on the area-wide allowance [} 54]
2 Areawise allowance with area balancing [} 20]
WARNING
In Allowance, the respective table only shows the values of the major BoQ area
Remaining. The totals visible in the upper part of the window are always based
on the entire project.
See also
2 Table of markups and DCMs in the two-step allowance [} 28]
See also
2 Basic information on the area-wide allowance [} 54]
2 Areawise allowance with area balancing [} 20]
WARNING
In Allowance, the respective table only shows the values of the major BoQ area
Remaining. The totals visible in the upper part of the window are always based
on the entire project.
See also
2 Table of markups and DCMs in the two-step allowance [} 28]
See also
2 Basic information on the area-wide allowance [} 54]
2 Definition of major BoQ areas and assignment of BoQ areas [} 22]
2 Define allowance section [} 23]
2 Assign BoQ sections [} 23]
See also
2 Determining the direct cost markups (DCM) [} 52]
2 Table of markups and DCMs in the two-step allowance [} 28]
3.2.2.2 Editing the markups and DCMs for major BoQ areas
The markups for GA, R+P and AM can be individually entered for each major BoQ
section in BoQ Areas of the lower table, if this makes sense. The program initially
suggests the values from the Allowance in all areas. These markups are normally
left uniform across all areas.
In terms of building construction, different markup rates for GA, R+P and AM
only make sense for areas, the turnover of which is followed separately later
and with different rates for GA.
Different rates for GA, R+P and AM are not as important as defining fixed DCMs in
individual areas, either for all cost codes or only for particular ones. In this way, for
example, you can define a major BoQ area with all services which are executed
See also
2 Basic information on the area-wide allowance [} 54]
2 Definition of major BoQ areas and assignment of BoQ areas [} 22]
2 Define allowance section [} 23]
2 Assign BoQ sections [} 23]
See also
2 Determining the direct cost markups (DCM) [} 52]
2 Table of markups and DCMs in the two-step allowance [} 28]
3.2.2.2 Editing the markups and DCMs for major BoQ areas
The markups for GA, R+P and AM can be individually entered for each major BoQ
section in BoQ Areas of the lower table, if this makes sense. The program initially
suggests the values from the Allowance in all areas. These markups are normally
left uniform across all areas.
In terms of building construction, different markup rates for GA, R+P and AM
only make sense for areas, the turnover of which is followed separately later
and with different rates for GA.
Different rates for GA, R+P and AM are not as important as defining fixed DCMs in
individual areas, either for all cost codes or only for particular ones. In this way, for
example, you can define a major BoQ area with all services which are executed
early on, and assign particularly high DCMs to this area. This would have the effect
that the liquidity of the construction site would be improved at the start, without the
grand total changing.
The DCM is specified separately for GA, R+P, AM and GC. From this, the program
calculates the allowance amount, which is then fixed and assigned. The remaining
allowance amount of the entire project is now distributed to all cost codes of all
areas where no fixed DCMs have been defined. The calculation is balanced
between the major BoQ areas. The name for this variant of the allowance was de-
rived based on this.
For editing the markups for GA, R+P and AM and the DCMs, see the table of
markups and DCMs in the two-step allowance.
You are also shown the DCMs on AA in the table of allowance sections. There, you
can define fixed DCMs on AAs, which of course only makes sense in the allowance
sections where there is an amount for AA.
WARNING
In Allowance the table of DCMs only shows the values of the major BoQ
areaRemaining . The totals visible in the upper part of the window are always
based on the entire project.
See also
2 Table of markups and DCMs in the two-step allowance [} 28]
If no areas are defined, the entire project is the allowance area. In this case, you
only work in Allowance; the DJCs in the markup table are then also the values
from the entire project.
See also
2 Markups on GCs [} 20]
2 GC area for optional items [} 21]
See also
2 Basic information on the area-wide allowance [} 54]
The sections of the BoQ which are not assigned to specially defined allowance
sections automatically belong to the Remaining allowance section, which al-
ways exists. If no special allowance sections are defined, the Remaining allow-
ance section is the entire BoQ.
If you name reference numbers in another BoQ area which are already con-
tained in another BoQ area of the same allowance area or a different allowance
area, you are shown a message to this effect ("overlapping areas"). You must
then correct this.
6. To obtain the totals for the allowance area, click Start | Actions | Calculate
totals. The recalculation message is then shown. You will then find the DJCs of
the assigned BoQ areas under the new allowance area. The same DJCs are
calculated from the Remaining area at the same time.
See also
2 Deleting major BoQ areas [} 24]
As a requirement, a GC area must be defined for optional items and this must be
selected as the deciding area for optional items. In this case, GCs for optional
items are calculated from the allowance of the optional GCs to the costs of the op-
tional and daywork items.
See also
2 Areawise allowance with area balancing [} 20]
2 Areawise allowance without area balancing [} 17]
This function is only available to you in the area-wide allowance without area
balancing.
See also
2 Areawise allowance without area balancing [} 17]
If you activate this function, differences in items with fixed prices in relation to the
calculated UR are offset against the amount of the direct cost markup, i.e. the cor-
rected DCM is allocated. In this case, fixed prices in standard items have no effect
on the tender total.
If you deactivate this function, the calculated balancing is removed again, i.e. the
original DCM is allocated again and the fixed price will change the tender total.
How this function is preset when the allowance is opened depends on the setting
under Properties (in Allowances in the properties of the estimate).
Shows the tender total based on the calculation of the Tender list, i.e. calculates
from the total of the ITs. There are differences in the rounding of the unit rates of
the items between the tender total according to the allowance and the tender total
from the total of the ITs. The allowance calculates the tender total via Total costs +
direct cost markups, i.e. without intermediate rounding.
You will be asked whether the determined prices should be transferred to the BoQ.
▪ If you confirm with Yes, the currently determined prices are transferred to the
BoQ.
▪ If you answer with No, the prices are not transferred to the BoQ.
WARNING
If the prices in the BoQ are not up-to-date, this can lead to an incorrect result.
You should therefore transfer the data to ensure that the BoQ always contains
the current price.
The Tender Total According To BoQ dialog box is shown for information purposes.
You can also activate this function with <F7> or via the context menu.
If the calculation of the GC-DCMs for optional items (Calculate GC Factors For
Optional Items) is activated under Options (only possible in Extended Allow-
ance), the command cannot be implemented. The program shows a corres-
ponding message.
3.2.4.2.6 Activate
Activates the allowance for the calculation of the tender prices. At the same time,
this allowance is entered as the active allowance in Allowance of the base data of
the estimate.
Recalculates the allowance. Since the analysis of the cost details may take some
time, you will be shown a message to this effect. You may confirm or cancel.
The specified markups for a cost code apply to all subordinate cost codes, until
new markups are set for a subordinate cost code.
Amounts and/or values are shown/entered in the lower table, sorted by (major)
cost code.
You can insert a new line via Start | New or New in the context menu, and insert
any new cost code subordinate to a major cost code by directly entering the code
or via <F3>.
You can also delete lines with subordinate CoCs.
CoC
Shows the code of the cost code. Initially, all major cost codes are shown.
Description
Shows the description of the cost code.
DJC
Shows the total of the individual costs of the work items per cost code. Only the
costs which are part of the allowance base are displayed.
GC
Shows the total of the estimated general conditions per cost code.
G&A [%]
Markup rate for general and administrative costs from the tender total or from the
total job costs, depending on the internal setting of the program. You can change
the value. The amount to be allocated for general and administrative costs is calcu-
lated with this markup rate.
R+P [%]
Markup rate for risk and profit from the tender total or from the total job costs, de-
pending on the internal setting of the program. You can change the value. The
amount to be allocated for risk and profit is calculated with this markup rate.
AM [%]
Markup rate for additional markup from the tender total or from the total job costs,
depending on the internal setting of the program. You can change the value. The
amount to be allocated for additional markup (e.g. for technical costs) is calculated
with this markup rate.
GRA [%]
Shows the combined percentage for general and administrative costs, risk and
profit and additional markup (GA[%] + RP[%] + AM[%]) on the total job costs. The
combined percentage is calculated according to the algorithm specified in the
Properties dialog box.
DJC (O)
DJC of the optional items and the daywork items.
WARNING
All non-standard items receive the DCM for GA + RP + AM of the standard
items. Only the DCM for GC on optional and daywork items can be influenced.
See also
2 Predefined DCMs on any cost codes [} 66]
2 Calculation of the amounts for GAs, R+P and AM, as well as the DCM [} 73]
2 Evaluation of the direct job costs (DJC) [} 81]
2 Combined or separate post-processing of the DCMs [} 67]
2 DCMs for non-standard items without ITs in the single-step allowance [} 53]
2 GCs for optional items in the advanced allowance [} 52]
– No
For the major CoC, the costs are then reduced to the costs of the new line.
In this case, you must click Start | Actions | Calculate totals after accepting
all new marked-up cost codes.
The CoC is inserted in the line after the major CoC to which it belongs. For the ma-
jor CoC, the costs are then reduced to the costs of the new line.
CoC
Shows the code of the cost code. Initially, all major cost codes are shown.
The specified markups for a cost code apply to all subordinate cost codes, until
new markups are set for a subordinate cost code.
Description
Shows the description of the cost code.
DJC (O)
DJC of the optional items and the daywork items.
See also
2 Create or delete cost code line [} 30]
2 Predefined DCMs on any cost codes [} 66]
2 Calculation of the amounts for GAs, R+P and AM, as well as the DCM [} 73]
2 Evaluation of the direct job costs (DJC) [} 81]
2 Combined or separate post-processing of the DCMs [} 67]
2 DCMs for optional items in the single-step allowance [} 53]
2 GCs for optional items in the advanced allowance [} 52]
See also
2 Table of markups and DCMs in the single-step allowance [} 31]
Options
The following setting options are available to you via drop-down lists:
▪ Allowance based on BoQ quantities
▪ Display of totals for BoQ quantities
The DCMs are calculated based on the costs with BoQ quantities. All totals are
shown with these factors and based on the BoQ quantities. The tender can be
created with the DCMs and totals of this setting.
In this setting, the Display drop-down list is hidden and cannot be modified.
WARNING
The setting of the active allowance present at this point is always included when
calculating the tender prices. If in doubt, check again whether you have set the
quantity base you actually want to use for calculating the DCMs in the first field.
If you close the allowance in this setting (both window lists set to AQ quantities),
then the calculation of the tender total for BoQ quantities becomes active again.
Single Step
Only for area-wide allowance
Enables to switch between single-step and two-step allowance.
FM on AA
Only for area-wide allowance.
The current valid percentage value for the remaining major BoQ area is shown
here.
CUR
The currency shown is normally the estimate currency in the properties of the es-
timate, unless you have changed the currency unit via Properties in Allowances.
3.2.7.2.1 Costs
DJC (normal)
Costs of standard items excl. items with the fixed price flag and surcharge-free
items.
DJC (FP)
Costs of standard items with fixed price flag (incl. FP + SF).
DJC (AM)
Costs of standard items with surcharge-free feature, but without items with FP + SF
feature.
GC
Costs estimated in the GC BoQ.
TJC
Sum of DJC (normal), DJC (FP), and DJC (GC) fields.
DJC (NonStd)
Costs of all non-standard items with IT.
DJC TOT 2
Sum of TJC and DJC (NonStd) fields.
3.2.7.2.2 Hours
Hrs. (normal)
Costs for standard items excl. items with the fixed price flag and surcharge-free
items.
Hrs. (FP)
Hours for standard items with fixed price flag (incl. FP + SF).
Hrs. (nM)
Hours for/costs of standard items with surcharge-free feature, but without items
with FP + SF feature.
Hrs. GC
Hours estimated in the GC BoQ.
Hrs.-TOT 1
Sum of Hrs. (normal), Hrs. (FP), and Hrs. (GC) fields.
Hrs. (NonStd)
Hours for all non-standard items with IT.
Hrs.-TOT 2
Sum of Hrs. TOT 1 and Hrs. (NonStd) fields.
3.2.7.2.3 Allowance
For area-wide allowance with area balancing, there is a separate tab for areas with
the area evaluations.
AA
Total advanced allowance from the items.
GC (remaining)
Calculated GC minus AA.
GC
Calculated GC minus AA.
G&A
Total of general and administrative costs from allowance base DJC.
R&P + AM
Total risk & profit from the DJC of the allowance base + total additional markup
from the DJC of the allowance base (see calculation of the amounts for G&A, R&P
and AM, as well as the DCM).
Est. Allw
Estimated allowance amount based on the allowance base: GC + GA + RP + AM
Def. + MM
Total from:
Deficit from the prices of surcharge items
+ items with fixed price
+ total of the manual markups for the items.
Eff. allow.
Effective contained allowance amount, not taking into account the non-standard
items:
= Est. Allow. + Deficit (S-Items) + other Def.+ MM
See also
2 Calculation of the amounts for GAs, R+P and AM, as well as the DCM [} 73]
2 Interventions in the unit rates and balancing of the deficits [} 56]
3.2.7.2.4 Tender
For area-wide allowance with area balancing, there is a separate tab for areas with
the area evaluations.
TJC (wo.nM,Inhouse)
Total job costs without the portions of the items with no markup and the costs with
the characteristic own amounts (see "Catalogs" documentation, costs from non-
standard items).
GA + RP + AM
Total of the corresponding values from the Allowance column
Inhouse + nM-Items
Total:
Costs with the flag Inhouse but without portions from no markup items
+DJC of all no markup items incl. FP + nM (see Documentation "Catalogs").
Total
Total of the corresponding values from the column Allowance
Def. + MM
= Def.(S-items) + other def. + MM (from the Allowance column)
T Total 1
Tender total without non-standard items with ITs
IT (NonStd)
Tender total of the non-standard items with IT (DJC + DCM)
T Total 2
Tender total incl. non-standard items with IT
3.2.7.2.5 Margin
For non-activated Allowances, it offers the Tender Total 2 sum. For activated Al-
lowances it offers the Total sum according to the BoQ. Also Costs are shown.
The difference is shown as the margin in amount and as a percentage in relation to
the costs and the tender total.
DJC (Std)
Costs of standard items excl. items with the fixed price flag and surcharge-free
items.
DJC (FP)
Costs of standard items with fixed price flag (incl. FP + SF).
DJC-TOT-0
Sum of the two above values.
DJC (AM)
Costs of standard items with surcharge-free feature, but without items with FP +
AM feature.
DJC (N-Item)
Sum of the two above values.
GC
Costs estimated in the GC BoQ.
TJC
Sum of the two above values.
DJC (NonStd)
Costs of all non-standard items with IT.
DJC-TOT-2
Sum of the two above values.
Hrs. (normal)
Costs for standard items excl. items with the fixed price flag and surcharge-free
items.
Hrs. FP
Hours for standard items with fixed price flag (incl. FP + FS).
Hrs-TOT-0
Sum of the two above values.
Hrs. (nM)
Hours for standard items with surcharge-free feature, but without items with FP +
FS feature.
Hours (n-item)
Sum of the two above values.
Hrs. GC
Hours estimated in the GC BoQ
Hrs-TOT-1
Sum of the two above values.
Hrs. (NonStd)
Hours for all non-standard items with IT.
Hrs-TOT-2
Sum of the two above values.
AA
Total of the advanced allowance from the items
GC (remaining)
Estimated GCs minus AA
GC
Total of the estimated GCs
G&A
Total of general and administrative costs from DJC + GC
R&P
Total risk and profit from DJC + GC
AM
Total additional markup from DJC + GC
Est. Allw
Estimated allowance amount based on the allowance base: GC + GA + RP + AM
Miscellaneous deficit
Deficit from items with fixed prices
MM
Total of the amounts entered in the manual markup field of the items
Actual allowance
Effective contained allowance amount without consideration of non-standard items
= Estimated allowance + Deficit (surcharge items) + Miscellaneous deficit + MM
See also
2 Calculation of the amounts for GAs, R+P and AM, as well as the DCM [} 73]
2 Interventions in the unit rates and balancing of the deficits [} 56]
TJC (wo.nM,Inhouse)
Total job costs without the portions of the items with no markup and the costs with
the characteristic own amounts (see "Catalogs" documentation, costs from non-
standard items).
GA + RP + AM
Total of the corresponding values from the Allowance column
Total 1
Sum of the two above values.
Total 2
Sum of the three above values.
Total deficit
= Def.(S-items) + other def. + MM (from the Allowance column)
T Total 1
Tender total without non-standard items with ITs
IT (NonStd)
Tender total of the non-standard items with IT (DJC + DCM)
T Total 2
Tender total incl. non-standard items with IT
+ Discounts / Lumpsums
+ Rounding difference
Total of discounts and lump sums + total of rounding differences.
Remember that these settings affect all projects that use this master project. For
existing projects, this assignment must be repeated if you want to use allow-
ance by cost portions.
In both, the allowance configuration and the actual allowance, the markup break-
down can be activated by the option With Markup Breakdown.
In addition to the percentages, the maximum possible portions (with code and de-
scription), separated into own third-party work, can be defined in the allowance
configuration.
These values apply when creating a new allowance as default for the allowance
properties.
The actual authoritative definition of the markup breakdown then takes place in the
properties of the allowance. However, entered percentages only apply as a default
for the individual allowance cost codes. If there is a subsequent change in value,
these can be transferred to the allowance cost codes on request. However, the au-
thoritative values are managed individually for each allowance row and can also be
edited via the docking window Markup Split.
Depending on the context in which row (A&G, R&P, AM) the focus is, these portion
values are displayed. Splitting is possible for all cost code levels. The total value
can always be entered.
If a splitting is already defined, the total value is distributed in proportion to the pre-
vious breakdown.
If no splitting has yet been defined, the total value will be distributed in equal parts
to all portions. The values determined are not rounded.
The different types of markup splits are defined in the allowance configuration and
are therefore deleted from the allowance and allowance targets when you delete a
markup split from the allowance configuration. The totals will be updated accord-
ingly.
If a Sub cost code is newly used in the allowance, the markup portions for this cost
code are preassigned in accordance with the allowance properties.
The values are taken from the active allowance row and displayed in the dialog.
For copying, the corresponding value ranges (G&A, R&P, AM) can be selected. If
the call is made from a specific field (G&A, R&P, AM), this is already preselected.
When calling from other fields, all three areas are already preselected.
The destination of the copy operation can be selected for the two options, for all
sub-elements and all cost codes as well as the current and all areas. This setting of
the two options will be saved depending on the user and pre-assigned the next
time.
Evaluations
For the evaluation, a separate report type Allowance with Markup Breakdown is
available. The markup splits of the cost code rows are taken into account. A value
block is displayed for each cost code used.
When using the areawise allowance by classifications, a cost code block is output
for each area.
Each of these rows contains the classification element (= Flag mentioned in the
preliminary notes) the markup default values for G&A, R&P and additional
markup. The Markup on GC is only needed for the 'Estimate-by-Markup
areawise via Classifications'.
In an allowance that has been created with this catalog the default values can
later be adjusted separately for each cost code.
To simplify work, it is recommended to create the classification in the master.
When creating a new project it can be copied into the project.
4 Print
You can also print the allowance, just like any other document in the program.
1. Switch to the project window.
2. Select the estimate document in the project structure.
3. In the properties, select Allowances.
4. Click on the desired allowance in the list.
5. Click Print in Allowances.
6. Expand the required folder and select the desired report type.
7. Configure the required print options for the selected report, if required.
8. Click Print.
If you have opened an allowance, you can print the open allowance via Application
Button | Print | Print.
Only the two print options Allowances Sheet and Cost Codes in Allowances Sheet
are described here.
Elements
The following functions are available here:
Cost codes
The following options are available here:
▪ Print CoCs which have their own allowance factors (default)
Select this option if CoCs with their own allowance factors should be printed.
▪ Print CoCs from the configuration
Select this option if CoCs from the configuration should be printed.
Page breaks
The following functions are available here:
▪ Page break before crew mix table
If you activate this function, a page break occurs before the crew mix table.
▪ Page break before table with markups and factors
This function allows you to set that this table should start on a new page. If you
deactivate this function, no page break occurs before this table.
Knowledge of the connections and effects of the direct cost markups is an im-
portant requirement for successful work.
Here, the subjects of direct cost markups (DCM) and price calculation are handled,
since the scope of the program extends well beyond the "standard" instructions.
The program offers a variety of working options based on technical concepts which
must first be explained. The respective working options can only be correctly and
successfully used in the software if you are familiar with these concepts.
The general explanations here allows the actual descriptions on how to use the
program to be kept deliberately clear and concise. For a complete understanding,
these descriptions should be read in conjunction with the instructions on how to
use the program. The theory is supported with numerical examples so that the for-
mulae can be better understood.
We recommend that you create a small project with the same numbers and
work though all steps shown in the program. You will see that the results in the
program exactly match the examples shown here.
At this point, two different methods have been mentioned, with which the direct
cost markups can either be calculated or in which they can be entered as fixed
markups. These methods are simple allowance and area-wide allowance.
Single-step allowance
In this method, the direct cost markups (DJC) for GC and GA/R+P are combined
into a single value. Therefore, only a markup amount is output as the FM (final
markup) in the item.
This method is contained in the user licence for the Tender Estimate module.
Two-step allowance
In this method, the direct cost markups (DJC) for GC and GA/R+P are handled
separately and applied successively (two-step) to the items. Both an allocated
amount for GC and an allocated amount for GA/R+P (= FM) are therefore output in
the items. Areawise allowance can also be switched to simple allowance.
This method is part of a separate user licence (Enhanced Allowance) which can
be purchased in addition to the licence for the Tender Estimate module.
Both methods can be used for both the estimate using the grand total and for the
estimate by markup.
The advanced allowance (AA) can not be used in non standard items without
IT.
5.4.2 Estimate-by-markup
If you specify fixed DCMs in all marked-up cost codes, a so-called estimate by
markup is performed. This applies for both the simple (single-step) and advanced
(two-step) allowance. Any GCs calculated in the GC-BoQ are then no longer part
of the calculation. Likewise, the introduced markups for GA, R+P or AM are no
longer relevant. Only the fixed DCMs determine the markup on the costs of the
items. The total of these item markups is a different allowance amount from the
one which would have been given via estimated GCs and entered markups for GA,
R+P, AM.
WARNING
Deficits from fixed DCMs on all marked-up cost codes cannot be balanced.
There are companies which generally work with the estimate by markup. A pro-
ject can also be started with an initial estimate by markup via the estimate using
the grand total, in order to be able to predict preliminary prices before pro-
cessing the details of the GCs and markups in the estimate of the items. In such
a case, preliminary DCMs are first entered in the allowance as fixed DCMs.
These predefined DCMs are deleted again later and replaced with calculated
DCMs by the program.
prepared here in order to assign certain portions of the GCs to the individual areas.
Here, the GC portions are either determined via percentages based on the total
GCs, or the GCs are split into areas so that a certain GC area can be assigned to a
certain BoQ area. The smallest possible unit in the BoQ and GCs is the individual
item.
Depending on the area definition and the assignment of the GCs, each area of the
BoQ to be submitted in the allowance behaves like a self-contained subproject.
The calculation algorithms described earlier apply in each individual area. There is
no balancing of allowance amounts between the areas.
▪ There is a certain area in BoQ which determined specific GCs. These GCs
should be assigned to the correct area.
▪ Only a partial award is to be expected. The GCs required for the partial award
must be determined and assigned to the actual work items under considera-
tion. A tender may need to be submitted for both the total award and the partial
award.
Stoneware pipes are listed in several items. In a surcharge item, the bidder
wants to know the costs of all fittings and requests that the bidder specify a per-
centage based on the sum of the ITs of all straight pipes. The items for the
straight pipes should be named as reference items. The IT of the surcharge
item is then: (Sum of ITs of the base items) x percentage.
The costs of surcharge items can be estimated but do not have do be. However, if
the user does not calculate DJCs, this results in an excess in the calculation, i.e. a
positive deficit which does not correspond to reality, since costs will occur. In addi-
tion, the item then does not generate an allowance amount from GA, R+P, AM and
GC, since it does not provide a contribution to the DJC total as a base variable for
calculating the FM.
There is no AA in surcharge items.
WARNING
A deficit from surcharge items cannot be balanced in the allowance.
This markup is not possible for items with fixed prices, since this would be contra-
dictory.
For an item quantity of 10.00, the tender total decreases to 100.00 due to the fixed
price. The allowance shows this difference amount if the function Balance the dif-
ference of fixed price items is not active.
If the function Balance the difference of fixed price items is activated in the allow-
ance, then the difference is interpreted as FM (GA/R+P/AM), which is included in
items in advance as a positive or negative value via the fixed prices.
Actual FM in FP item = FP - DJC - AA - (DJC x DCM for GC)
Remaining FM = (Total FM) - (Actual FM in FP item)
Actual FM = 10.00 x (112.22 - 100.00 - 0.00 x 10.00%)= 22.22
Remaining FM = 2933.33 - 22.22 = 2911.11
This amount should be allocated to the TJCs of the standard items without FPs.
Remaining TJCs = 26400.00 - 1100.00 = 25300.00
DCM for FM for remaining item = 100 x (2,911.11 / 2,5300.00) = 11.51%
Once the deficit of the fixed price items has been balanced, there is no longer an
amount in the respective field.
The tender total changes depending on whether the balancing is activated or deac-
tivated.
After the balancing, the sample item with the fixed price appears as follows (shown
using the two-step allowance):
Cost code DJC GCs TJC DCM for DCM for GA/R+P
Standard Estim- GCs in GA/R+P Amount
Items ated % in % of
on TJCs TJCs
1 – Hours/La- 10,000 1,200 11,200 10.00 20.00 2,240.00
bour
2 – Materials 9,000 200 9,200 10.00 5.00 460.00
3 – Plant 1,000 1,000 10.00 5.00 50.00
4 – Auxiliary 500 500 10.00 5.00 25.00
Labour/Trans-
port
5 – Subcon- 3,000 3,000 10.00 5.00 150.00
tractor Services
6 – Misc 500 1,000 1,500 10.00 5.00 75.00
Total 24,000 2,400 26,400 3,000.00
In this case, the GCs are included with an amount of 10% in the items per DCM for
GCs, regardless of the cost code. This way, for example, parts of the GC labour
are distributed to the other cost codes. Labour from the GCs must receive a DCM
of 20%; however, the portions in the items per DCM for GCs which are assigned to
the other CoCs only receive a DCM of 5% there, since the following formula ap-
plies for the items:
UR = [DJC + (DJC x DJC for GC)] x (100% + DCM for FM)
If the items were analysed with the above unchanged DCM after allowance of the
GCs per DCM of 10%, this would give the following project total:
A total of 3,000.00 would thus no longer result. The cause of this is that an amount
of 1,200.00 is entered in the GCs for labour which should receive a DCM of 20%,
but after the allowance, only GCs with an amount of 1,000.00 per DCM for GCs are
applied to the labour. The difference amount of 200.00 is distributed to CoCs with a
DCM of only 5%. The following is thus missing:
(1200.00 - 1000.00) x (20% - 5%) = 30.00
For this error to be balanced, the DCM for GA/R+P/AM must be converted so as to
give a tender total of 3,000.00 again.
The solution is given by the following condition:
The amount for GA/R+P/AM which results when using the entered markup rates on
DJCs and GCs according to their original cost code assignment must be identical
to the amount which results when using a converted DCM on DJCs and GCs in the
items.
If we label the DCMs before correction of the error as FM1 (20% and 5% in the ex-
ample) and the corrected value as FM2 and set FM2 = (factor) x FM1, then the
above condition can be expressed as a formula as follows, taking the AA and the
average DCM for AA into consideration according to the previous chapter:
(DJC + GCK) x FM1 = Factor [ (DJC x FM1) + (DJC x DJCGC x FM1 ) + (AA x
Average DCMGC)]
Factor = [ (DJC + GC) x FM1] / [ (DJC x FM1) + (DJC x DJCGC x FM1 ) + (AA x
Average DJCGC)]
Factor = [(10000 + 2000) x 20% + (14000 + 1200) x 5%] / [10000 x (100% + 10%)
x 20% + 14000 x (100% + 10%) x 5%)]
Factor = (2240 + 760) / (2200 + 770) = 3000 / 2970 = 1.010101
This factor should be applied to the FM1 of 20% and 5%, which will cause the pro-
ject result to be displayed correctly again:
None of this is relevant in the single-step allowance, since a uniform DCM for all
cost codes is immediately determined there by immediate allowance of the total al-
lowance amount (GC + GA/R+P/AM) to the total of all cost codes.
In the two-step allowance, this also ceases to be relevant wherever a fixed DCM is
specified. In this case too, the remaining amount of GA/R+P/AM is allocated to the
costs of all remaining cost codes, which causes the calculation to be automatically
balanced in the average remaining DCM. The same also applies if the deficit is bal-
anced by fixed prices, which also results in an average DCM for all cost codes.
See also
2 Predefined DCMs on any cost codes [} 66]
2 Interventions in the unit rates and balancing of the deficits [} 56]
WARNING
Advanced allowance is part of the GC amount!
In our project example, we will assume that an amount of 400.00 per AA has been
assigned to our sample item. At the same time, we will assume the original state of
the DCMs, i.e. an equal DCM on all cost codes.
The estimated GCs had an amount of 2,400.00. This means
Remaining GCs = GCs – AA = 2,400.00 – 400.00 = 2,000.00.
This gives an equal DCM for GC as follows:
DCM for remaining GCs = 100 x (remaining GCs)/(DJCs)
DCM for remaining GCs = 100 x (2,000.00) / (24,000.00) = 8.33 %
Our project now appears as follows:
Since the AA is equal to GC, the DCM for FM also effects the AA.
Our sample item, which contains the amount for AA of 40.00/UoM, appears as fol-
lows:
WARNING
Since the AA is part of the GCs, the AA in the item receives the same DCM as
the GCs do.
Given this connection, an anomaly occurs in the two-step allowance if the DCMs
per cost code are not identical, as is the case in the above example. As long as the
DCM for FM is identical in all cost codes, the AA also receives the same DCM. Let
us assume that the DCMs in our project appear as follows.
In this case, it is no longer clear which DCM should be used for the AA. If a GC
portion is moved per AA, it can no longer be determined which cost code portion of
the GC is meant. It is a portion from each CoC used in the GCs. The amount of the
DCM on the GCs must always be identical before and after applying the AA, or
else the tender total would change.
We will now assume that the cost code for reinforced concrete, which is a subor-
dinate cost code of the major material cost code, should receive a higher DCM
than the remaining materials. The costs under the cost code Reinforced concrete
are 2,000.00.
Create a new line in the allowances sheet and select the desired cost code;
here, this is the cost code 24.
The separate post-processing of the DCMs for GCs and GA/R+P/AM is only
possible with the two-step allowance.
The DCMs are managed separately and used separately in the calculation of the
item price, so that the allowance amounts there can also be output separately:
DJC: 100.00
GC: 10.00
FM: 12.22
UR: 122.22
For separate post-processing of the DJCs, the following applies to the items:
UR = (DJC + DJC x DJC for GC) x (100% + DCM for FM)
In the example:
UR = (100.00 + 100.00 x 10%) x (100% + 11.11%) = (122.22)
If the DCMs of the allowance are deliberately changed, this occurs separately for
the GCs and for GA/R+P/AM.
This is first shown in the example for the GCs. The labour costs should be marked
up with a fixed rate of 20% for GCs.
This determination assigns a fixed portion of the total GCs to the labour costs. The
size of the amount is calculated from the labour costs of the items (10,000.00) and
the selected DCM (20%):
DCM for GC on labour = 20% of 10,000.– = 2,000.–
From the total GCs in the amount of 2,400.–, 2,000.– have therefore already been
distributed to the labour costs. The remaining GCs should be distributed among the
remaining costs:
Remaining GCs = GCs – (GC on labour)
= 2,400.00 – 2,000.00 = 400.00
Remaining DJCs = Total DJCs–Labour DJCs
= 24,000.00 - 10,000.00 = 14,000.00
Remaining DCMs - GCs = 100 x (400 / 14000) = 2.86%
For the total of the standard items, the project now appears as follows:
In this state, all items with a high labour portion become more expensive, other
items become cheaper.
If you were to fix the direct cost markup for GCs in all cost codes, you would no
longer be in the estimate method using the grand total, but in the markup estimate
for GCs. The amount from GC markups generated via fixed DCMs can then be dif-
ferent than the amount of the estimated GC (forced excess or deficit).
The deliberate intervention per fixed DCM for GA/R+P/AM is now shown for a cost
code, where we have determined a DCM of 20% on the labour costs. At the same
time, we will again use the project state with a DCM for GCs of 10.00% equally
across all cost codes.
We thus have the following initial state:
The total amount for GA/R+P/AM on standard items has an amount of 2,933.33 in
our project example. Since the DCM for GA/R+P/AM relates to the DJCs marked
up with GCs, the labour costs from DJC + GC markup should be used as a basis!
DCM for GA/R+P/AM on labour = 20 % x 11,000.00 = 2,200.00
There thus remains
Remaining allowance for GA/R+P/AM = 2,933.33 – 2,200.00 = 733.33
This amount is split across the remaining TJCs
Remaining TJCs = 26,400.00 – 11,000.00 = 15,400.00
This gives a DCM for the remaining cost codes of
DCM for remaining GA/R+P/AM = 100 x(733.33) / (15,400.00)= 4.76 %
In this state, all items with a high labour portion become more expensive, other
items become cheaper.
If you were to fix the direct cost markup for GA/R+P in all cost codes, you would no
longer be in the estimate method using the grand total, but in the markup estimate,
i.e. the output values of 8% + 2% would no longer have any effect.
The following example shows the effects of manipulating both final markups; 20%
is set as the DCM on labour, both for GCs and DJCs
However, you can also predefine DCMs for particular cost codes in the allowance
procedure and let the program calculate the DCMs for the other cost codes. Let us
assume that the labour costs should receive a fixed DCM of 30%. This task as-
signs a certain partial amount of the total allowance amount specifically to the la-
bour costs.
Determined partial amount of the allowance = (Labour costs) x 30%
= 10,000.00 x 30%
= 3,000.00
Remaining allowance amount = 5,333.33 – 3,000.00 = 2,333.33
The remaining DCMs result from the remaining allowance amount.
Remaining DJCs = 24,000.00 – 10,000.00 = 14,000.00
Remaining DCMs = 100 x (2,333.33) / (14,000.00) = 16.67 %
For the total of the standard items, the project appears as follows:
The tender total from standard items thus has not changed, the allowance amount
is just split differently across the cost portions. Services with a high labour portion
now become more expensive, other services become cheaper.
A different price is now given in the sample item:
If you were to fix the direct cost markup for GA/R+P in all cost codes, you would no
longer be in the estimate method using the grand total, but in the markup estimate,
i.e. the output values of 8% + 2% would no longer affect the DCMs.
In the above example, the markup rates for GA and R+P have been set as 8% and
2% (not visible in the table) for all cost codes, to give a value of 11.11% converted
to TJCs in each line.
The conversion to TJC is carried out individually for each cost code (line). If the
company has defined different markup rates per cost code, this therefore also
results in different converted values per line.
The values of the first three columns can be compared with estimate details,
and the values in the fourth column are DCMs calculated from these (common
DCMs for GA/R+P/AM). The calculation of the URs of the items works with the
values of the 4th column! The amount to be allocated is calculated using the
values from the first three columns, and the values of the 4th column are results
for post-processing in the items. At the latest, this statement will become import-
ant if there is a manual adjustment of the values of the 4th column, which is also
explained in a later chapter.
To begin with, we will remain with the project state as currently shown, in which all
cost components of the DJCs and GCs (!) receive a DCM for GA/R+P/AM of 11.11
%. This applies both for standard items and all non-standard item types, as long as
the user (you) has not deliberately adjusted in individual items. The types of inter-
vention that can be made are explained further below.
The calculated item total for GA/R+P/AM is split across the individual components
as follows, shown using the project example with markups of 8 % for GA, 2 % for
R+P and 0 % for AM:
See also
The amount of the GCs is then converted to a direct job cost by allocating the total
of the GCs to the total of the DJCs of the standard items:
DJCs for GCs = 100 x (2400 / 24000) = 10.00%
If nothing is changed, a markup of 10% of the costs is applied to each cost portion
in the price calculation of the items in order to take the GCs into consideration. In
the above case, the GCs are equally distributed across all cost portions. The entire
project is then represented as follows in the total of the standard items:
The above individual amounts from the GC markup no longer have anything to do
with the costs in the individual cost codes. For example, the amount 1,000.00 is a
markup amount on the labour costs of the items, without 1,000.00 being the
amount for labour costs in GCs; this would be 1,200.00. GCs allocated per DCM at
the destination only represent "money".
As the user, you can replace the calculated DCMs with fixed DCMs for individual
cost codes, which will make the program recalculate the other remaining DCMs.
This is explained further below. To begin with, we will remain with the equally cal-
culated DCMs for GCs, as shown above.
In this case, the DJCs of all standard items receive a DCM for GCs to the amount
of 10.00 %. As long as the user (you) does not intervene, all non-standard items
also receive the same markup.
= Cost price
+ R+P (Risk and profit, estimated via a surcharge rate based on the
TJCs)
= Tender Total
When estimating the GCs to be applied, you must orient yourself as closely as pos-
sible to the actual scope. This is usually just the standard items of the enquiry. It is
not normally known whether the non-standard item types that are included are
used. The partial analysis of the DJCs is thus only important for standard items.
The precise scope of the standard items may be uncertain. In cases of doubt, at
least perform a check of the submitted quantities (= BoQ quantities) for the most
important items. The results of this quantity check are the adjusted quantities or
billing quantities (=AQ quantities), which are entered separately from the BoQ
quantities. The GCs to be estimated will thus be oriented on the scope of the
standard items for AQ quantities.
If non-standard item types are used later, the expenses in the GCs will generally
only become larger than estimated if the output volume from non-standard items
takes on a larger scope or if specific technical requirements must be created for
this. You can attempt to estimate certain GC costs for non-standard items in the
Tender Estimate module. The program enables this sort of separate consideration
and processing.
In the course of the calculation of the DCM, the estimated GC will be allocated to
the DJC. The "standard" GCs are allocated to the DJCs of the standard items, and
special GCs for optional items can be determined and allocated to the DJCs of the
optional items (the latter is only possible in the Enhanced Allowance). It is up to
you, the user, whether to select the DJCs with BoQ quantities or with AQ quantities
as the allowance base. In any case, this allowance of the GCs to the DJCs is the
reason that the DJCs of the standard items must be assessed separately from the
DJCs of the non-standard items.
For the estimate using the grand total, you will therefore know the tender total be-
fore the unit rates of the items have been determined. The direct job costs with
which the unit rates of the items can then be calculated from their DJCs are only
calculated or partially predefined afterwards. All of this preparatory work for calcu-
lating the unit rates is carried out in the Allowance.
Direct job costs are calculated according to the following principle, that amounts to
be allocated are allocated to the DJCs of the standard items.
DJCs of the standard items
= Basis for estimating the required allowance amounts
DJCs of the standard items
= Basis for allowance of the allowance amounts
= Allowance base
A direct job cost (DJC) is generally calculated as follows:
DJC in % = 100 x (Allowance amount / Allowance base)
DJC for BoQ quantity = 100 x (Allowance amount / DJC of the standard item for
BoQ quantity)
DJC for AQ quantity = 100 x (Allowance amount / DJC of the standard item for AQ
quantity)
Example of the DJC totals of all items (with deliberately small numbers)
DJC
Cost code Standard Optional Alternative DW/T+M
items items items items
1 – Hours/Labour 10,000 500 100 200
2 – Materials 9,000 300 80 100
3 – Plant 1,000 50 20 100
6 International Allowance
CoC DJC Local GC Local DJC + GC G+A R+P GRPAM G+A R+P GRPAM
+ DJC For- +GC For- Local Local Local Foreign Foreign Foreign
eign eign
1 2 3 4=2+3 5 6 7=4*(5+ 8 9 10=4*(8+
6) 9)
1 4000 2000 6000 8% 2% 600 13% 2% 900
2 6000 3000 9000 5% 5% 900 8% 2% 900
3 10000 5000 15000 4% 6% 1500 9% 1% 1500
Total 20000 10000 30000 3000 3300
GC(Local) GC(Foreign) GC
6.4.1 GC Allowance
At the request of the user (see Calculate Allowance for GC [} 85]) the following ap-
plies:
▪ GC(Local) = 4000
▪ GC(Foreign) = 6000
1. Calculating GC Factors Local
6.5 Calculate UR
But IT is:
TT_2=BoQ-Quantity(Item 1)*UR(Item 1)+BoQ-Quantity(Item 2)*UR(Item 2)
= 1*19989.61+1*16 309.61
= 36299.22
The difference between TT_1 and TT_2 is due to the fact that in the example
the factors were only calculated with 2 digits after the decimal point.
Calculation of line GC
GC on standard item = (GC Total in CoC 1) * (GC Markup Local in CoC 1)
+ (DJC Total in CoC 2) * (GC Markup Local in CoC 2)
+ (DJC Total in CoC 3) * (GC Markup Local in CoC 3)
= 4000 * 0.08 + 6000 * 0.05 + 10 000 * 0.04 = 1020
The deficit of -3000 arises from the fact that the GC was split by specifying a
percentage factor of 60% for foreign exchange.
GC(Local) GC(Foreign) GC
the splitting calculated by the program 7000 3000 10000
user-requested splitting 4000 6000 10000
PERC(Foreign) = 60 %
Difference - 3000 + 3000
All values on the Allowance Sheet Foreign are determined in the same way as the
Allowance Sheet Local.
GA 2920 1460
R+P 1280 640
AM
Advanced Allocation
FM on Advanced Allow-
ance
Total Tender Total 1 24200 12100 36300
Corporate Work
DJC of nM-Items
Total Est. Tender Total 24200 12100 36300
Manual markup
Deficit
Total Tender Total Net 36300