• Discuss the two main types of Asphalt Plants • Understand common elements of both types of asphalt plants • The Batch Plant Production Process • The Drum-Mix Production Process • Dust Control • Asphalt Plant Safety CHAPTER 5 – MANUFACTURE OF HOT MIX ASPHALT The two most popular types of plant facilities / production processes for producing HMA are called:
Batch facilities Drum-mix facilities
5.7 – BATCH FACILITIES
• The first hot mix asphalt plants were batch
facilities • They were popular in the early 1900s until the advent of drum-mixers in the 1970s • Many batch facilities still exist today even though 80 % of HMA is produced with drum- mix plants. 5.7 – BATCH FACILITIES
• Individual aggregates are proportioned from
the cold feed bins onto a single collector belt and sent to the dryer to be dried and heated • The dried & heated materials flow into a bucket elevator to be carried to the top of the batch tower and deposited onto sizing screens • The aggregate is then separated into different sizes and direct the fractionized aggregate into hot bins 5.7 – BATCH FACILITIES
• The screens in the tower determine the size of
the aggregates in the hot bins and how the blended aggregate mixture from the dryer is fractionated • Aggregates are then dried, sized and stored in the hot holding bins, for proportioning according to the mixture specified 5.7 – BATCH FACILITIES
• The mixture is made by weighing the
fractioned aggregates stored in the hot bins with an accumulative aggregate weigh hopper, positioned below the hot bins • Each predetermined fraction of material is individually weighed into the aggregate weigh hopper until the entire batch is weighed 5.4 – COMMON EQUIPMENT
• Both types of facilities have common equipment
components that operate similarly and have essentially the same functions: * Liquid binder storage tanks * Aggregate and RAP stockpiling * Cold aggregate and RAP feed bins * Aggregate and RAP conveyors * Aggregate dryers 5.4.1 – ASPHALT BINDER STORAGE TANKS • Generally stored inside insulated and heated tanks adjacent to the other plant equipment • Multiple storage tanks are common at stationary facilities and are not uncommon with portable plants • This allows the producer to keep different grades of asphalt binder properly separated • Tanks must be kept heated to maintain the asphalt binder at the proper mixing temperature • Pipes that transfer the liquid asphalt to the mixing area of the plant are insulated 5.4.2 – AGGREGATE STOCKPILING • Aggregates are delivered to plant sites by truck, rail, barge or belt conveyor directly from the aggregate source • Aggregates are usually stockpiled onsite and then fed into cold feed bins with a front end loader • A plant can also be fed directly from the stockpile by feeders under the stockpiles or by trucks dumping directly into the cold feed bins 5.4.2 – CROSS CONTAMINATION
• Materials should be kept separated from one
another by space or dividers before being loaded into the cold feed bins for mixing 5.4.2 – SUBGRADE MATERIALS
• If the materials are moved with a front end loader
the operator must ensure that the bucket does not pick up subgrade materials along with the desired aggregate • Remedy could be to have your aggregate placed on asphalt 5.4.2 – WHEEL & TRUCK CONTAMINATION
• Driving on the aggregate stockpiles
with haul trucks or stockpiling equipment can also cause contamination from materials that stick to the vehicle wheels or tracks, and should be discouraged 5.4.2 – BREAKDOWN / GRADATION CHANGE
• Materials can change in gradation if
equipment is driven on the aggregate stockpile • A thorough understanding of the aggregate materials and aggregate handling procedures must be accounted for in the design and construction process 5.4.2 – SEGREGATION / GRADATION CHANGE
• When aggregates are dropped from
a significant height or if aggregates are allowed to flow down the face of the stockpile, segregation can occur • Segregation is probably the biggest concern in stockpile management at a hot mix plant 5.4.2 – MINIMIZING STOCKPILE MOISTURE • Providing a solid draining surface under the stockpile area not only helps keep the subgrade material from contaminating the cold feed bins but also helps to keep the aggregates dry • Moisture drastically affects the production of the plant and fuel consumption • A solid sloped or paved drainage surface under the aggregate stockpile area greatly helps to achieve this objective 5.5 – AGGREGATE & RAP COLD FEED BINS • Feed bins are similar for both batch and drum mix plants • Practically all plants now use conveyors with variable speed motors located below feed bins to regulate the flow of materials to the drying drum • Variable speed belt feeds are consistent and repeatable and therefore easy to calibrate • With a drum mix plant setting the different feeder speeds actually establishes the gradation blend in the final mix 5.5 – AGGREGATE & RAP CONVEYORS • Both batch and drum mix facilities use the same style of aggregate conveyor to transfer material between the cold feed bins and the plant • Belt-type conveyors with fixed speeds • They can be fitted with scrappers or guards to minimize spillage or with wind guards to reduce the effect of the wind on belt scales 5.6 – AGGREGATE DRYER • Needed for both types of plants • It is the responsibility of the dryer to produce mix with a consistent temperature • A temperature swing greater than 6˚ to 11˚C typically affects field performance • Dryers are inclined and rotate • They function by picking up and dropping aggregate material into the hot gas stream • Inside the dryer are steel flights or lifters 5.7 – BATCH FACILITIES
• In a separate section, asphalt is weighed in a weighing
device, typically called an asphalt weigh bucket or asphalt scale • After the aggregate and the binder are weighed, the aggregates are dropped into the pugmill mixer to be blended together in the dry-mix cycle 5.7 – BATCH FACILITIES
• The dry-mix cycle is a 2 to 5 second cycle that
blends the aggregates thoroughly before the asphalt binder is added • When the dry mix cycle is completed, the asphalt is dropped into the mixer and the wet-mix cycle begins • The wet mix cycle lasts 25 to 45 seconds 5.7 – BATCH FACILITIES
• The cycle time is determined by the time required
to produce a homogeneous, well coated mix • Uniform coating of large rock mixes typically takes longer than fine mixtures • The time is usually determined subjectively by visual inspections 5.7 – BATCH FACILITIES 5.8 – DRUM MIX FACILITIES
• The continuous flow of a drum mix
plant requires the availability of stockpiled aggregate material that will meet the specifications without rescreening • The individual aggregate materials are proportioned directly from the cold feed bins to the final job-mix formula 5.8 – DRUM MIX FACILITIES • The individual aggregate materials are proportioned directly from the cold feed bins to the final job mix formula • The materials are then sent to the drum to be dried and heated • In route to the drum, the blended aggregate passes over the belt scale, which is a continuous weighing device • The plant’s control system uses the reading from the belt scale to calculate the liquid asphalt binder and other additives required for the mixture 5.8 – DRUM MIX FACILITIES
• Drum mix plants can be designed as one piece drum
mixers or with separate dryer and continuous mixer units • Both are referred to as drum mixers 5.4 – COMMON EQUIPMENT
• Plant automation is similar in both and is typically
computer controlled • The blending automation is different because of the differences between the batch and drum mix processes • Most automated plant control systems provide for multiple stored mix formulas and automatically handle all the blending, metering and mixing 5.4 – COMMON EQUIPMENT
• In both plant types, truck load out and ticketing
systems are also computerized and provide not only weight figures but also detailed project information on the load ticket 5.9 – EMISSION CONTROL & DUST COLLECTION EQUIPMENT
• Fine particles are often separated from the coarse
aggregate particles through the drying process. • These dust particles are collected primarily for environmental reasons, however they can also be reused in the asphalt mix, depending on the type of equipment used in the asphalt plant. 5.9.1 – DUST COLLECTION EQUIPMENT • There are two stages of dust collection on plant systems: • Primary dust collectors • Secondary dust collectors • Dust removed using primary collectors are usually 100% returned to the plant process. • Secondary collectors consist of either wet washers (wet scrubbers) or fabric filter collectors (baghouses). 5.9.3.2 – DUST COLLECTION EQUIPMENT – WET SCRUBBER
• Wet washers (scrubbers) add water to
the mix to make the particles heavier. Once the dust becomes wet it cannot be returned to the plant process. It is usually treated in a settling pond and the clean water is reused. 5.9.3.1 – DUST COLLECTION EQUIPMENT – BAGHOUSE
• A baghouse removes dust through a dry
filtration process. • Dusty air is passed through a fabric filter. Occasionally the flow of air is reversed which knocks the dust particles into the hopper of the baghouse. • This dust can then be either removed to the plant mix process or removed and disposed of. 5.10 – FINISHED PRODUCT STORAGE SILOS • Allow the plant to run continuously whether or not trucks are present • Silos are required for drum mix plants because the mix flows continuously from the mixing area when the plant is running and must be elevated for dispensing into trucks • Silos on batch plants allow the plant to run continuously thereby increasing daily output 5.12 – ASPHALT PLANT SAFETY • Personnel working at an asphalt plant must always be safety conscious. Potential hazards which could be encountered at an asphalt plant include: • Dust • Noise • Moving Equipment/belts • Working around Heavy Equipment • High Temperature equipment and Materials • Traffic • General Housekeeping / Tripping Hazards