ABSTRACT
The project is planned and implemented to celebrate a prom night for all students
majoring in Logistics and Supply chain management (LSCM) at Foreign Trade
University, which has just been launched for only three years, so that all generations of
students in this major can enlarge their network for good value in the future: mentor in
career path, love story, etc. This idea come from the staquo that there has been no
networking events within LSCM community in ForeignTrade University, the team
found many reasons but the two main of them are the small number attendants in the
first year of major launched and the covid-19 making waste of time as well as social
distance in the next two year. Our core team expects that this first prom night for all
intakes as well as the pioneer events will lead to some traditions for generations in our
field that can connect with their seniors and their inferiors as well. The prom will take
place at the of June – also the end of school year, at a Hall in Ho Chi Minh city, easy to
approach from the university. The price fluctuates around 200.000 VND, affordable for
these students as they are studying in high-qualified courses, which guarantee their
financial background from upper-middle income. In short, our project provides a cozy
atmosphere to relax after school time, a funny event to make an interactive bridge
between people learning the same major and gives them chances to enlarge their network
for further purposes.
1
PART 1: INTRODUCTION
In the field of Logistics and Supply Chain, networking connection remains one of the
most successful factors to achieve desired career path. At Foreign Trade University -
HCMC Campus (FTU2), the Logistics and Supply Chain Management (LSCM) major
has been launched for over 3 years since 2018. During the period of 3 years, no relevant
activities were performed to connect and improve the solidarity among students
majoring in LSCM of the 3 classes. Moreover, there was no incentive to execute the
similar events in the last 3 years due to the small number of participants for the first year
and Covid-19 pandemic in the last 2 years. Our core project team as the first ever class
majoring in LSCM finds it important and necessary to develop a prom night called ‘The
L` Night’ to fulfill the needs of networking connection and of LSCM students at FTU2
(according to our survey at FTU2). This project aims to connect the students among 3
classes through interactive activities and games. Furthermore, prom night is set to let
students freely start conversations and get to know different people in an open way. The
prom will take place at a venue hall in Ho Chi Minh City at the end of June, which is
the time when the 3 classes finish schooling and need some fun activities to relax.
2
1. Social problem
1.1 Justification
Discovering this gap in solidarity, our core project team decides to celebrate an event
where all students of LSCM major in Foreign Trade University have chances to connect
with each other, with the younger and the older, to find soulmates as well as relax after
school time. Also, to find the reason why people have not made such events during this
time and detailed information about students’ demands, we intend to conduct a survey
within this community to clarify the demand. The survey was conducted follow these
steps:
✔ The average budget that attendants can cover for such event
✔ Factors affect their decision to attend (if they are willing to join our event)
3
● Step 2: Transform the ideas into questions, ensure these question clear and soft
enough for customer to be detail and honest
● Step 3: Double check the questionnaire and write description of the survey
● Step 4: Contact with other monitors of the rest 2 intakes for support in spreading
the questionnaire
● Step 5: Filter the answers and highlight the ones that were picked most.
Moreover, we interviewed the organizers of similar events but in different majors, such
as the DDD Night of External Economics major, Finance and Banking major, v.v to
consult the feedback of their attendants as well as some tips they drew after the event to
fulfill as much as possible the satisfaction of our community.
QUESTION RECOMMENDATION
- Marketing campaign
- More interaction
Things want to upgrade - Proactive personnel to flexibly solve
problem
There are some suggested requirements that the event has to meet after gathering
requirement and information through online questionnaire and private interview:
FIELD REQUIREMENT
Informative session
These requirements are based on customer demand and are first priorities when any idea
comes up with, the organizing team must ensure that we can meet the basic needs of
customer as well as the lowest standards of an networking event by using tool to keep
track the standard of what we do:
Detail of personnel
Masterplan
distribution and network
TEAM
Criteria PROM
BUILDING
Cost (15%) 3 4
The 2 projects are evaluated based on Weighted Factor Model with 7 criteria,
respectively: Willingness of Participants (25%), Cost (15%), Scope of participants
(15%), Safety of participants (10%), Availability of resources (10%) and Benefits for
sponsors (5%). Each criterion has 5 rating levels from 1 to 5.
Comparing between the 2 projects, we see that the “Prom” project has higher scores
than the “Team Building” project. So we choose to implement the “Prom” project.
2.2. Assumption
We would like to reclaim that our event is only for students who are studying in Logistics
and Supply chain management (LSCM) at Foreign Trade University HCMC Campus,
as we assume that:
● There is high demand within the community to be connected with other students
in same major
● It is necessary for all student to make connection with other generations in their
major for purpose of consulting
● Studying same major can help people more easily connect with each others
● We can share more things with simple but clear concept if all attendants have
mutual point (hear is LSCM major)
2.3. Objectives
STAKEHOLDER OBJECTIVES
7
Audiences
Have a relaxing session
We believe that there are 3 primary stakeholders that in mainstream connect with the
project, one is the Audiences who the project aims to serve, the other is the Organizing
Team, who conduct and operate the project and the final one is the Sponsor who directly
supports the finance to operate the event.
Additionally, since we are the first networking event in LSCM student community, we
certainly face to many unavoidable constraints, especially:
● There is no precedent action in LSCM major for us to consult about the model,
the attitude of attendants, some high probability risk and suggested solutions,…
● The project is the pioneer so that customer's shyness about new networking event
is the main factor preventing them from joining, which is so risky of wasting time
and finance for nothing.
BOUNDARIES DETAIL
2.5. Deliverables
To successfully achieve those above objectives, the team carefully settles some
deliverables to keep track and ensure the objectives will be completed:
Relaxation
Stakeholders Interest/ Managemen Key Interests Message Needed Action Needed Communication
Power t Strategy Channel
Participants H/H Manage Students want to We try to provide a - Class talk to provide - Direct
highlights and benefits of communication
Closely enjoy a party to memorable party for
joining party
relax and expand relaxation and a - Facebook,
- Send mail weekly for email
networking good chance for participants
mutual interaction
Sponsors M/M Keep The benefits to the We strive to fulfill - Keep contact with sponsors - Direct
Satisfied sponsor to be responsibility for the and provide proof of communication
performance
implemented sponsors fully and - Facebook,
- Send a report after fully email
effectively effectively perform responsibility
10
Prom night Core Team - Fully served comply with the fee
To achieve a successful prom night, which not only satisfied the basis but also have some
high-leveled requirements about customer experience, the core team is divided into 4
functions: Technical, Content, Marketing and Operation, suitable with the ability of our
personnel and high requirements for the best result.
3. Planning
DATE MILESTONE
The Prom night is estimated to spend around 21 million VND, compared to the usual price
of market, also, for any problem that accidentally happens, the contingency plan may be up
to 25 million VND, nearly fit with the suggested scope of about 120 attendants being
charged 200.000 VND per ticket.
3.2.1.Funding resources
Besides the attendant fee, our project intends to look for sponsors who would like to
promote their brand in the university student community, especially in the LSCM field.
Here is the estimated expense during preparation process as well as on-site night:
Proposal printing
300.000 VND 500.000 VND
(colored)
2.000.000
Performers fee Content 1,500.000 VND
VND
10.000.000
Venue 8.000.000 VND
VND
1,500.000
Decoration 1.000.000 VND
VND
4,500.000
Teabreak 3.000.000 VND
VND
14
1.000.000
Others 2,500.000 VND
VND
19,950.000 24,600.000
Total
VND VND
In view of students majoring in LSCM at Foreign Trade University and through the survey,
we believe that our audiences’ pain points come from the needs of close interaction and
cross-course integration to cover the demand of enlarging the network in LSCM field for
help in future, or far more, for love, which to cover the fears of lost future directions or
being lonely, stress in studying (especially in top university like Foreign Trade University).
To help audiences enjoy a good experience as much as possible, the coreteam brings class
performances as an introduction of each intake then comes to the team games and yule ball
to create more interaction than ever, make cross-course integration to fulfill the need of
close relationships. Teabreak and chill atmosphere take people into relax condition,
contemporarily keep away stress mind, making new friends in cozy space (Appendix 1)
About potential sponsors, understanding that almost all local brands and start-ups have big
difficulties in approaching customers and increasing brand awareness, our marketing
campaign and some warm up games will be designed to help sponsors promote their image
and customer trial. Via media publications during marketing timeline and the on-site day,
our sponsor not only approached 120 attendants but also spread their image among more
than 4000 students in Foreign Trade University. (Appendix 2)
The objectives of the L’ Night prom completely stick to the high demand of all stakeholder
(shown above in Market fit field), verified via our survey in LSCM community and
coreteam survey. Furthermore, the core team consists of students experienced in conducting
similar events from student organizations, meeting the high-level requirements so that they
can obviously handle such 120-attendant prom. Other elements in the technical and
strategic field also work in our capacity and ability. The core team, additionally, exclude
money-waste items to reduce the estimated cost much lower than estimated profit to ensure
the high probability of the prom.
16
2. Network Diagram
21
22
23
24
25
26
27
1. Proposed Schedule
1. Format and detailed plan for On-site day 2.2.1. Draft timeline
1.1. Theme and concept 2.2.2. Finalize timeline
1.1.1. Brainstorm 2.3. Promoting Content Writing and Visual Design
1.1.2. Finalize theme and concept 2.3.1. Research and brainstorm
1.2. Agenda 2.3.2. Idea craft
1.3. Seeking and Contacting Performers 2.3.3. Final writing post
1.4. Interactive activities 2.3.4. Key visual design
1.4.1. Brainstorm 2.3.5. Post visual
1.4.2. Rehearsing Execution 3. Operation
1.4.3. Review & Modify 3.1. Collaborators Recruitment
1.5. Technical material (stage coordination) 3.1.1. Define needed skills and quantity
1.6. MC script 3.1.2. Application form
1.7. Technical script (Sound, Light & Screen) 3.1.3. Interview
1.8. HR Allocation - Onstage 3.2. Venue selection
3.2.1. Criteria
2. Promotion to target audience
2.1. Marketing Plan 3.2.2. Research, Venue scouting and Contract
2.1.1. Survey/Questionnaire concluding
2.1.2. Brainstorm 3.2.3. Finalize Venue
2.1.3. Team discussion/meeting 3.3. Ticket design and selling plan
2.2. Marketing Timeline 3.3.1. POSM design (brochure)
3.3.2. Database Prom Final
28
3. Operation
3.1. Collaborators Recruitment 6 8 10 8 1,33
3.2. Venue selection 16 19 25 19,5 3
3.3. Ticket design and selling plan 4 6 8 6 1,33
3.4. Decorating Plan 4 6 9 6,17 1,17
3.5. Sourcing Plan (Materials) 8 10 12 10 1,33
3.6. Printing (Backdrop, etc.) 3 5 7 5 1,33
3.7. Rehearsal 5 6 8 6,17 1
4. Funding
4.1. Sponsors Proposal 6 7 8 7 0,67
4.2. Finalize Sponsors Phase I 12 15 18 15 2
4.3. Finalize Sponsors Phase II 12 12 15 12,5 1
4.4. Finalize Sponsors Phase III 10 12 14 12 1,33
4.5. Follow-up Activities 16 21 26 21 3,33
4.6. Acceptance Report 6 8 14 8,67 2,67
5. On-site Day 1 1 1 1 0
31
3. Crashing activities
Normal Crash
Slope
Activity Predecessors
Duration Cost Duration Cost
1.2. Agenda 15 0 10 0 0
(Materials)
4. Funding 5
In the event of unexpected circumstances that arise where The L`Night is unable to take
place on the originally planned date, the project team is forced to speed up the project.
Crashing is done by increasing the resources to the project, which helps make tasks take
less time than what they were planned for. Of course, this also adds to the cost of the
overall project. Therefore, the primary objective of project crashing is to shorten the
project while also keeping costs at a minimum. However, The L`Night has the triple
constraint that says, if you reduce the duration of the project, or its time, then costs will
in turn have to increase. It’s a trade off.
This Project has: Critical Path = 96 (days) and Best Schedule= 65 (days) which
means we can organize 31 days earlier than intended onsite day. However, since
we have clear and specific requirements for the onsite date that includes to take
place on weekends, right after most Logistics classes finish their final exam of
Term II and right before summer vacation of Foreign Trade University students,
this project has strict time constraints. Hence this project could only be crashed
7 days ahead of the intended schedule.
Any project is subjected to events, or risks, that have the potential to impact the project
goals. Risk management aims to exploit implicit risks that have not been addressed into
identifiable risks, and to evaluate the effects and develop effective risk mitigation
strategies. In this context, our project team decides to execute the Qualitative Risk
Assessment by utilizing the Analysis of Probability and Consequences Model. There
are 4 steps in our risk management process: risk identification, risk impact/probability
chart, risk mitigation strategies, and control.
1. Risk Identification
We will start with an establishment of a set of likely risks to be expected to affect the
prom night. For the methods, we are using the brainstorming meetings, history and
team-based assessments. The core project team will hold meetings twice a week, make
a review of the accomplished work and the similar projects to define the key project
risks. In the table below, we categorize the risks into 4 types: stakeholders, project team,
materials and on-site day.
Identified Risks
Stakeholders 1. The number of attendants could be lower than the expected amount.
There would be not enough people to enjoy the planned activities.
2. The project budget could be reduced and trimmed in the middle of
the project because of withdrawal of sponsors.
2. The project budget could be reduced and trimmed in the middle of
the project because of withdrawal of sponsors.
Project Team 4. Project team members could get lost in tracking the project progress.
5. Conflicts could arise between members of functional teams because
of poor communication.
6. Delays in executing activities because of lack of personnel, time
management, experience or just due to procrastination.
7. The operating team could not satisfy the requirements of the content
team.
36
Once the process of risk identification is completed, an assessment of risk impact can
be undertaken. Risk Analysis chart evaluates potential risks based on 2 factors,
Probability of Occurrence and Consequences. The matrix reflects all the potential risks,
along with the likelihood of occurrence of the risk and its level of effects on the project.
The scale for both sides of the matrix ranges from low, medium to high. The pink boxes
on the chart reflect the highest severity of the risk factors on the projects and need
forthwith actions to alleviate the risks, while the green parts represent the low-risk
factors that can be ignored or managed later.
37
Consequences
Low Med High
High
5 6
Probability
Medium
1, 3, 7, 11,
2, 4, 10
Low 12, 15
9 13, 14 8
The next step in risk management is to build up strategies to mitigate the risks. As we
have sorted the risks from the most severe to the least ones, we need different strategies
to alleviate the risks. All the strategies come from the evaluation of the core project
team and assessment of the risk mitigation strategies of the precedent similar projects.
the on-site day despite - Getting the technical team ready for any further issues.
the rehearsals. - Downloading all the pre-recorded music/videos that could be
done in advance in case of Internet cutdown.
6. Decorations could be - Considering the feasibility of the decoration (the size, shape,
broken on the on-site etc.).
day. - Using stronger glue to reinforce the decoration.
- Giving notice to team members and participants the place
where there are easy-to-tear decorations.
- Allocate a member to take charge of supervising and fixing
the broken parts.
7. The MC could not be - Signing contracts with the MCs.
able to host the event on - Getting 2 back-up MCs from the project team as they know
the on-site day. perfectly about the concept and theme.
8. A key project team - Cross-training personnel on elements of one another’s job.
member could not be - Functional team leaders could take the place of that key
able to work on the project member.
project.
9. Conflicts could arise - Team leaders should seek out and address the conflicts before
between members of it could affect other activities.
functional teams due to - Functional teams should hold meetings or get-togethers to
poor communication. understand the personalities and characteristics of team
members.
- Team leaders should give feedback to any progress that has
been done by members.
- Making sure that all team members understand the objectives
or goals that the teams aim to.
- Team leaders should be empathetic when listening to team
members' problems.
4. Control Risks
The final step is to control the risks by implementing all measures mentioned in the
strategies. All the measures vary from the least costly to the most expensive ones,
therefore, if the previous measure does not work, the project team can move forward to
the next measure.
5. Project Termination
Though we have identified all the potential risks as well as their mitigation strategies,
there still remains the worst scenario: project termination. Project termination means
that a project is stopped because there is no more need or resource for further
continuation. For the successful side of project termination, a project is cancelled when
it has achieved its goals, in this context, our prom project proves to satisfy the needs of
the target audience and bring the value that the customers are expecting to gain. On the
other side, the core project team has decided the below assumptions that can cancel the
project:
1. The number of participants is far lower than the expected amount (lower than 60
people), which leads to no sufficient fund to operate the project.
2. The regulations of Government to restrict the public activities due to the Covid-
19 pandemic.
3. The core project team members are not able to work on the project (more than 3
people drop out)
41
Benefits
- Network
in LSCM
- Enable cross-course field
- Enjoy fun memory
connection
in student’s life
- Relaxation Experiences
- Meet more people to - Love, close - Lost direction
develop social relationships Wants
- Network with new relationship - Study stress
Fears
friends in same major - Be updated on - Loneliness
- Relax time in cozy university’s news - Lack of network
Features
atmosphere - Close interaction
university
- Needs with other people
- Team games
- Class performances - Cross-course
- Yule Ball integration
- Teabreak
42
Key Partners Key Activities Value Propositions Customer Relationship Customer Segment
- Venue Supplier - Format and - Relaxation, - Class talk, send - FTU Students
- Perfomers & detailed plan networking email (C1) major in
MC - Promotion to connection - Contact weekly, Logistics and
audience among LSCM send email, Supply chain
- Operation students (C1) report (C2) management
- Funding - Brand Promotion (C1)
(C2)
- Organisations
Key Resources Channels
sponsor for
- Team members, - Social Media project (C2)
collaborators - Direct
Communication
- Contacting the sponsors to inform them of the issue and keeping in touch with them to update
the situation. In case of project termination, the project team shall hold meetings with sponsors to
find the best solutions.
4. The operating team - Content team should carefully research the idea, look for any events which have done similar
could not satisfy the activities.
requirements of the - Preparing the back-up ideas in case the operating team could not fulfill the requirements.
content team. - Giving the suggestions or constructive ideas to the operating team during the executing process.
- Right after receiving the ideas, the operating team should hold meetings to research, feedback
and brainstorm the ideas.
- In case the ideas could not be exercised, the operating team should inform the content team
immediately and both teams start to consider the back-up ideas. Any changes shall be announced
to other functional teams.
5. Technical issues - The event would be held in the evening so the rehearsal should start from the morning to make
could still take place on sure that everything is fine.
the on-site day despite - Getting the technical team ready for any further issues.
the rehearsals. - Downloading all the pre-recorded music/videos that could be done in advance in case of Internet
cutdown.
6. Decorations could be - Considering the feasibility of the decoration (the size, shape, etc.).
broken on the on-site - Using stronger glue to reinforce the decoration.
day.
46
- Giving notice to team members and participants the place where there are easy-to-tear
decorations.
- Allocate a member to take charge of supervising and fixing the broken parts.
7. The MC could not be - Signing contracts with the MCs.
able to host the event on - Getting 2 back-up MCs from the project team as they know perfectly about the concept and
the on-site day. theme.
8. A key project team - Cross-training personnel on elements of one another’s job.
member could not be - Functional team leaders could take the place of that key project member.
able to work on the
project.
9. Conflicts could arise - Team leaders should seek out and address the conflicts before it could affect other activities.
between members of - Functional teams should hold meetings or get-togethers to understand the personalities and
functional teams due to characteristics of team members.
poor communication. - Team leaders should give feedback to any progress that has been done by members.
- Making sure that all team members understand the objectives or goals that the teams aim to.
- Team leaders should be empathetic when listening to team members' problems.
Moderate Risk
47
10. The project budget - Signing contracts with the agreed sponsors.
could be reduced in the - Extending the sponsors seeking duration if the team could not find the appropriate sponsors.
middle of the project.
11. Team members - Functional team leaders should update and make a weekly brief report of the progress to the
could get lost in project core team.
tracking the progress. - Holding bonding activities like lunch, brunch, etc. for everybody to catch up the current situation
of team members.
- Team members should proactively ask for progress and feedback online and offline.
- Team members proactively inform the leader when getting lost in tracking for better solutions.
- Clearly expressing individual opinions, ideas, constraints, delaying reasons to the whole team.
- If the team members could not take time for the project, the leaders shall consider whether that
person could continue with the project or not.
12. Materials could get - Team leaders should notify the people in charge to carefully handle the fragile materials.
lost due to negligence. - Making a clear list of materials and informing everybody about the list.
- Materials should be gathered together at one place.
- Checking the amount of materials before ending all the tasks.
- In case of losing or missing: Expensive materials shall be borrowed; operating team shall seek
for an affordable replacement or repurchase within the budget limit. Operating team could seek
for replacement or repurchase the inexpensive items within the budget limit. The one who is in
charge of keeping the materials shall be liable for 50% of the value of the materials.
48
13. Filming team could - Signing contracts with the filming team.
not attend on the on-site - Borrowing back-up equipment or team members could bring along their equipment for a back-
day. up plan.
- Getting the back-up equipment ready on the on-site day.
14. Performers could - Making a list of potential performers and calling in advance for availability.
cancel their appointed - Signing contracts with the chosen performance teams.
schedules. - Getting 2 back-up performance teams on ready.
Low Risk
15. Printing materials - Printing could be exercised once the decorating and sourcing plans are done, so they could be
could be delayed. completed in advance.
- In case of wrong printing, operating team could ask for re-printing and the duration could be
extended to 2 days before the on-site day.
- Making a list of potential printers for replacement.
49
REFERENCES
[1] A Brief History of Scheduling: mosaic projects.com.au Archived May 18, 2015, at
the Wayback Machine.
[2] Clark, Wallace (1922). The Gantt Chart: A Working Tool of Management. New
York, NY: Ronald Press.
[3] Evtodieva, T. E., Davydova, N. N., Videneeva, S. V., & Fedorov, V. A. (2016). The
Concept of Network Organization and Design of Networks in Logistics. International
Journal of Economic Perspectives, 10(3).
[4] Jack R. Meredith, S. J. (2009). Project Management - A managerial approach (7th
ed.). United States of America: John Wiley & Sons, Inc.
[5] Kelley, James; Walker, Morgan. Critical-Path Planning and Scheduling. 1959
Proceedings of the Eastern Joint Computer Conference.
[6] Lee, J. Y., & Woo, S. H. (2019). The Impact of Power on the Relationships and
Customer Satisfaction in a Logistics Triad: A Meta-Analysis. The Asian Journal of
Shipping and Logistics, 35(4), 194-199.
[7] Morris, Peter W. G. (1997) [1994]. The Management of Projects. Thomas Telford.
ISBN 978-0-7277-2593-6.
[8] Pinto, J. K. (2015). Project Management: Achieving Competitive Advantage (4th
Edition) (4th ed.). Pearson.