Query No. 3 - DLSU Drainage Outfall
Query No. 3 - DLSU Drainage Outfall
Query No. 3
EVP
1 Please specify construction duration.
2 Please provide plan and section details for the double barrel
drainage manhole. Initial provided details are for single only.
Page 1 of 3
4.
Please clarify which layout should govern for the drainage
system insude DLSU campus.
Layout 1:
Layout 2:
NOTE: Your reply to the above queries on or before (17 April 2023) would be of assistance, please.
Date
Item Query List No. Remarks
Sent Required Replied
1 Query no. 1 8 Feb 2023 10 Feb 2023 14 Feb 2023
2 Query no. 2 30 Mar 2023 04 April 2023 11 Apr 2023
3 Query no. 3 13 Apr 2023
Total No. of Pending Queries 1
Total No. of Answered Queries 2