Professional Documents
Culture Documents
SECTION-I
SCOPE OF WORK
[SOW]
&
SPECIAL CONDITIONS OF CONTRACT
[SCC]
1. GENERAL INFORMATION
a) The Special Conditions of Contract (SCC) shall be read in conjunction with the General Conditions Contract
(GCC), Schedule of Rates (SOR), Scope of Work (SOW), and any other document forming part of the contract,
wherever the context so requires. The same is enclosed along with the Tender Documents.
b) Notwithstanding the sub-division of the document into these separate sections and volumes, every part of each shall
be deemed to be supplementary of every other part and shall be read with and into the contract so far as it may be
practicable to do so.
c) Where any portion of the general condition of the contract is repugnant to or at variance with any provisions of the
special condition of the contract, then unless a different intention appears, the provision(s) of the special condition
of the contract shall be deemed to override the provision(s) of general condition of contract only to extent that such
repugnancies of variations in the special condition of contract as are not possible of being reconciled with the
provisions of general condition of contract.
d) The intending bidders should be deemed to have visited the site and familiarized themselves thoroughly with the
site condition before submitting their bid. Non familiarity with the site condition will not be considered a reason
either for extra claim or for not carrying out work.
2. NAME OF WORK:
“Annual Rate Contract for Hiring Agency for providing Environmental Services at GAIL (India) Limited, Hazira
3. LOCATION OF SITE:
GAIL Hazira Compressor Station is located at Surat, Icchapur – Magdalla Road, about 20 KM away from
Surat Railway station in Gujarat State.
4. CONTRACT PERIOD:
The duration of the Contract is 36 months to be reckoned from the 15th day of the issue of LOA/FOA. Contract period
shall be for three years and can be terminated at any point of time without assigning reason, in case performance of work
is not found up to the expectation of Engineer in Charge.
5. ENGINEER – IN – CHARGE:
Mr. Sujoy Chatterjee, SM (F&S) shall be EIC for the job.
7. MOBILISATION ADVANCE:
No mobilization advance will be paid to the contractor.
9. ADVANCE PAYMENT:
No advance payment is permissible.
16. QUANTITIES
The quantities mentioned in the Schedule of Rates (SOR) may vary as per actual site conditions and shall be executed as
per the instructions of the Engineer-in-Charge. GAIL reserves the right to revise/amend/add any conditions/clauses and
other terms for speedy and timely execution of job by issuing the orders.
II (A) Based on rates of machine and labor as available from the contract (Which includes contractor’s supervision,
profit, overheads and other expenses).
II(B) In case rates are not available in the contract, rates will be calculated based on prevailing market rates of machine,
material and labor plus 10% to cover contractor’s supervision profit, overheads & other expenses.
The Rules 72 & 73 of the Contract Labour R&A) Central Rules - 1971 which provide the manner in which wage is
to be disbursed to the contract labour are reproduced below:
f) The contractor shall indemnify the Company against all losses or damages, if any, caused to it on account of acts
of the personnel deployed by him.
g) The contractor shall ensure regular and effective supervision and control of the personnel deployed by him and
gives suitable direction for under taking the contractual obligations.
h) No worker of contractor is allowed to consume alcohol or narcotics.
i) No person below 18 years of age will be deployed by the contractor.
j) The contractor will be required to submit an indemnity bond on a non-judicial stamp paper duly notarized
indemnifying GAIL against all consequences which may arise out of any case filed by any
worker/labors/vendors/sub-contractor/partners who may have been engaged by the contractor directly or indirectly
with or without consent of GAIL for above works, which may be pending before any court of law including non-
judicial authority, competent authority, labor court arbitrator, tribunal etc. At the time of completion of the said
contract on a prescribed pro forma given by GAIL.
k) In case of the contractor intends to engage any labor other than Gujarat appropriate permission should be sought
from the management and concerned Government authority for the same to initiate necessary action under the
interstate migrant Act.
B. SCOPE OF WORK:
The scope of work shall include but not limited to the following:
The detail scope of work is for each item mentioned in SOR section is described below:
1. STACK MONITORING
Stack Emission Monitoring is to be carried out as per the schedule of GAIL, subject to minimum two samples in every
month from the following location:
Parameters to be measured
SN Parameter Unit
1. Particulate Matter (PM) mg/Nm3
2. Sulphur Di Oxide (SO2) ppm, mg/Nm3
3. Oxides of Nitrogen (NOx) ppm, mg/Nm3
4. Carbon Mono Oxide (CO) mg/Nm3
5. Hydrocarbon (HC) mg/Nm3
6. O2* %
7. CO2* %
Note- The parameters may not be limited to the above mentioned and can be revised, if any, according to new
guidelines/direction is received by any statutory authority during the contract period. No extra payment shall
be made by GAIL in case any new parameters are imposed by any authority for measurements.
*O2 and CO2 in flue gas are to be measured in % and submitted as per format given below.
Standard to be followed: as per Latest MoEF, CPCB, GPCB and other statutory Guidelines (also as per “Stack
Monitoring – Material and Methodology for Isokinetic Sampling” published by CPCB. Also as per IS 11255, IS 5182.
The following analysis of stack also to be given separately as per below format:
SN Parameter Unit
1. Sulphur Di Oxide (SO2) %
2. Oxides of Nitrogen (NOx) %
3. Carbon Mono Oxide (CO) %
4. Hydrocarbon (HC) %
5. O2 %
6. CO2 %
Note- The parameters may not be limited to the above mentioned and can be revised, if any, according to new
guidelines/direction is received by any statutory authority during the contract period. No extra payment shall
be made by GAIL in case any new parameters are imposed by any authority for measurements.
Ambient air quality sampling is to be done and following parameters are to be measured:
SN Parameter Unit
1. SPM (Suspended Particulate matter) µg/m3
2. RSPM/PM10 (Respirable Suspended Particulate matter) µg/m3
3. Oxides of Sulphur (SOx) µg/m3
4. Oxides of Nitrogen (NOx) µg/m3
5. Carbon Mono Oxide (CO) µg/m3
6. Hydrocarbon (HC) µg/m3
7. PM 2.5 µg/m3
Note- The parameters may not be limited to the above mentioned and can be revised, if any, according to new
guidelines/direction is received by any statutory authority during the contract period. No extra payment shall
be made by GAIL in case any new parameters are imposed by any authority for measurements.
3. WATER ANALYSIS
Location & Frequency of water Analysis
The parameter shall be measured and tested in accordance with the relevant IS as prescribed by the statutory
authorities. All parameters as per latest IS: 10500 for drinking water. Service water are excluded from MPN, faecal
coliform and total bacterial count.
The results of noise level monitoring should contain the following details:
Date Time Leq(dBA) Avg. leq (Night)
The noise level is to be measured by digital sound level meter having resolution of 0.1 dB. The instrument must have
been calibrated by a reputed agency and also it should have an internal calibration system. Calibration report to be
submitted to EIC.
Note: Noise Monitoring of Group-A and Group-B is to be done alternately at the interval of 2 months.
5. Miscellaneous Services for submission of Yearly Statement /Returns/reply to query /notice from GPCB & Env.
Related Statutory regulations etc.
Reply to the Queries/Notices raised by GPCB & Env. Related Statutory regulations etc. against submitted data like
environment Statement, Form–3 or 4, Hazardous Waste and etc. on GPCB XGN portal or GPCB hard Copy at GAIL
Hazira or during site visit by GPCB officials.
Note: Invoice for Line Item No. 5 shall be raised on yearly basis. After completion of work.
13. Proof of calibration of the measuring instruments shall be submitted to EIC in the following format:
Parameter Instrument Method of calibration Frequency Last date of