Professional Documents
Culture Documents
(MINISTRY OF RAILWAYS)
(RAILWAYS BOARD)
REHABILITATION, UP-GRADATION
AND CONVERSION OF
400 COACHES
(Revised PC-I)
PC-I Performa
March, 2014
1
PART – A
4. a. Plan Provision.
( Rs.in Million )
Total Block Amount already Amount proposed Balance Available
Provision Committed for this project
- - 5,200.000 -
2
b) Provision in the current year PSDP/ An amount of Rs. 289.000 million
ADP for the year 2013-2014. has been provided in the financial
year 2013-2014. Additionally an
amount of Rs. 575.000 million
including an amount of Rs. 98.000
million FEC is required to achieve
the desired objective.
Further more 125 passenger coaches are required to be rehabilitated and up-
graded by conversion into air conditioned standard and business class coaches as
under:-
3
The cost of the project has already over run as indicated above, incurring an
expenditure of Rs. 3336.731 million till June, 2013 and an allocation of Rs.289.000
million made for the year 2013-14. In order to complete the work Rs. 575.000 million
including an amount of Rs. 98.000 million FEC additionally required for the year 2013-
14 and an amount of Rs. 704.120 million for the year 2014-15. Total cost of the project
will as such work out to Rs. 5200.000 million i.e. is an increase of Rs. 1766.000 million
including Rs. 446.432.000 million FEC which is about 51.4 % higher than the approved
cost.
i. Labour charges have increased 117% during the execution period i.e.
2006-07 Rs. 30.000 per man/hr to Rs. 65 man/hr.
ii. During 2013-14 overhead charges have been increased from 2006-07 to
2012-13 as under:-
2006-07 = 911%
2007-08 = 517%
2008-09 = 430%
2009-10 = 476%
2010-11 = 549%
2011-12 = 551%
2012-13 = 558%
iii. The average rate of overhead charges during the execution year is 570%
due to increase in the utility bills and wages of staff and allied facilities
provided to staff.
iv. Material cost has been increased from 50 to 100% during the
corresponding years.
v. Rupee has been devalued against US$ and Euro by about 66.7% during
2006-2013, resulting in the increase of the prices of raw material used for
the rehabilitation, up-gradation and conversion of passenger coaches into
air conditioned coaches (AC Standard/AC Business).
vi. 750 employee were allowed on TLA vide annexure-XVI of the original
PC-I to complete the rehabilitation work within target time but due to
inadequate allocation of funds during 2009-10 to 2011-12, only 42
coaches were rehabilitated, up-graded and converted into air conditioned
coaches (AC Standard/AC Business) and factory has also made payment
to TLA staff from the PSDP allocation which was also a reason of cost
over run. At present the TLA staff strength has been reduced to 462 (vide
4
Annexure-V/I) employees. It is suggested to continue to deploy them on
subject project.
vii. Inflation rate in Pakistan during 2006-07 to 2012-13 was above 10%
which increased the cost of material for the rehabilitation, up-gradation
/conversion of passenger coaches into air conditioned (AC Standard/AC
Business) coaches. (See Annexure- VII )
i. Inadequate allocation of funds against actual demand has been provided during
the execution period and demanded funds were not provided to achieve targets
fixed. The execution time has increased from three years to nine years, resulting
in increase in the cost due to inflation of prices. Furthermore, funds were released
on quarterly basis due to financial constrains. It created problems in timely
procurement of material and purchase orders for material had to be placed in low
quantity on requirement basis.
ii. Turn-out factory is badly suffering due to load shedding of electricity and natural
gas, resulting in shortage of water supply and consequent reduction in working
hours & increase in idle hours, which were beyond the control of factory
administration from January, 2008 till 30 June, 2013.
iii. The growth of passenger traffic in Pakistan is directly related to the increase in
population, urbanization and rise in national income. The extent to which the
railways can play their role in sharing the responsibility of carrying passenger
traffic will, however, depend upon the operational economics of different modes
of transport and passenger amenities offered.
Passenger and freight traffic targets for 2017-18 have been fixed in Business Plan
from 2012-13 to 2017-18 as 32,800 MPKMs and 25,200 MTKM. Railway carried
16,093.350 million PKMs and 402.481 million TKMs during 2011-2012.
Passenger traffic has increased by 4 % per year during 2000-2001 to 2008-2009,
i.e. 19,589 MPKM to 25,702 and decreased 30 % during 2009-2010 to 2011-2012
23, 522 MPKM to 16,093 MPKM @ 10 % per annum. Freight traffic have been
increased by 4 % per year during 2000-20001 to 2008-2009 i.e. 4,519 million
TKM to 5,896 million TKM and decreased 90 % during 2009-10 to 2011-20122
from 4,846 to 402.481 million tones @ 30.6% per annum. The decrease of
passenger traffic and Freight traffic was due to less availability of locomotives.
5
Due to economic activities in Pakistan, the time consciousness has increased and
every one prefers better means of transportation with less journey time and
facilities specially the A.C standard / A.C business class. Passenger traffic of A.C
standard / A.C business class has been increased by 25 % during the last five
years. A big potential for increase in passenger traffic specially in A.C standard /
A.C business class and Economy class is available if journey times of trains are
reduced by increasing speeds of trains.
At present, there are 1687 coaches on the System (See Annexure-VIII. 113
coaches have already completed their economic life. This number would increase
with passage of time and it would increase to 300 by the year 2014-2015 as ample
number of coaches would require condemnation on age cum condition basis.
However, in order to keep the trains in service and in view of resource constraints,
it would not be possible to withdraw all these coaches from the system. As such,
it is considered imperative that a maximum No of coaches is rehabilitated, up-
graded and converted into A.C standard / A.C business class coaches to make
these coaches operational for another 15 years of service providing better
facilities and amenities to the travelling Public.
i) At present, first class sleeper coaches have a low earning potential. It will be in
the fitness of things to replace these first class sleeper coaches with A.C standard /
A.C business class coaches to significantly improve Railways earning. It is,
therefore, planned to convert 70 first class sleeper coaches and 65 2nd class
/Economy Class Coaches into A.C standard / A.C business class traveling public
and at the same time to improve the Railway earnings.
6
ii) Present availability of power vans is hardly sufficient to meet the present
commitment of A.C standard / A.C business class coaches on various trains. For
inducting additional 135 AC lower class coaches, there is a need to provide
matching power vans so that A.C standard / A.C business class coaches are
worked independent of existing power vans. For this purpose, thirty (30) 2nd class
coaches will be converted into power vans under this “rehabilitation/ up gradation
and conversion project”.
iii) As per grand reality it has been decided to rehabilitate 280 BG-64 bogies instead
of procurement of new design high speed bogies.
iv) The present capacity of the Pakistan Railways to carry passenger traffic is
approximately 26.000 billion passenger kilometer annually which is not sufficient
to meet the needs of developing economy which requires growing volume of
passengers to be transported across the length and breadth of the country.
Pakistan Railways is, at present, carrying 20% of the total passenger traffic
moving only from Karachi due to which balance 80% is carried by road which is
more expensive as compared to rail but also generates excessive pollution and is
less safe. There is an additional demand of over 4 billion PKMs to be moved from
Karachi to up country cities like Multan, Lahore, and Rawalpindi etc. for which
Pakistan Railways is required to expand its transportation capacity.
v) It is necessary that these coaches are fitted with air brake system because the
existing vacuum brakes are unable to provide the required braking power to match
higher speeds and loads of passenger trains. The cost of air brake set has been
included in the cost for conversion of coaches from sleeper class and second class
into Air Conditioned Standard / Business Class.
As the prices of material have been increased due to price hike in the World
market, specially with respect to steel, coal and consumable items, devaluation in
Rupees against U.S. Dollar, Euro, Pound Sterling and annual increase in labour
cost/charge along with utility bills which can be seen as per comparative
statement placed at Annexure-II. The PC-I is, therefore, revised and additional
51.4% amount of Rs. 1766.000 million is required for changing the scope of work
whereas, the quantity will remain the same. The revised PC-I has been submitted
for the approval of the competent authority to regularize expenditure already
incurred for the procurement of material, payment made to the Factory
workers/labour and the utility bills.
7
The salient features of the revised project are further discussed as under:-
Due to low earning potential of first class sleeper / economy/ 2nd class, 135
coaches shall be converted into Air conditioned standard/Business class coaches
to fetch more revenues. With the conversion of 135 Air conditioned
standard/Business class coaches, the revenue will increase.
15 Nos 2nd Class /Economy Class Coaches will be rehabilitated and converted
into Air Conditioned Dinning Cars to provide better facilities and amenities to the
travelling public /passengers during the journey.
In order to provide electric power to the Air Conditioning and electric equipment,
of 135 AC Lower coaches, 30 Nos. 2nd class coaches Brake Vans / Guard Vans
will be converted into power vans under the project with rehabilitated bogies.
As the present, bogies of BG-64 design are giving maintenance and operational
problems as such it is planned to rehabilitate 280 trolleys (bogies) instead of
procuring imported material. These will be fit to run at a speed of 110 KMPH.
284 coaches shall be converted from vacuum brake to air brake system so that
after their putting into service, speed and load of trains are significantly enhanced,
reducing the journey time and increasing revenue.
220 Nos. 2nd class/ Economy class coaches/ TL Vans have been deteriorated with
passage of time, particularly, those manufactured locally which require
replacement / rehabilitation as such these coaches would be rehabilitated provided
with modern facilities/amenities along with head end generation system and Train
lighting Van for smooth working of train lighting and air conditioning system
which had already been introduced in the past.
8
(IV). SCOPE OF WORK FOR REHABILITATION / UP GRADATION OF
COACHES
* TEMPERATURES:
i ) .Max. recorded ambient temp: 520c
ii) Average max. readings : 480c
iii) Min. recorded ambient temp: (-) 180c
iv) Average min. readings: (-) 50c
9
* RELATIVE HUMIDITY :
a) Max. 100 %
b) Average of max. reading 48 %
c) Min. 2%
d) Average of min. reading 21 %
c. Basis of determining the capital The Costs are based on the last,
cost to be provided. It includes present purchase rate (material
market survey, schedule rates, procured during the execution and
estimation on the basis of previous existing market rates and up-dated
work done etc. according to planning commission
formula.
d. Provide year wise estimation of See annexure- I
physical activities.
The average annual maintenance cost of a coach during the Financial Year
2006-2007 is worked out as Rs. 0.630, Rs. 0.473 and Rs. 0.840 million for A.C
class, economy class and power van respectively. This cost is shown in column 5
of the work sheet. These costs have been increased/ updated upto 2015-16 and
remaining cost is assumed to remain the same like passenger fare charges which
have also been frozen like-wise. Any increase in maintenance and operating costs
will be charged directly to passenger fares in future to maintain the present I.R.R.
Operating Cost
10
The average annual operating cost of a coach during the Financial Year
2006-2007 is as worked out Rs. 0.368, Rs. 0.357 and Rs. 4.725 million for A. C.
class, economy class and power van respectively. This cost is shown in column 6
of the work sheet. These costs have been increased /updated upto 2015-16 and
remaining costs have been assumed to remain the same like passenger fares
which have also been frozen like-wise. Any increase in maintenance and
operating costs will be charged directly to passenger fares in future to maintain
present I.R.R.
At present, there are 1687 PCV coaches on the System. 113 Nos. of coaches
have already completed their economic life. This number would increase with
passage of time and it would increase to 197 by the year 2014-2015, as an
ample number of coaches would require condemnation on age cum condition
basis. However, in order to keep the trains in service and in view of resource
constraints, it would not be possible to withdraw all these coaches from the
system. As such, it is considered imperative that a maximum No of coaches is
rehabilitated, up-graded and converted into Air conditioned standard/Business
class coaches to make these coaches operational for another 15 years of service
providing better facilities and amenities to the traveling Public.
11
d) Supply –demand gap.
Passenger and freight traffic targets for the years 2017-18 have been fixed in
Business Plan from the F.Y. 2012-13 to 2017-18 as 32,800 MPKMs and
25,200 MTKM. Railway carried 16,093.350 million PKMs and 402.481
million TKMs during 2011-2012. Passenger traffic has increased by 4 % per
year during 2000-2001 to 2008-2009, i.e. from 19,589 MPKM to 25,702 and
decreased 30 % during 2009-2010 to 2011-2012 i.e. from 23, 522 MPKM to
16,093 MPKM @ 10% per annum. Freight traffic has been increased by 4 %
per year during 2000-20001 to 2008-2009 i.e. from 4,519 million TKM to
5,896 million TKM and decreased 90 % during 2009-10 to 2011-20122 i.e.
from 4,846 to 402.481 million tones @ 30.6% per annum. The decrease in
passenger traffic and Freight traffic was due to less availability of locomotives.
Due to growing economic activities in Pakistan, the time consciousness has
increased and every one prefers better means of transportation with less
journey time and facilities specially the Air Conditioned Standard/Business
Class Coaches services. Passenger traffic of Air Conditioned
Standard/Business Class Coaches has been increased by 25% during the last
five year. A big potential for increase in passenger traffic specially in Air
Conditioned Standard / Business Class Coaches and Economy class is
available if journey time of trains is reduced by increasing speed of trains. The
major bottlenecks are the non-availability of Passenger coaches and speed. To
increase speed, the design proposed in this project will up-grade passenger
carriages with bogies capable of running upto 120 KPMH.
At present, first class sleeper coaches have a low earning potential. It will be in
the fitness of things to replace these first class sleeper coaches with Air Conditioned
Standard/Business Class Coaches to significantly improve Railways earning. It is,
therefore, planned to convert 70 first sleeper class coaches and 65 Economy Class
Coaches into Air Conditioned Standard/Business Class Coaches with separate
compartments to provide better comfort to the travelling public and at the same time
improve the Railway earnings.
Present availability of power vans is hardly sufficient to meet with the present
commitment of Air Conditioned Standard/Business Class Coaches on various trains.
For inducting additional 135 Air Conditioned Standard/Business Class Coaches, there
is a need to provide matching power vans so that AC coaches are worked independent
of existing power vans. For this purpose 30 coaches will be converted into power vans
under this rehabilitation project.
12
10. Financial Plan
Sources of financing.
a) Equity.
NGO’s /Beneficiaries. -
Others. -
b) Debt.
13
The loan repayment schedule be
also annexed.
c. Grants. Not known
CAPITAL COST.
Capital cost has been divided into following distinct groups as under:
Group-I.
The estimated cost of Rehabilitation of 220 Economy Class coaches/TL Vans under
Rehabilitation Plan and cost of conversion of 70 first class sleeper coaches and 65 2nd class
economy class coaches into 135 Air Conditioned Standard/Business Class Coaches, 15
14
Dinning Cars and 30 2nd Class Coaches into Power vans under this project for the Rolling
Stock of the Passenger Business Unit, has been worked out to be Rs. 5180.633 million with
Rs. 2664.851 million labour charges including over head charges including establishment
charges and Rs. 2515.782 million for the procurement of material required for rehabilitation
of passenger coaches and up-gradation and conversion of first and economy into air
Condition classes coaches, Dinning cars and Power Vans. It includes the cost of material such
as melamine panels for compartments and toilets, toilet fittings, local material, charges, etc.
for the Rolling Stock of the Passenger Business Unit.
NOTE :-
Rs 600.00 million depreciation cost (booked value) have been calculated for 400
coaches to be rehabilitated or converted into air conditioned lower class coaches and power
vans for group I and II and has been charged to the project while making financial and
economic analysis on work sheet at annexure III and IV.
Group-II
The estimated cost for procurement and fitment of air brake kits to 288 passenger
coaches worked out to Rs. 76.285 million. It includes the cost of 288 imported air brake Kits,
local material and labour charges which are included in the cost for the rehabilitation of
coaches. Being a minor cost, all the costs have been charged to the project.
i) Financial.
Income to the project along with
assumptions.
Benefits (earnings)
Earnings based on one day passenger fares. The charges per passenger for the financial years
2007-08, 2008-09, 2009-10, 2010-11, 20011-12 and 2012-13 on actual average basis and
class-wise earning have been taken into account and divided by the Nos. of passenger coaches
running /working on the line during every year. Fares of the financial year 2013-2014 and
2014-15 are kept same as of the F.Y 2012-13. These carriages were re-used for trains between
Peshawar Cantt – Karachi Cantt and as unit trains in future between Rawalpindi – Karachi
Cantt., Multan Cantt – Karachi Cantt, Quetta – Peshawar Cantt, Sukkur –Karachi Cantt and
Lahore – Karachi Cantt. and their earning has been calculated at annexure- VI and charged
accordingly.
30% of this earning is attributed to coaches on the basis of investment ratio on other
elements of infrastructure i.e. Track. Locomotives etc.
* Economic
Benefit to the economy along with
assumptions.
15
1. Rehabilitation, up gradation and conversion of old coaches into Air Conditioned
Standard/Business Class Coaches and increased transportation capacity of
Pakistan Railways.
2. Better utilization of available Railway infrastructure.
3. Improved financial liquidity.
* Social
Benefits with indicators. i) To provide better, comfortable, reliable
and safe journey to the traveling
passengers.
ii) Improvement in quality of services to be
rendered to traveling public.
iii) Improvement in standards of efficiency.
iv) Good will of Public through punctual
running of trains.
ii) Environmental.
Environmental impact assessment For the haulage of one metric tonne over
negative /positive. a distance of one kilometer by road,
18000 BTUs are consumed, whereas, by
rail only 3000 BTUs are consumed for
the same distance. Thus pollution
generating ratio between road haulage
and Railway haulage is approximately
6:1.
Financial/Economic Analysis
( with assumption )
Financial Analysis
iii) Quantifiable output of the project. See section 11 Financial.
16
vii) Pay back period. 05 Years.
* Employment analysis.
x) Impact of delays on project cost Not applicable as the project cost has
viability. already been over run and the project is
five years delayed.
12 Implementation Schedule.
xi) -
Indicate starting and completion Project has already been started from
date of the project. May, 2007. Completion period was 36
Months w.e.f 1st May 2007. Now the
project has already been delayed and
cost has already been over run by more
than 15%. Project will be completed by
30th June, 2015, because the provision of
funds was not made in time and project
17
was delayed on this account.
18
allowance according to Finance
Division’s letter No. F-4(9)R-3/2008-
499 dated 12.08.2008
(iii). For operational and maintenance,
staff requirement of these coaches may
kindly be seen at annexure-V & V/II.
This will be required on permanent
basis.
15 Certificate
19
It is certified that PC-I has been prepared as per guidelines issued by the Planning
Commission for the preparation of PC-I for Infrastructure Sector project.
(RAHAT MIRZA)
Prepared by DY. CHIEF MECHANICAL ENGINEER/DEV.
# 042-920 1657
RAD. 2666
(AMBREEN ZAMAN)
Checked by CHIEF ELECTRICAL ENGINEER
(PARVEEN AGHA)
Sanctioned by ACTING SECRETARY/CHAIR PERSON RAILWAYS
(ECNEC)
20
It is certified that PC-I has been prepared as per guidelines issued by the Planning
Commission for the preparation of PC-I for Infrastructure Sector project.
(PARVEEN AGHA)
Sanctioned by ACTING SECRETARY/CHAIR PERSON RAILWAYS
(ECNEC)
21
Rehabilitation, Up gradation and Conversion
of 400 Passenger Coaches
( conversion of 70 First Class Sleeper Coaches, 80
Economy Class Coaches into Air Conditioned Lower
Class, 15 Dinning Cars & 40 Power Vans.)
2006-2007 10 8 2 20 40
2007-2008 70 20 4 82 176
2008-2009 70 12 9 85 184
TOTAL 150 40 15 195 400
22
xiv) Net present value ( NPV) and NPV . 325. 582 Million
Benefit Cost Ratio. Benefit Cost Ratio = 1.051 : 1
23