Professional Documents
Culture Documents
Jostein Pettersen
Outline
2010-09-26
Snøhvit LNG Project - Hammerfest
Made possible through technology development
• First gas development project in the Barents sea
(Hammerfest: 70 north)
o
, ,
,
Brunei
NORWAY
LNG
ADGAS
Oman LNG
2010-09-26
Hammerfest – Melkøya (May 2006)
2010-09-26
Snøhvit facts
The first gas development project in the Barents Sea
Discovered: 1981 – 84
Fields: Snøhvit, Albatross and Askeladd fields in
the Barents Sea
Water depth: 250 – 340 m
Distance to shore: 140 km
Gas in place (GIIP): 317 GSm3 or
11.2 TCF (terra cubic feet)
Condensate: 34 MSm3
Owners:
Petoro AS 30.00 %
2010-09-26
Snøhvit LNG
Value chain
Field
Pipeline LNG plant Shipping Receiving
development
terminal
2010-09-26
Slug catcher Inlet facilities
SNØHVIT Pretreatment
Simplified overview
Carbon dioxide
Snøhvit
Production wells
Fractionation
Production wells
Plem
Condensate production
CO2 Injection well
Production wells
Albatross
Seabed
CO2 Injection Production well
well Reservoir
2010-09-26
Prepared by Petrolink
Snøhvit offshore – a subsea development
Snøhvit 8 wells + 1 CO2 injector
6 wells + CO2 in 2004/2005, 2 wells in 2011
Albatross 4 wells
3 wells in 2005/2006, 1 well in 2014
Askeladd 8 wells
All wells in 2014/2015
2010-09-26
Hammerfest LNG plant - block flow diagram
N2 to atm.
CO2 reinjection
(to pipeline)
CO2 drying
and Nitrogen
recompression removal
Fuel gas
system LNG
Storage
Feed from
pipeline Slug Inlet facilities/ CO2 De- Mercury Natural gas LNG
catcher Metering removal hydration removal liquefaction Storage
C1 / C2 / C3 Refrig. Make
-up
Fractionation
MEG (Refrigerant LPG
Recovery Make-up) Storage
Lean MEG
(to pipeline)
Condensate Condensate
treatment Storage
Utility Flare Control
Systems Facilities room
2010-09-26
LAYOUT - HAMMERFEST LNG PLANT
Area 1 Area 2 Area 3
HP flare
Construction jetty
Slug catcher
2010-09-26
HAMMERFEST LNG – Process barge
1
3
2 Natural gas Cold
Box
Nitrogen Removal
Cold Box
Process
substation
Process area
Compressor area
Electric power
generation
Work of liquefaction - effect of cooling sink temperature
Basis sink temperature is 30 °C
% Reduction in Compressor
30
25
20
Work
15
10
5
0
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32
Heat sink temperature
2010-09-26
Mixed Fluid Cascade (MFC®) Liquefaction process and
power/heat generation at Hammerfest
65 MW
NGL
32 MW
65
MW
2010-09-26
Cold box
Containing cryogenic
equipment
2010-09-26
LNG/LPG/Condensate storage during
construction
LNG
Condensate
125.00
75.000 m3
0 m3
LNG
125.00
0 m3
LPG
45.000
m3
2010-09-26
Product Jetty during construction
2010-09-26
Melkøya before construction start-up…
June 2001
2010-09-26
Melkøya August 2006
2010-09-26
During and after ”Narve” storm – Jan 2006
2010-09-26
Prefabrication and use of
large modules
Why this very large extent of
prefabrication?
• Harsh weather conditions
• Remoteness – lack of necessary
infrastructure
• Reduce the necessity of steel work at site
• Higher productivity at construction yard
• Reduce work at site in general -
of the total estimate of 15 million man-
hours to build the plant, 50 % is done at
site.
2010-09-26
Slug catcher
2010-09-26
MEG tanks
2010-09-26
Heat
exchangers
2010-09-26
Kuldeboks Cold box
2010-09-26
Cold box
2010-09-26
Process
plant
2010-09-26
Prefabrication – LNG plant on a barge
Process systems on the barge
Weight: 21.000 tonnes
Height over deck: 60 m
Barge
Weight: 10.000 tonnes
Size: 154 x 54 x 9m
2010-09-26
Blue Marlin and process barge in Cadiz….
2010-09-26
Hammerfest – here we are!
2010-09-26
In-docking of process-barge….
2010-09-26
21 August 2007: Production start
800
700
600
500
400
300
200
100
0
21.08.2007 - 06.10.2007 - 25.01.2008 - 12.04.2008 - 10.07.2008 23.08.2008 30.10.2008 15.01.2009 06.05.2009
24.09.2007 28.10.2007 27.01.2008 13.04.2008
2010-09-26
Shipping and new markets…
Melkøya - Cove Point: ca. 20 days ”return”
Melkøya – Bilbao: ca. 12 days ”return”
Cove Point
annually 2.4
billion cubic
metres
Iberdrola S.A.
annually 1.6
billion cubic
metres
2010-09-26
Arctic Shipping
36 - 2010-09-26