21-22 Best Practice Of|Diesel Generator
Overhauling
January 15, 2021 by Marinediesel
Table of Contents
Introduction to Diesel Generator
Overhauling Procedure
In this post, we shall explain the Diesel Generator Overhauling Procedure.
The diesel generating schedule has presented in a simplified way and
language.
21-22 Best practice of|diesel generator overhauling 11
The DG Sets (Diesel generating sets) are the only source of Power on
board a ship. It is not possible to operate any machinery without the
Diesel generating sets.
As per the power requirement, various types of Diesel Generators are
used.
For the proper maintenance of Diesel generators, Engineers should
understand the the following.
[Link] 1/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
1. knowledge of design, construction
2. Working of the machine.
3. Overhauling Procedure and the maintenance works:
There are standard procedures for the Diesel Generator Overhauling
Procedure and maintenance of these machines, irrespective of their
design and manufacturing.
Diesel Generator Overhauling Procedure–Major
Overhauling/De-carbonisation:
The process of dismantling, cleaning, and removal of carbon deposits
from the following parts.
Piston
Cylinder Liner
Cylinder head
Major maintenance/ Decarbonisation is
carried out on the following occasions.
Completion of running hours as per the planned maintenance
program of OEM (Original equipment manufacturer).
Accident/Breakdown.
Before continuous survey in which process of change of running
parts like and piston rings etc.
There are standard procedures for the maintenance of these machines,
irrespective of their design and manufacturing.
Planning;- Planning of maintenance is to done keeping the following
points in view.
[Link] 2/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
MakeShift arrangements for the emergency in the event of Power
failure
Special Tools and tackles to be beforehand in proper operating
condition.
Measuring Instruments and tools: All measuring tools gauging and
measuring devices should be in suitable working conditions with a
reasonable calibration period.
Spare Parts: check and ensure the availability of spares needed to
accomplish the maintenance.
To ensure the working of Power Packs if available on board.
Engineers/technicians to be involved in the care should know the
procedure as per the Operating manual.
The maintenance team should have Knowledge of symbols and
signs used to indicate the safety of machinery.
Real Life Incidences
Onboard, a ship inventory of the spares was not taken by the
engineer in charge. While the maintenance on the way, during the
inspection, it came to the light that the Con-rod bolts were
elongated and needed replacement. Since the bolts were not
available in the ship’s stock and the overhauling period was
extended. Due to this delay company has to lose the revenue for
not taking the container with perishable goods because of lack of
power.
Before the hydraulic tool’s maintenance pump for loosening the
Cylinder head, Main Bearing and Con-rod nuts were not building
pressure. During the maintenance engineer –in charge found out
that the nuts were not getting loosened up, and hence dismantling
work couldn’t be started. Ultimately it caused the delay in
maintenance.
Very often has been observed that due to the proper upkeep and
maintenance of Measuring instruments/ calibration of the same in
the stipulated period, many instruments fail to operate or lead to
inaccurate measurements.
[Link] 3/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
Preparation
Prior to maintenance following preparation is essential.
Quarantine
Tagging Out
Inspection of special tools supplied by Manufacturer.
Knowledge of functioning and procedure for operating the devices.
Referring to the correct tightening torque and hydraulic pressure
values.
Complete understanding of parts assembly.
Preparation of safety regulations for safe working.
Quarantine: – Before the maintenance start, the machine is to be
quarantined for care to avoid any operating fluids spilling and
injury/accidents.
Both the Prime mover and alternator are to be quarantined.
Following steps are to be taken to isolate the Electrical and mechanical
system.
Open the ACB ( Air Circuit Breaker) to cut off the link between the
Alternator and the bus bar.
The power supply of Pre-Lube oil Pump.
Oil supply to Engine
Cooling water supply
Lube oil
Fuel oil supply
Air supply
A checklist of all the isolated areas is to be prepared, and the same is to
be referred to before reopening the systems.
During the isolating process/opening procedure, a slow action with close
observation is to be adhered to to ensure other equipment is not
[Link] 4/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
affected during this process.
Add on safety: While the maintenance work is in progress, additional
tagging out is to be carried out to prevent any opening up of Valves or
Electrical breakers resulting in an accident of serious nature.
The following special tools: supplied by the engine manufacturer are to
check for their correct working, calibration, and leakage on the hydraulic
device.
Injector and starting valve opening tool
Spanners
Cylinder head opening tool
Cylinder liner Removal Tools
Cylinder Liner Holding Tool
Cylinder head lifting tool
Piston Lifting tool
Bearing removal tool
Cylinder Head and con rod nuts loosening and tightening
hydraulic tool
Valve grinding tool
Valve seat grinding machine/tool
Injector testing tool
Rope and ceilings with proper size D shackles.
Overhead cranes.
Engine Barring arrangements
Cylinder Liner Brushing tool
Piston Ring removal tool
Piston guide tool for inserting the piston.
All the pressure and temperature calibration instruments.
Electrical measuring instruments.
Points to be followed for assembly
Engineer in charge should know assembly of parts and doubt
Instruction manual/Consult with Senior Engineer.
[Link] 5/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
Store all the dismantled components in a separate box with the
marking on significant parts. For each unit, a separate container to
be used.
Mark all the bearings and con-rod bolts and wrap the threads with
the cloth to avoid the threads’ damage.
Dismantling of parts
Overhauling of Generator is governed by the following factors.
No. of Running hours clocked.
Company’s policy.
Order of wear down of individual parts is as under
1. Cylinder Head & Piston Rings
2. Cylinder Liner and Connecting Rods
3. Bearings.
Due to the forthcoming Voyage or defect/incident, all the Dismantle all
the significant parts including Main and con-rod bearings.
In addition to the above Engine parts, undertake the overhauling of the
following components as per the maintenance schedule laid down in the
Instruction manufacturer’s manual.
Carry out the following jobs.
Cylinder Heads
All cylinder heads are de-carbonized.
Inspect cylinder heads.
Inspect Valve spindles.
[Link] 6/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
Carry out the Inspection of Inlet, Exhaust valves & Inlet valve
guides. Record the measurements. Replace the Corroded & worn-
out valve guides with the new one.
Inspect valve seats and reject the excessively dented, pitted, and
uneven working surfaces. Accepted valve seats are to be re-
grounded with the machine.
Dismantle all the valve rotators for inspection. Observe for deep
markings on the inclined surfaces of ball pockets.
Inspect all the Injector Sleeves and record the observations.
Adjust the opening pressure to 170 bars.
Inspect Indicator valves.
Inspect cylinder head cooling water spaces.
Carry out the lapping of cylinder head seating face.
Carry out the pressure testing of all the cylinder heads.
Carry out all Cylinder head valve seat grinding work fo. Old/new
seats.
All Water guide jackets are to be removed, clean, inspect and fit
back with new O rings.
Tighten all the nuts for cylinder heads with prescribed torque as
per the OEM instructional manual.
Cylinder Liner
Pull out all cylinder liners for inspection.
Inspection/ bore measurement and honing to be carried out at
workshop as per OEM procedures for Inspection and Honing of
Cylinder liner.
Enter the records of size into the forms.
Carry out the lapping of the cylinder liner’s upper face.
Replace all the flame rings with an excessive worn-out working
surface.
Piston and Piston Ring
[Link] 7/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
Withdraw all pistons for inspection and overhauling.
De-carbonization of all the pistons (The pistons are to be cleaned
both from inside and outside )
Clean all piston and oil scraper ring grooves, inspect and measure
for wear with groove measuring tool supplied by OEM. Record the
measurements.
Replace all piston rings with the new one.
Confirm the piston ring position is offsetting the ring joint 1800 to
each other, and the spring joint of the scraper ring also fitted 1800
offset to ring joint while mounting the Pistons.
Check the Piston plug tightness on specified torque.
Connecting Rod
Inspect all Connecting rod big-end bearing shells and replace if
found with the deep grooves and excessive wear down more than
the accepted norms for the shell thickness and free spread.
Check the Connecting rod big end bore and record the
measurements.
Check the Small end bearings.
Check the clearance between the wrist pin and bush.
All the piston pins are to be subjected to an ultrasonic test to
check hairline cracks.
Thumb rule for oil clearance calculations (
Important guidelines checks during Diesel
Generator Overhauling Procedure )
Thumb rule for oil clearance calculations
0.01905mm to 0.0254 mm. (Three quarter to 0.0254 of a millimeter) of
clearance per mm of a shaft diameter is the reasonable starting point.
[Link] 8/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
For example 2 mm shaft diameter would require 0.0381mm to 0.0508mm
(0.01905×2=0381 and 0.0254×2=0.0508mm)
For the super performance, engines add 0.0127 to the maximum
calculated value. The recommendations for 2 mm shaft will be 0.0508
mm + 0.0127=0.0635mm.
( For the purpose of maintaining hydrodynamic lubrication between
the shaft and bearing the maximum ovality should not be greater than
the maximum oil clearance. If exceeded then there will be bearing
failure due to boundary lubrication.)
Camshaft and Camshaft Bearings
Inspect all gear wheels bolt and connection as per OEM
instructions.
Replace all Camshaft bush if found worn-out
Check the condition of a camshaft.
Check the lubrication of the camshaft. Observe the flow of lube oil
from all the bearings and spray pipe nozzles. The oil jet should be
hitting at the gearwheel right at the meshing point.
Check the tightness of all the fasteners, including locking devices.
Inspect all pushrods for straightness.
Adjust inlet valve and exhaust clearances as per the OEM
recommendations.
Inlet Valve, Exhaust Valve, and fuel injection
pumps operating mechanism (Diesel
Generator Overhauling Procedure)
Inspect the Roller Guide for
Event of any marks.
Deformation on the spherical stud.
[Link] 9/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
Inspect the Surface of rollers for any mark or deformation.
Check for free play between the rollers and the bush and the pin.
Check the Valve Gear, springs, and Pushrods.
Inspect all the valve bridge springs, Rocker arm brackets, and
pushrods.
Check the Roller Guide for fuel injection pumps.
Inspect all the roller guides for any marks.
Check the Surface of rollers for any defects and deformation.
Check for free play between rollers, bush, and pin.
Check the lubrication of all the operating gears.
Governor
Overhaul the Governor.
Change the Governor oil.
Crankshaft and Main Bearings
Inspect all the crankpins: Polish all main &CR pins with glossy
paper.
Inspect & replace thrust bearings if wear is more than the
prescribed limit.
Re-tighten counterweights at the specified torque.
Dismantle all main directions & Polish all the Crank-pin.
Check the runout.
Carry out the Tightening of main and guide bearing caps at the
prescribed torque.
Check and replace all main bearing if found with abnormal wear
down.
Turbocharger & Charge Air Cooler checks
during Diesel Generator Overhauling
Procedure
[Link] 10/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
Remove the TC cartridge.
Change nozzle ring.
Dismantle the cartridge and inspect the bush and labyrinth ring,
and change if required.
Re-assemble the cartridge
Check the clearances as per the procedure.
Clean the CAC (Charge Air cooler).
Pressure tests the CAC.
Engine Frame and Bed Plate (Diesel
Generator Overhauling Procedure)
Re-tighten of Holding down bolts.
Re-tighten the bolts between the engine and base frame.
Carry out the functional test of safety covers.
Check the AVM paid adjusting screw clearance and adjusts if
required.
Fuel oil System
Calibrate the Fuel injection valves.
Check all high-pressure fuel pipes & replace “O” rings.
Check FIP roller, and measure nominal height.
Overhaul all the Fuel Injection Pumps. Replace barrel, plunger & ‘O’
ring kit.
Lube Oil System checks during Diesel
Generator Overhauling Procedure
Remove the engine-driven Lube oil Pump for inspection. Dismantle
the complete pump and change the bushes.
[Link] 11/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
Apply the correct torque for tightening the self locking nut.
Remove old oil from the engine and charge new oil.
Overhaul Pre-lube oil pump.
Replace the Lube oil filter cartridge.
Clean and replace the kit of Glacier (bypass filter).
Clean the Lube oil PHE ( Plate Heat Exchanger) by circulation with
the chemical.
Cooling Water System checks during Diesel
Generator Overhauling Procedure
Dismount LT (Low Temperature) and HT (High Temperature) water
pumps from the engine.
Carry out the complete overhauling of pumps.
Change the rotating sealing and both ball bearings of the HT
Water Pump.
Change the rotating sealing and both ball bearings of the LT water
Pump.
Tighten self-locking nuts of both the pumps at the specified
torque.
Carry out the overhauling of the HT water thermostatic valve.
Clean the LT/HT PHE.
Mechanical Over-speed
Overhaul the Mechanical over speed device.
Miscellaneous (Diesel Generator
Overhauling Procedure)
These points are very important for the Diesel Generator Overhauling
Procedure.
[Link] 12/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
Record Fuel pump index at Governor Index 0.
Check the compressed air system of the engine.
Check the fuel oil system and nozzle cooling system.
Carry out the functional tests of Safety shutdown switches and
analog switches.
Calibrate all safety switches
If required, replace the Alternator bearing.
On completion of maintenance work, Start the D.G. Set and follow
all moving parts’ sequence as per the standard procedure of
Diesel Generator Overhauling Procedure.
Carry out the load trials of the D.G. Set as per the OEM protocol.
Record the set’s performance in stage load sequence from 25% to
maximum available load for the machine prescribed in Manual.
Monitor the parameters and record them in Logbook.
Data for pressure and Tolerances
[Link] 13/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
21-22 Best practice of|diesel generator overhauling 12
All the procedures explained will help in for proper accomplishment of
Diesel Generator Overhauling Procedure
Share on Facebook Tweet Follow us
My Posts
Marinediesel
Hi, I’m Sham, Founder of [Link]. A web site that provides
authentic information regarding Marine Diesel Engines, and learn marine
Engineering free with us
1 thought on “21-22 Best practice of|diesel generator
overhauling”
1. Pingback: - Uncategorized MARINE ENGINEERING AT A GLANCE
Comments are closed.
Search …
Recent Posts
21-22 best review on engine performance parameters
[Link] 14/15
25/9/2021 Diesel Generator Overhauling Procedure-21-22 Best Practice
21 22 best review on engine performance parameters
21-22 the best review on |Turbocharger Surging
21-22 best review on Engine over speed failure
21-22 BEST REVIEW OF FUEL CONSEQUENCES ON | DIESEL INJECTOR
21-22 Review on Major Accident Due to Hole in Piston
Privacy Policy
Terms & Conditions
Disclaimer
Cookie Policy
DMCA
Please follow & like us :)