Professional Documents
Culture Documents
~~
Doc 9184-AN/902
Part 1
AIRPORT PLANNING
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
MANUAL
PART 1
MASTER PLANNING
SECOND EDITION - 1987
Orders for this publication should be sent to one of the following addresses, together with the
appropriate remittance (by bank draft or post office money order) in U.S. dollars or the currency
of the country in which the order is placed.
10191
The Catalogue of
ICAO Publications
Issued annually, the Catalogue lists all publications
currently available.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Airport Planning
Manual
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
(Doc 9184AN/902)
Part 1
Master Planning
AMENDMENTS
Els==l
~~ ~ ~~ ~~
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
The Council af ICAO on 10 March 1967 (EX-8) approved International, Inc.; British AirportsAuthority; Dallas-
a proposal of the Secretary General that guidance material FortWorth Regional AirportBoard;Department of
be prepared to assist States in planning the expansion Transport, Canada; International A i r Transport Associ-
of existing international airports and the construction of ation; University of California. Additionally, a substantial
new ones. amount of work was done on it by the regular Secretariat.
This project was conceived in the realization of the In 1976 a general revision of the manual was prepared
major impact that expansion of air transport was having by the Air Navigation Bureau, assisted under contract by
and would continue to have on facilities throughout the the firm TCB/MorrisInternational, and by the Air
world, it being recognized that, in addition to the major Transport Bureau whichrevised Chapters 3 and 4. The
problems of great expansion in absolute volume of intent of this revision wasto incorporate experience gained
passengers, cargo and air traffic, the introduction of very from use of the original Manual, experience from the
large-capacity aircraft was likely to cause special problems introduction intoservice of large-capacity aircraft and new
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
at an increasing number of airports. Existing programmes planning technology. This second editionincorporates
of ICAO did not provide airport authorities with guidance changes and additions resulting from an over-all review
for the development of airport master plans in all their made by the Secretariat.
aspects, nor had it been intended that they should.
It is important to note that thematerial contained in this
The first manual entitled Manual on Airport Master manual does not necessarily reflect the views of ICAO nor
Planning was written by three professional airport those who have assisted in its development. It deals in
planners recruited exclusively for this purpose. An many areas in which there is as yet no certaintyor precision
advisory group composed of representatives of the and it is planned to update the material in the future. Any
following organizations provided invaluable assistance in suggestions which may assist in improving and updating
defining the structure of the manual and reviewing this material would, therefore, be greatly appreciated.
material: ACroport de Paris; Aerospace Industries Associ- These should be directed to the Secretary General of
ation of America, Inc.; Airport Operators Council ICAO.
Page pas
3.1 About this Chapter .................. 1-13 SECTION TWO .AIR SIDE
3.2 The Requirements ................... 1.13 DEVELOPMENT .......................... 1-46
3.3 Forecasts Required . . . . . . . . . . . . . . . . . . 1-13
3.4 Accuracy and Limitations of Forecasts . 1-16 Chapter 6 . Runways and Taxiways .......... 1-47
3;5 Converting Annual Traffic Forecasts
into Planning Criteria ............... 1-17 6.1 About this Chapter ................... 1-47
3.6 Factors Affecting Traffic Growth . . . . . 1-18 6.2 Runway and Taxiway Physical
3.7 Principles of Forecasting ............. 1.19 . Characteristics ...................... 1-47
3.8 Forecasting Methods ................ 1-20 6.3 Airport Capacity .................... 1-54
3.9 Presentation of Forecasts . . . . . . . . . . . . 1-22 6.4 Typical Phased Development Plan . . . . 1-58
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
ICAO 9 3 8 4 P A R T t 3 t f 4 8 4 L 4 3 b 0 0 5 8 5 3 5 355
Page Page
Chapter 7 . Aprons ........................ 1-59 9.10 Passenger Amenities and Other
PassengerBuilding Services . . . . . . . . . . 1.108
7.1 About
this
Chapter .................. 1-59 9.11 Consideration of Disabled and Elderly
7.2 Planning
Parameters ................ 1-59 People in Passenger Building Planning . 1-1 11
7.3 Passenger
TerminalApron ........... 1-62
7.4 Cargo
Terminal
Apron .............. 1-66 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.113
7.5 MaintenanceTerminal Apron ......... 1-66
7.6 Parking
Apron ..................... 1-66 Chapter 10 . Cargo Facilities ................ 1-115
7.7 Holding Bays . . . . . . . . . . . . . . . . . . . . . . . 1-66
7.8 General
Aviation
Apron ............. 1-67 10.1 AboutthisChapter ................ 1-1 15
7.9 Helicopter
Apron ................... 1-67 10.2 Sound Cargo Facilities Planning . . . . ~ 1-115
7.10 Apron
Security ..................... 1-67 10.3 Siting . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1
16
7.1 1Fixed Facilities . . . . . . . . . . . . . . . . . . . . . . 1-67 10.4 Systems Planning . . . . . . . . . . . . . . . . . . 1-117
7.12 Apron Taxiways and Aircraft Stand 10.5 TheCargo Building . . . . . . . . . . . . . . . . 1-119
Taxi
Lanes ......................... 1-67 10.6 CargoApron ...................... 1-120
7.13 Apron Service Roads and Ground 10.7 Cargo Facility Requirements . . . . . . . . 1-120
EquipmentParking Areas ............ 1-68 10.8 CargoTerminalArea Access . . . . . . . . 1- 121
10.9 CargoTerminalParking ............ 1-122
References ................................. 1-68 10.10 Control
Authorities Inspection ...... 1-122
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Page Page
12.11 Rescue and Fire Fighting Services .... 1-129 Chapter 14 . Security Considerations ......... 1-134
12.12 General Aviation Facilities . . . . . . . . . . 1-129
14.1 About this Chapter .................. 1-134
References ................................. 1-130 14.2 Land Side Security .................. 1-134
14.3 Air Side Security .................... 1-136
Chapter 13 . Aircraft Fuel Facilities .......... 1-131
References ................................. 1-137
13.1 About this Chapter .................. 1-131
13.2 Storage Capacity .................... 1-131 APPENDICES
13.3 Location of Storage ................. 1-131
13.4 Fuellingof Aircraft ................. 1-131 Appendix A . Glossary of Terms ............. 1-139
13.5 Safety and Special Design Require-
ments Related to Fuelling Systems .... 1-132 Appendix B . Other ICAO Publications
Related to Aerodrome Master
References ................................. 1-133 Planning ..................... 1-142
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
operators deliver and receive passengers,where govern- 3) determination of the environmental effectsof airport
ment control authorities undertake their inspections and construction and operation; and
amenities for passengers’ comfortandassistanceare
provided. Additional requirementsare buildings and 4) establishment of access requirements of the airport.
parking areas for aircraft maintenance, roads and parks
for vehicles used by passengers, visitors, aircraft operators Actual construction of each physical facility designated
andalloccupants of the airport, and buildings for the on the master plan shouldbe undertaken only when traffic
dispatch and receipt of air cargo. volumesandeconomicsindicatethatsuch facilities are
required to meet the demand. Therefore, the master plan
The operation of an airport essentially integrates the should establish a schedule of priorities and phasing for
functions of many of these facilities and, therefore, they the various improvements described in the master plan. A
should not be planned as separate units. Aircraft apron furthereIaborationofwhatmasterplanning is may be
areas have to be functionally integrated with the buildings
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
found below.
with whichthey areassociated.Similarly, vehicle parks
need to be related to the activities of the people who use I. General considerations
them and the buildings which those people occupy.
A. An airport master plan is a guide for:
Airportplanning is theevolution of acompromise - development of on the
physicalfacilities
between the conflicting features of the best plan for each airport
of theindividual facilities. The essentialdegree of pre- - development of land uses for areas surround-
cision and balance in the overall plan varies with the scale ing the airport
of activity which the airport is intended to support. As the - determination of environmental effects of
rate of aircraft,vehicle and passenger movements increases aerodrome construction and operation
itbecomes more necessary forairportplans to be the - establishment of airport access requirements.
optimumcompromise, so thattheplanningof all the
individual facilities contributes and combines into the most B. Among other things, an aerodrome master plan is
efficient total plan andprovidesthegreatest degree of used to:
flexibility and expansibility for future development. - provide short- and long-range policy/decision
guidance
Purpose of a Master Plan - identify
potential
problems
as well as
opportunities
- assist in securing financial aid
Definition and planning considerations
- serve as a basis for negotiations between the
A generallyaccepted definitionstatesthatanairport aerodrome authority/concessionaire interests
- generate local interest and support.
masterplan“presentstheplanner’sconception of the
ultimate development of a specific airport. It effectively 11. Types of activity involved in the muster plan process
presents the research and logic from which the plan was
evolved and artfully displays the plan in a graphic and A.Policy/co-ordinativeplanning:
written report. Master plans are applied to the modern- - project goals and objectives
B. Economicplanning:
It is important to recognize that an airport master plan - prepare an analysis of aviation market charac-
is only a guide for: teristics and forecasts of aviation activity
- determinerepresentativebenefitsand costs
1) development of physicalfacilities of an airport -
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
replaced by data. It is hoped that the method of presen- all framework or plan. This, in turn, provides the sound
tation used here may help to lay the foundation for a set foundation necessary for realization of the maximum
of agreed facts andprinciples on which a general approach advantages of good design, prudent investment and
to airport problems can be based. From such facts more efficient operation and management.
functional airports may evolve.
Support Elements. Chapters are arranged within each of meet, concepts for the various operational systems have to
these sections to present related subject matter in a logical be considered and compared.
order.
1.3.5 The principal factors to be considered are
outlined in this section. Because of their physical charac-
Section One - Airport Planning Process teristics and the land required and all the other factors
which affect them and limit free choice of layout, runways
1.3.2 This section outlines the planning process and and taxiways are the first to be considered. After deter-
the important factors which authorities must consider in mination of the dimensional criteria, pavement strength,
preparing an airport master plan. It explains the import- and airfield capacity and configuration, other elements of
ance of consultation and co-operative planning and the the air side of the airport, namely the apronand navigation
need to develop a systematic approach in determining and traffic control aids are covered in turn.
futureairport requirements. Further,the purpose and
objectives of an airport master plan are described together Chapter 6 - Runways and Taxiways. Because of the
with guidance as to how the master plan should be used, large areas of land they require and their relationship to
once it has been completed. the large airspaces necessary for aircraft operations,
runways and their associated taxiways serve as a starting
1.3.3 Within Section One are four chapters describing
point for consideration of airport layout.
the significant features of the airport planning process.
A substantial body of information exists on the subject
Chapter 2 - Preplanning Considerations. The purpose of planning and design of airport runways and taxiways.
of this chapter is to identify the most important of pre- Theinformation contained in this chapter serves the
planning considerations which, if followed, will provide purpose of informingtheairport planner on matters
the framework for an effective and feasible airport master pertaining to dimensional criteria, pavement strength,
plan. runway length, and airfield capacity. It illustrates the
relationship and importance of these elements in the
Chapter 3 - Forecasting f o r Planning Purposes. overall airport master planning process.
Aviation forecasts provide basic data for determining the
needs and required capacity of an airportand are the basis Chapter 7 - Aprons. The greater portion of this
for projection of airport revenues. chapter brings together, in a capsulized manner, the
significant concepts and considerations needed to satisfy
Chapter 4 - Financial Arrangements and Controls. the planning objectives for aircraft aprons. The chapters
The economic analysis establishes a programme for cover, inter alia: locations, layouts, number of stands
providing the necessary funding of the aerodrome. This required, facilities for passengers and cargo to board and
chapter delineates the more significant elements which leave aircraft, and facilities for aircraft servicing.
need to be considered relative to forecasting and economic
planning.
Chapter 8 - Air and Ground Navigation and Traffic
Chapter 5 - Airport Site Evaluation and Selection. In Control Aids at Airports. Planning of airports must
include provision for facilities which will support the air
order for the airportto have the longest possible useful life
trafficcontrol system, for navigation aids foraircraft
and in order to maximize the substantial capital investment
approaching the airport,and finally for control of aircraft
required in airport development, sufficient ground area
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
2.4.3 Capital costs to be considered at this stage are 2.5.2 For practicalplanning,carefulconsideration
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
broadorder-of-magnitudeestimates, over a period of must be given to the future ability of the airport to meet
years. These include, inter
alia, land acquisition (if these annual capital charges and defrayits direct operating
required),construction,equipment,partsandmainten- and maintenance costs. This must be done from the outset
ance,administrationandoperating costs, andfinancing in order that the scale of facilities and services contem-
fees. Benefits should include increased airport capability/ plated shall not at a later stage prove toexceed the bounds
capacity, increased safetyand reliability, andimproved offinancialpracticability. Aside fromanycontinuing
public service. Where practicable, an estimate should be governmentgrantsorcontributions pledged fromother
madeofthe saving accruing to passengers, cargoand sources,the chief revenue-earningmeansavailableto
aircraftas a result of theproposedinvestment.These an airport, are, in order of importance: charges for the use
savings, including those of time, should be expressed in of landing and
associated facilities; the
granting
of
monetary values. Additionally,the likely impact of the concessions;andtherentalofpassenger-buildingspace
master plan recommendations on the over-all economy of and other airport accommodation andservices. The traffic
theStateshouldbeindicated,includingeffectsonthe forecasts utilized in planning the facilities and services to
balance of payments and employment, among others. be provided should be seen as serving the double purpose
of enablingprojectionsto be made of theincomethe
2.4.4 All of the broad estimates of feasibility made at airportmight expect to derive fromlandingandother
this early stage of the master planningprocess will indicate charges, the calculations being made for various levels of
the propriety of continuing or changing the scope of the charges as a basis for judging what proportion of costs
master plan. Itwill also set the generalguidelines for extent remainingto berecovered by such means would be an
of development possible, consideringtheavailability of achievable target. The extent of the contribution to costs
funds to finance recommended development. Guidance on realizable from such charges must, of course, depend on
financing arrangements and theneed for financial control the assessment made by the airport authorities concerned
andaccountingduringtheplanningandconstruction ofwhat level of charges it would be practicableand
phases is given in Chapter 4 of this manual. reasonable to impose on users, having regard to the nature
of the traffic served and the variety of other circumstances
peculiar to the particular airport.
These may include economicand operational forecasts for airports, organization and effectiveness of central and
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
basic and detailplanning, operational research surveys, local government land planning and transport authorities,
analysis of statistical and sociological data, cost-benefit and the agency legally responsible for financing the
analyses of alternative solutions, aircraft operations in the planning project.
air and on the ground, building construction and traffic
and road planning. The planning team should not include 2.7.2 A most effective organization will be one that is
every specialist whose advice may from time to time be capable of 1) establishing policy which is acceptable within
requiredbutshould be restricted to those necessary to the airport community, 2) bringing together for advisory
cover the primary planning aspects, and who are involved and co-ordinative purposes all appropriate aviation and
at allstages of planning. For example, mechanical non-aviation related interests, and 3) assuring a planning
engineering systems can affectthe size and layout of process that is technically sound and responsive to policy
related areas in addition to the specific area in which they andthe co-ordinativeprocess. Most importantly,the
are contained and have to be consideredin the basic arrangement should be such that the master plan can be
determination of the over-all operating system for established as an effective, continuing programme capable
passenger or cargo areas.The disciplines which should of implementation.
generally be considered for inclusion in a planning team
are statistician, economist, financier, operational research 2.7.3 Unless effective organization, in the above
scientist, architect, civil, mechanical, electrical and traffic terms, is established at the outset, the goals of airport
engineers, pilot, air trafficcontroller and airportmanager. master planning may not be completely fulfilled. A poorly
The advice of all other specialists shouldbesought as organized effort will resuir in 1) fragmented public
necessary. Of course the specific skills appropriateto support, includingavoidable or uninformed public
particular projects depend upon the scale of the traffic for controversy, for the master plan’s recommendations, 2)
which theairport is intended, butit is increasingly unrealistic recommendations that are not acceptable to the
necessary with the growth of traffic toutilize the skills of aviation community or to those responsible for compre-
as many of these specialists as possible. For over-all co- hensive andsurfacetransportation planning, 3) a com-
ordinationanddirection, aplanningteamrequiresa pleted study of no further use, which is not updated in a
planning co-ordinator who should be anexpert in manage- timely fashion and, most importantly, not implemented.
menttechniques and who should have a wide aviation Thus, the importance of effectively organizing the airport
background. This co-ordinator should be responsible for master planning effort cannot be over-emphasized, as it
the evolution of the optimumoverall plan, its progressand may be the most critical step in the process.
cost control. Frequently an aviation consultant will fill this
role. 2.7.4 In general, the organization should be structured
to perform three principal functions, namely, policy
2.6.2 Airport planning should be
undertaken in formulation, advice andco-ordination,and technical
consultation with all other interested agencies and carried planning, as generally described in Figure 2-1.
out in the closest liaison with national and loca1 govern-
ment transportand planningauthorities andaircraft
operators.The civil aviation authorities should act as
leaders in bringing together the government-control 2.8 PLANNING PROCEDURE
authorities with the aim of ensuring a high degree of
facilitation in passenger handling. Figure 2-1 describes the 2.8.1 A master plan for the whole airport should be
relationship of the planning team with the over-all plan- prepared, defining the basic concepts and over-all layout
ning organization. which will best exploit the potential of the site. The master
plan should evolve through consideration of all the factors
which affect air transportand which will influence or
impinge on thedevelopment and use oftheairport
2.7 THE PLANNING ORGANIZATION throughout its working life.
I
I
GOVERNMENT GOVERNMENT CONTROL I
I
I
I AVIATION POLICY
AIRPORT AUTHORITIES (CUSTOMS, I
I MASTERIMMIGRATION,
PLAN SECURITY,
ETC.) I
I DEPARTMENT
I
I MILITARY (IF NEEDED) I
------------ 7
ORGANIZATtONS I
AIRCRAFT AND EQUIPMENT
I MANUFACTURERS I
L--,-,--------l
PLANNING TEAM
DIRECTOR
b
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
PLANNING TEAM STAFF
1
1
CENTRAL AND LOCAL AND AIRPORT
LOCAL GOVERNMENT NATIONAL AVIATION
MANAGEMENT
LAND PLANNING TRANSPORT CONSULTANT
STAFF
AUTHORITIES AUTHORITIES
TECHNICAL PLANNING
_-------------- POLICY
terms andthe dates bywhich they are forecast to be c) Protect and enhance the environment through the
required. Planning procedures for the individual facilities location and expansion of aviation facilities in such
which make up a total airport are the same as for the a way that impairment of the ecology and the
airport master plan. These major stages are: intrusion of unacceptable levels of noise andair
pollution into the community are avoided.
Forecasts: Develop long-term forecasts covering
aviation operational, economic and other factorson d) Promote the establishment of an effective govern-
which future planning can be based. mental organization for implementing the master
plan in a systematic fashion.
Systems concepts: Develop concepts for the basic
systems of operation and identify the developments that Ensure compatibility with the content, format,
will be required to meet the forecast needs of aI1 airport standards,and criteria of governmental aviation
users. policy departments, ICAO and IATA, among
others.
Airport master plan: Determine an ultimate over-all
layout that will best exploit the potential of the site, Co-ordinate the specific airport master plan with the
making the fullest use of any natural features. state airport system and regional air transportation
plans, when they exist.
2.8.3 At all stages of planning, reasons for particular
decisions and the influences supporting particular concepts g)Serve as a basis for co-ordinating plans forair
and lines of progress should be stated and recorded. At navigation facilities, airspace use, and air traffic
subsequent stages the reasons should be tested to ensure control procedures.
that they remain valid and form acoherent and continuous
pattern. Through the long and complex process of devel- h) Inform public and private aviation interests, 8s well
oping airport plans it is easy to make decisions based on as the general public, of aviation requirements, and
judgements which are entirely validinthemselves but create a general awareness of the need for a system-
which conflict with the reasoning for earlier decisions. atic
approach to planning and developing the
Throughout the planning of a project it is important to airport.
ensure that policies, concepts and lines of reasoning are
understood and continuously followed. i) Develop the aviation portion of long-range state
plans and establish appropriate priorities for airport
financing in short-term governmental budgeting for
public facilities.
2.9 GOALS AND POLICY OBJECTIVES j) Optimize the use of land and airspace resources
which are inherently limited in some areas.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
formulation”) and the study design. After these two steps budgetingthat is consistent with theairportfinancing
are completed, thetechnical planning phase begins with an programmes at the national level, and the local budgeting
inventory of existing facilities. Next, a forecast of aviation process.
demand is made in order to determine the future facility
requirements.Alternative systems to meet thefuture
facility requirementsarethen developed andevaluated. 2.10 USE OF CONSULTAN‘TS
While this ends the initial planning process, a continuing
planning process following these same general procedures 2.10.1 The retention of consulting services by airport
is established while implementation of the long-range plan management usuallyinvolves explaining to higher auth-
is underway. ority the need for such services, as well as justifying the
expenseinvolved. However,atacertainpoint in the
2.9.3 The first step in the master planning process is preplanning considerations, employing a consultant is not
the establishment of ground rules which may be termed only desirable but may even be essentiaI.
policy objectives. For example, it is necessary to state at
the outset the time frame, or planning horizons, for which 2.10.2 Onecommonreasonforretainingconsultant
planning is to be accomplished. The geographic limits of services is a lack of technical expertise within the internal
the planning area must also be established in order to guide structures of organizations. It is, most often, not practical
such elements as data collection, forecasting, and potential for a civil aviation agency or authority to maintain, on a
siteselection. Whetheradherencetonational or inter- permanent basis, all of the skills required to manage all
nationalairportdesign/dimensionalstandards will be phases of a large master planning programme. Consultants
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
required, should be determined. are often usedwhen the airport management has insuf-
ficient manpower to perform work ofa temporary nature.
2.9.4 In general, there should be an attempt to relate Rather than increase the permanent staff, consultants are
the
communities’individual
and
sometimes
unique hired to provide additional manpower fora limited period
objectives to the goals in 2.9.1. One should not assume of time. There are also circumstances when assignment of
that all policy can be established at the outset. Airport in-house staff to solve a specific problem would derogate
policy development may take place at several points in the the permanent, long-termmission of the staff. Consultants
master planning process: during preparation, discussion, may be engaged for their experience in areas with which
andinitialadoptionofanairportmasterplan;during the airport management staff is not familiar.
majorreconsideration of theentireplan;andduring
consideration of theday-to-daydevelopmentmatters 2.10.3 Airport projectsmay involve tasks
pro-
which call for the review of general long-range policies. grammed over several years. When there is turnover in the
airport staff, such long-term programmes canbe disrupted
2.9.5 Thelong-rangetimeperiodfortheplan is by a lack of a single management/planning group with
generally 20 yearsandshouldincluderecommended responsibilityforthetotalprogramme,fromstartto
development,timing
of
development,and
order-of- finish.
magnitude costs. Precisedevelopment needs andcosts
should not be required, althougha reasonable estimate of 2.10.4 If, in the planning process, decisions are to be
needs should be expected. Since it may take as long as made whichinvolve considerablerisk,theconsultant’s
10 years for a major airport to be established after its need contribution may be most valuable in the capacity of a
has been identified, a 20-year horizon is not unrealistic. In judgewhocanprovidebothtechnicalexpertiseandan
establishing the length of time for the long-range planning impartial viewpoint. Consultantscanalsoprovidean
period,considerationshould be
given toother local element of objectivity in aidingairportmanagersto
planning efforts such as the transport and land use plans, present their requirements to higher authority.
with consistency as an objective. The intermediate range is
normally for a 10-year period and should more precisely References
determine development requirements and associated cost
estimates than specified in the long-range period. “Airport Master Plans”, U.S. Federal Aviation Adminis-
tration, AC 150/5070-6A, June 1985.
2.9.6 Theshort-range period is normallyfor t w o to
five years and planning should include a detailed treatment “Planning and Completing Airport Improvements”,G . H .
of facility needs and cost estimates. The latter should be Hogarty, Jr., in Proceedings of a Short Course for Airport
sufficiently accurate to permitfinancialplanningand Managers, Texas A&M University, March 1974.
3.1 ABOUT THIS CHAPTER airports, forecasts are generally produced on an annual
basis (forecasting smaller time periods is more complex
This chapter describes the role of forecasting in airport and feasibility is also limited by data availability). But,
master planning. It discusses why forecasts are needed, since capacity utilization of airport facilities becomes most
what forecasts are needed and what they are needed for, critical during daily and hourly traffic peaks, it is the peak
where they fit into the planning functions, and how their demand ratherthantheannual demand that mustbe
validity and contribution might be assessed. The chapter is determined in order to evaluate facility requirements. The
thus one of the philosophy underlying forecasting pro- basic forecasts thus have to be converted into information
cesses and of practical application of the forecasts them- relating to peak periods forbothaircraft movements
selves, rather than an exposition of forecasting techniques. (which define runway, taxiway, air trafficcontrol and
Descriptions of some techniques are given in the comp- apron requirements) and for passenger, cargo and mail
lementary ICAO Manual on Air Traffic Forecasting, throughput (which defines terminal and accesssystem
hereafter referred to as the “Forecasting Manual”. requirements when additional analyses concerning
numbers of visitors accompanying passengers, spectators,
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
airport
i
Capital and recurrent
cast
evaluation A-
master
Airportplan
I
t
I
I Air and ground navigation
~~ ~~
II
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Traffic
forecasts
(limited controi
within plan)
forecasts to
typical peak
hour:
1
I
1
Passengers,
freight and
throughput
mail i I
I
I
I
I
analysis)
I
I
I
I
I
i
4 Income
evaluation
0
0
W
-
1 0
Revise plan if necessary
categories of aircraft ownership, are of little use for airport Types of aircraft using theairport, including the
planning purposes other than’ to point out over-all trends total numbers of each major type and their ratio at
in the development of aviation. Such trends serve only as busy times.
general indicators for the longest term considerations and
donot provide a basis for the planning of individual Number of aircraft to be based at the airport by
airports. scheduled, and non-scheduled carriers and by
general aviation. Base and line maintenance require-
3.3.2 The primary forecast is usually developedin ments of these and other aircraft (broad estimates
terms of passenger and cargo throughput, since historical only required to evaluate airline service area and
data for these items are generally available and the basic access requirements).
demand for use of airport facilities are defined by them.
Access system requirements between the airport and
This demand is mainly determined by factors external to
the region which it serves, since this may affect the
the airport planning process itself and hence provides a
airport layout onboth the air side (e.g.iffeeder
cornerstone from which to build the plan.
services are anticipated) and the land side.
3.3.3As already mentioned, facility requirements are Number of visitors and number of airport workers
defined by peak period throughput, and mainly by that in by category (for use in facilities planning, possibly
the “typical peak hour”. In order not to cater unnecess- including housing requirements).
arily for rare occurrences, the “typical peak hour” is not
defined as the peak hour for the year, but is commonly 3.3.4 Specific categorization may need to be made of
accepted asthe 30th or 40thbusy hour. Similarly the cargo. Arrival and departure characteristics of cargo often
“typical busy day” is the 30th or 40th busy day. An differ appreciably in volume, in timing and in facility
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
important relationship which has to be established is that requirements. Where cargo is expected to arrive or depart
between the primary forecast (Item 1 in the list below) and on all-cargo aircraft as well as in combination aircraft
the typical peak hour forecasts (Item 2 below), a subject (passengers and cargo), categorization is necessary to plan
which is discussed later in 3.5. The list below also includes cargo terminal and handling requirements, and the
other items whichmay require to be forecast. Some of transfer of cargo fromthe combination aircraft to the
them will help to define the above relationship, and indeed cargo terminal. Cargo handling areas are generally
most of them are interdependent. Provided suitable base planned on the basis of a square metre per tonne handled
dataare available, it is worth forecasting major items per unit of time, but this ratio can vary with the traffic
independently as wellas establishing their interaction in mix, degree of containerization etc, and further categor-
order to provide a cross-check on the validity and consist- ization may be necessary (usually based on analyses of air
ency of the forecasts. way-bills). The availability of off-airport consolidation
depots can affect the type and duration of throughput. All-
Annual throughput of passengers, cargo and mail, cargo aircraft movements themselves should be forecast
categorized by international and domestic, by separately as such aircraft can often be directed away from
scheduled and non-scheduled, and by arrivals, peak hours byuseof suitable policies, although such
departures, transit and transfer/trans-shipment. efforts may be limited by night curfews.
Typical peak hour aircraft movements and through- 3.3.5 Since volumes of mail trafficare currently
put of passengers, cargo and mail, preferably relatively small and are generally carried on combination
categorized by arrivals and departures as well as aircraft, a forecast is necessary only to determine space
combined (the typical peak hour may occur at requirements in the: terminal building. If policies for the
different times for each item and categorization). furthertransfer of surface mail to air become more
established in the future, planning for mail can be handled
Average day of peak month aircraft movements and in a similar manner to cargo.
throughput of passengers, cargo and mail, categor-
ized as in 1) above (for use in facilities planning). 3.3.6 Specific attention may also need to be given to
general aviation and charter activities. General aviation
Number of airlines serving the airportand their route activities are particularly difficult to forecast, since theydo
structures, both domestic and international, in not necessarily reflect socio-economic characteristics of the
relation totheairport(for provision of check-in, region or show smooth trends. However, both general
office and maintenance facilities and for cross- aviation and non-scheduled activities can again usually be
checking 1) to 3) above). redistributed away from the peak.
3.3.7 Selection of the forecasts requiredin a particular exceeds the physical ability for provision at an existing
case, and, sequencing of the forecasting tasks in line with airport, the unit of capacity again becomes large. Greater
proposed methods and activity requirements for the plan, accuracyintheforecast(andgreater flexibility in the
are important featuresof the forecasting process. The level master plan) is similarly required for apron requirements.
of detail of the forecast requirements will differ with the
time scale. For example,only broad indications will be 3.4.2 Financial feasibility is a much moreuncertain
required in the first phase determination of land require- factorthantheestimation of physical requirements.
mentsforairportsite selection or expansion.These Financialresults dependonthe margin between total
forecasts should be madeforat least 20 years ahead. revenues and totalcosts which are cumulativeover time. A
Naturally, long-term forecasts of thisnaturecannot be relatively small change in trafficforecastscan havea
expected to be precise, particularly as they need to relatively great effect on finances.
anticipate technological change.
3.4.3 The accuracy of forecasts themselves is subject
3.3.8 Thefuturerequirementsfor handling traffic to a large number of factors, and it is very difficult to
over the projected life of the airport can only be broadly estimate precisely the timing and size of future require-
judged, but they can afford to be somewhat optimistic so ments. The longer the period of the forecast the more there
thatanarea is protected sufficiently toensurethat is scope for variations in factors which affect the results
reasonable development potential of the site is preserved. andthegreaterthefinancial risk involved inerror(a
It may take a longer or a shorter period than forecast for consistent annual 2 per cent traffic growth under-rating
demand todevelop to the foreseen levels, but this is not of becomes a 49 per cent error after 20 years).
majorimportance provided suitable land
areas
are
available to permit development whenrequired (and canbe 3.4.4 The increasing sophistication of forecasting
put to good use in the meantime). methodologyandan increasingsignificance of“objec-
tive” factors in such methodology should
improve
3.3.9 Actualconstructionshouldbecarriedoutas accuracy in the future. Nevertheless, there will always be
proven necessary by the growth of traffic and short-term a numberoffactors which will make forecasting an
forecasts which are less susceptible to major errors. Thus imprecise science. Such factors include:
long-term forecasts provide the broad guidance necessary
for master planning. Shorter-term forecasts, say three to poor forecasting method;
five years in advance, provide thebasis for actual develop-
ment work, while medium-termforecasts (from 5 to poor base data;
20 years,usually in five-year intervals for convenience)
bridge the gap to thelong-term and provide interim infor- poor forecasts of the socio-economic factors which
mation on probable subsequent phases of development. are considered most likely to affect the demand for
air transport;
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
unpredictedintroduction of new socio-economic
3.4 ACCURACY AND LIMITATIONS influencing factors not previously considered to have
OF FORECASTS been of prime importance; and
3.4.1 The degree of accuracy warranted in forecasting the influence of factors which are difficult to
can be defined in relation to the increments in capacity for quantify.
which it is practicabletophaseairport developments.
These will vary to some degree between airports. If the As long as the above limitations are recognized as such,
increments are such that there is no critical dependence on somethingcan be doneaboutthem by examining their
the accuracy of the forecasts, a simple (and inexpensive) likely effects in the planning process.
forecasting system may then suffice. In forecasting aircraft
movements the accuracyrequired is associated with the 3.4.5 Therearetwomajorapproachestohandling
capacity offered by each additional runway. In forecasting limitations i.n forecasting. In order to deal with item 1) in
passenger and freight trafficthroughput somegreater 3.4.4 above, andto some extent with item 2 ) , the approach
accuracy is desirable because the units of capacity in which is to carry out sensitivity tests to establish the range of
terminal buildings can be built and/or extended are smaller accuracy that can be expected in a single forecast - in
than the units of capacity resulting from the addition of other words, to evaluate the probable errors inherent in the
runways. However, if an additional terminal requirement forecasting process given the base data used. The second
approach deals with item 3), and to some extentwith 3.5.2 It is not possible to laydownspecific methods
item 4), and is to prepare alternative sets of assumptions for conversion processes as the method will depend on the
under which the forecasts are made - in other words, to individual situation, and will be related to the forecasting
build up alternative pictures of the future socio-economic method(s) used and vice versa (for example, seasonal
environment and/or policy and hence alternative sets of rather than annual passenger forecasts might be developed
estimates of traffic. It maybe that one factor alone is for the short-term as a means of arriving at more accurate
considered critical (for example airline operating costs, peak information).At large airportsa systematic pro-
and hence fares and rates) and changes are made to this cedure can perhaps be used to translate annual data to
factor while leaving the others unchanged. hourly peaks, but at small airports a single movement of
an aircraft could change the whole situation. Indeed the
3.4.6 One feature of the results of establishing profile over the day might be as important a featureas the
alternative sets of traffic estimates is that the upper limit peak hour itself as this profile would determine policy and
so determined is not necessarily (and indeed not usually) requirements if congestion occurs in the peak hour.
the same amount above the “most likely” estimate as the Nevertheless, some useful guidelines (on both conversion
lower limit is below. This is an important point, as it has and on data requirements) are given by the methods used
an effect on the risks involved in investing in too much to obtain primary criteria from annual data quotedbelow:
capacity as against those involved in investing in equival-
ently too little capacity. Fof assessing financial feasibility A. Estimates ofpeak hour aircraft movements
it is useful to present the most likely forecasts and the
ranges in terms of a time scale (as well as in terms of the Total annual seats from the airport for the most
various volumes of traffic estimated at a particular point recent year for which actual data is available (the
in time). For example: “It is most likelythat a throughput “base” year) are forecast to increase at the same
of 3 million passengers will be reached in 1995; the earliest rate as the forecast of the enplaned passengers (i.e.
that it will probably be reached is 1992, andthe latest no change in enplaned* load factor).
1997”.
Total seats so forecast are then distributed among
3.4.7 Extra work is involved in producing alternative the types of aircraft the carriers are expected to
forecasts, but such work is usually marginal in comparison operate in the forecast year. Seat totals by aircraft
with the work involved in establishing the primary fore- type are divided by average seating capacities to
cast, particularly if a systematic procedure isset up. A obtainthe number of aircraft operations. Total
compromise mayneed to be made between applying annualaircraft
operationsare determined by
resources to refining the primary forecast or to producing summing the operations by aircraft type.
series of alternative forecasts. With alternative sets of
forecasts available, it is possibleto use the planning system The number of seats required during the peak hour
to evaluate the risks involved in investing according to the forthe forecast year are determined by first
criteria suggested by the primary forecast. Estimation of multiplying the annual seats required by the ratio
the planning parameters from the forecasts is, of course, of seats in a typical busy day in the base year to
also subject toerror,afactor which should also be seats in the base year as a whole.
considered in the risk analysis.
The busy day seats required are then multiplied by
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
the base year peakhour percentage of the busy day.
3.5 CONVERTING ANNUAL TRAFFIC The peak hour seats required are allocated among
FORECASTS INTO PLANNING CRITERIA the various types of aircraftthe carriers are
expected to operate during the forecast year, based
3 . 5 . 1 As mentioned in 3.2.3, it is the peak rather than
theannual demand which defines facility requirements.
Intensified effort to produce a quality forecast can be
negated by poor translation of the forecast into facility
requirements - a chain is as strong as its weakest link. Of
paramount importance is the conversion of the passenger
traffic forecast intoannual, seasonal and peak aircraft * Attention is drawn to the distinction between enplaned passenger
movement projections, as well as into seasonal and peak loadfactor and the passenger load factordefinition generally used
passenger
flow projections. carriers by (passenger-krn divided by available seat-km).
Relate the
total
peakhour passenger traffic 3.6 FACTORS AFFECTING TRAFFIC GROWTH
recorded on the peak day over several years to the
total peak day traffic,
to
obtain a weighted 3.6.1 Muchofthedevelopmentworkinthefore-
proportion of peak hour/peak day traffic. casting field is aimed at making forecasts more explana-
tory rather than simply descriptive. There is naturally a
Determine the two peak traffic months in the year greater feeling of confidence in a forecast based on an
from an analysis of seasonal variations. understandingofthe process generatingthe observed
traffic variables. The preliminary phases in a forecasting
Calculatethenumberof passengersusing the procedurearethususuallyconcerned with identifying,
airportontheaveragedayduringthetwo peak isolating and quantifying the effects of the factors under-
months;hypothesizethat
this
average
day is lying air traffic activity.
representative of the 30th - 40th busy day of the
year. 3.6.2 Such factors may be classified into four broad
subject headings: economic, social/demographic, techno-
Relatethe peak hourtrafficratiotothetypical 1ogicaVsystems andcornmercial/political.General indi-
busy day,todeterminethe typicalpeak hour cators in each of these areas are often used for determining
passenger figure by type of service. totalnationalandinternationalairtraffic activity (for
example,grossnationalproduct is often used asone
Divide the typical peak hour by the average number economic indicator), but more specific indi- cators at a
of enplaning/deplaning passengers per movement regional oreven finer level may need to be examined in the
todeterminethe typicalpeak hourmovements case of a particular airport. I t is preferable where possible
figure,notingthatthe“average” is likely to be to categorize the air traffic demand itself by ‘reason i-or
higher than usual during peak periods. travel.since themotivations,and hence theunderlying
indicators, will differ (for example, between business and
3.5.3 There is also a technique commonly referred to non-business trips, between high-income and low-income
as the “triggering” method for adding flight fcequencies traveilers, betweenemergency andplannedair freight
on a route segment. This method is based on the assump- movements, etc.).
tion that when traffic reaches a level which impi’ies some
specified averageloadfactor,anadditional flight is 3.6.3 In the Forecasting Manual there is a table lisring
triggered on that segment. a number of factors thought io influence the demand for
air transport, categorized by specific aspects. ‘These were
3.5.4 Each of thesemethodsand/orothermethods limited to those whose values over a period of time are
can obviouslynot be precise, andeachcouldleadto often readily available from published data, and are again
different results from a given set of data (and, indeed, data intended only as a guideline. Use of a single indicaior or
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
group of indicators, particularly if chosen by reason of objective is to estimate the trafficwhich the airportshould
measurability, should not preclude further examination of serve adequately. This means if past traffic trends are to
be
the activity which it represents. For example, while the used in the forecasting process, they should be adjusted
gross nationalproduct of aparticular country might where necessary for congestion effects.
continue to grow according to historical precedent, the
effects of inflation and floating currencies might affect its
relationship to air traffic growth. Similarly, international
air freight is particularly affected by specific trade tariff
and quota changes. 3.7 PRINCIPLES OF FORECASTING
assessed on subjective
a basis, perhaps founded on take into account all the significan: factors than to use
precedent and/or sophisticatedconcepts (e.g. “value of elaborate methods when dealing w~th-some of them.
time”).
3.7.2 The method(s) of forecasting will depend on the
3.6.5 It is important todistinguish between exogenous available data, on the time and resources available to carry
factors (thoseexternal to the planning function, which out the forecast, andon the purpose forwhich the forecast
cannot healtered within thiscontext) and endogenous is being developed (with which are associated the accuracy
factors (which can be influenced by the plan, up to and requirements discussed under 3.4 above). A forecast or
possibly including public transport policy of the region in forecasting system has therefore usually to be tailor-made
question). to the needs of a situation. It is therefore only possible to
make general observations ratherthan point out any
particular method or procedures.
3 A.6 Assessing the role which an individual airport is
going to play in relation to other airportsmay prove to be 3.7.3 The forecaster should endeavourtake
to
an intricate task. The distribution of the population and advantage of all the significant statistics and other
the locations of theairports in relation t o prevailing information which may be produced in order to approach
directions of the air traffic flows will be important factors. the problem from many sides and check the results of each
Apartfromthe local interaction between neighbouring approach.Inordertoobtain a reliable background of
airports,thefuture relative roles of theairports in a economic, demographic, trade and technical forecasts to
network may depend on demographic developments, on support the demandforecasts, a close liaison with planning
regional developments of business, on the relative growth bodies in other fjelds is highly desirable. A list of scurces
rates for thedemand and the aircraftsizes, on thedevelop- of reliable data was given in 2.3.2. If resources are
ment of aircraft flying ranges and on therelative develop- available,such sources can besupplemented forfore-
ments of terminal costs and en-routecosts for the aircraft.
casting purposes by market analyses of existing data from
Because of the sensitivity of demand t o frequency of carriers (for example, of passenger ticket coupons and/or
service and to the “quality” of services
the being supplied, air way-bills) and/or by setting up market surveys.
a small change in the relative demand at two airports (e.g.
due t o demographic changes or due to a changed accessi- 3 . 7 . 4 As previously discussed, thesophistication of
bility of one of them) may be greatly amplified by resulting the method used should be determined with a view to the
differences in the services being supplied. This may inevitable margin of error in the final result.Different
ultimately lead to a substantial redistribution of the roles methods might be used for the short and long term time-
for the two airports. scales, since a mure accurate peak traffic flow could be
produced if forecasts incorporating seasonality trends are
3.6.7 The efficiency of existing airports is also a factor used in the short term.
which may require particular examination. In a demarid
forecast which is to be used for technical planning of an 3.7.5 An important distinction can he drawn between
airport, effects of congestion and/or other inadequate “top down“ and “bottom up” forecasting. “Top down”
functioning should not be taken into account, since the methodsproject an aggregate figure and then use frac-
tional coefficients and other approaches t.o break it down 3.8.2 Informed judgement of an individual or group
into lower level estimates. “Bottomup” forecasting of people is the original forecasting “method”, and it is
consists of synthesizing forecasts of categorized units. It still the most comprehensive in that it usually implies the
has the advantage of being more easily relatable to cause consideration of a wide range of variables. A large amount
and effect, but the categorized activities are often subject of personal judgement is inevitable, whatever the basic
to wide fluctuations, summation of a number of forecasts forecasting method used. Judgement can introduce
leads to a wider variation in the confidence limits of the subjective and often unsubstantiatedbias, but is useful for
aggregate, andthe cost of processing alot of finely checking thatthe results of other forecasting methods
disaggregated data is high. “Bottomup” forecasts are make sense, and in estimating effects of factors which are
usually more accurate and useful in the short term, and difficult to quantify. One specific feature which might be
“topdown” in the longer term. Wherefeasible, both worth incorporating in the forecasting process is a check
approaches may be used and theresults compared. Indeed, that the evaluation of the long term is not influenced too
it generally is a good idea touse more than one approach greatly by recent or current short-term events.
to forecasting, bothas a cross-check procedureand in
orderto estimatepossible variationsduetoinaccurate 3.8.3 Trend extrapolation consists of trying to
forecasting methodology. identify some long-term underlying growth pattern of a
form which fits the behaviour of air trafficin the past. The
3.7.6 A specific
distinction
must
also be
drawn growth pattern considered over time is usually a straight
between forecasting foran existing airportandforan line (implying a constant absolute changebetween success-
entirely new airport. In cases where the airport concerned ive time periods), or asymptotic (implying that develop-
has been in operation for several years, where the region ment proceeds towards some limiting level at a gradually
to be served is in a state of stable development, and where decreasing rate). A time series of historical data has first
the aircraft operators’network connecting the airport with to be smoothedtoaccountforunusual effects such as
others is well developed, the forecasting may largely be labour strikes, special events,etc. The chosen growth
based on historical data for the airport, the air transport pattern is then fitted to the smoothed data andprojected.
system and the region concerned. Fairly reliable prelimi- Fitting can be done using statistical techniques, but can
nary forecasts may be made by projection of past traffic also be carried out roughly by eye on graphical plots of
trends, and refined forecasts may be developed by analys- historical traffic data. Trend extrapolationassumes that all
ing the factors that have affected the past development. factors influencing airtraffic in the past (except the
unusual effects mentioned above) will continue to operate
3.7.7 An entirely different problem is toproduce in the same way in the future. This is often not the case.
forecasts for a new airport, particularly if the transport Trendextrapolationalso poses problem
a when the
environment is unstable and the region is in a stage of historical data shows a recent kink, asshown in Figure 3-2.
rapid economic development. In such cases the methods Nevertheless, trend extrapolation is a useful tool, in that it
and approacheswill also have to be entirely different. The introduces a degree of objectivity into forecasting. It is
assessment of central traffic flows may prove to be more also relatively easy to carry out andimposes a discipline in
critical than the forecast itself. The approaches used for presenting the situation in a simple form which can aid
new airports include ratio methods (relatingcategorized further analysis and/or providea basis from which to
levels of aviation activity for a particular airport to thatof check the validity of forecasts developed independently by
the region or nationas a whole) and cross-sectional other techniques. Indeed if described as trend analysis it
analyses (analyses and comparisons with otherairports becomes a valuable analytical tool in its own right.
and environments). In the case of a new airportthe
role of market analyses and market surveys is likely t o be 3.8.4 Econometric modelling is one approach used to
significant. attemptto explain airtraffic developmentsinterms of
underlying causes. By using statistical techniques, it has
been shown thatjust a few of thequantifiablemajor
factors influencing air transport demand can explain most
of the variation in this demand, and the contributory effect
3.8 FORECASTING METHODS of each factor can beisolated to acertainextent. The
method can be used both for historical time-series data
3.8.1 As mentioned in 3.1, the Forecasting Manual and/or
for “cross-sectional” data. Forecasts of the
exists as a handbook on techniques; only a brief resume of contributory factors,which are generally less sensitive than
some of those which are relevant toairport master those of air transport demand itself, can then be used to
planning is given here. produce an air transport forecast. Econometric modelling
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
4.1 ABOUT THIS CHAPTER once the project, o r any part of it (e.g. the first of two
planned runways), becomes operational. These two kinds
This chapter explains the significance of financing of costs involve differentfinancingconsiderations and
arrangementsand financial controland accounting in hence need to be dealt with separately.
airport master planning, and provides guidance for
developing practical approaches in these matters. It
discusses the financing of projects in terms of capital and Capital Costs
operational costs, the requirements for domestic and
foreign funds tofinance the capital investment, the various 4.2.2 As far as capitalcosts are concerned(oper-
channels and arrangements through which such financing ational costs are dealt with in 4.2.22 and 4.2.23), the
may be secured, and the sources of income available to an financing plan needs to provide such basic information as:
airport for defraying its costs onceit becomes operational.
The treatment of financial control and accounting brings a)
estimates of thecomponent costs (i.e. labour,
out the close relationship of these two functions and also materials, equipment, etc.) of each distinct part of
the purposes that financial control serves. Alternative the over-all project;
systems of accounting for recording expenses by cost item
or by airport area andservice are described in some detail b) the amounts of funds requiring to be disbursed at
and their relative merits examined. The presentation of various stages in the project’s progress;
assets and liabilities in balance sheet form is described and
a final section devotes itself to budgeting as the medium c) the currencies in which payments are to be made; and
through which financial control is accomplished.
d) the sources from which the funds are to be forth-
coming, and the applicable conditions (i.e. interest
rate, repayment period, etc.).
4.2 FINANCING ARRANGEMENTS
4.2.3 No furtherelaboration seems called for con-
4.2.1 The preplanning consideration given to the cerning a), the estimation of costs having already received
questions of economic feasibility and financing (see 2.4 adequate treatment, orb), since the relevance of such data
and 2.5) should have produced order-of-magnitude is self-evident. Something does however need to be said
estimates of the costs that will be incurred over time by the about currencyrequirements, item c), and sources of
proposed airport development projectandshould also funds, itemd), even though suchguidance as can be
have broadly identified possible sources of thefunds offered in these matters will necessarily have t o be of a
required todefray thosecosts. As the masterplanning generalized nature.
process proceeds, the magnitude of such costs and when
they will be incurred become more definitive. Forecasts of
expected traffic volumes and the definition of potential Currency requirements
revenue sources also
become more detailed, making
meaningful revenue projections possible (see 3.2). These 4.2.4 Where, as will often be the case,project costs
data in turn become essential inputs into the preparation of call for payment in foreignfunds and the national currency
the project’sfinancingplan. The financing plan is in is not freely convertible, it is essential to establish at an
essence a blueprint indicatinghow the costs associatedwith
the project aretobedefrayed,andin its preparation
thought therefore has to be given to both capital costs and
operational costs: theformerconstitutethe investment * ICAO is in the process of developing a manual on airport
that the project represents up to its completion, and the economics. This Chapter has therefore not been revised pending
latter are the costs that are incurred on a continuing basis completion of that manual.
1-23
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
early stage that it will be practicable ti) obtain the foreign d) wages, salaries, allowances and other related costs of
exchange required. The provision of such exchange will expatriate personnel; and
need to be examined with the appropriatefiscal authorities
of thegovernment,andfor thispurpose a statement e) interest on foreign credit.
should be prepared detailing as fully as possible both the
foreigncurrencypayments involved andthe extent to Note.- Policy directives and contractual arrangements
which prospective sources of financing for the project can seeking maximum use of domestic labour and materials
be expected to accommodate foreign exchange problems: can effective
be restraints on foreign currency
While arrangements securing the loan of foreign funds or requirements.
even the provision of foreign goodsand services on
extended credit terms, serve initially to reduce exchange
problems, ail such arrangements nevertheless remaina Sources of funds
legitimate concern of the fiscal authorities of government
since repayment of the debtinvolved ultimately constitutes 4.2.8 A survey of potential sources of funds to finance
a demand on foreign exchange reserves. the project and the selection of which to approach, should
be done as early as possible in the planning process. It is
4.2.5 The extent to which payment of projectcosts important to do so in order to have from the outset an
can be made in domestic currency or will involve foreign indication of the probability of financing being available;
exchange, depends on the many and varied factors present to provide adequate time for completion of the usually
in each situation, and it is therefore only possible to give lengthy preliminaries preceding the conclusion of specific
the following general guide as to the kinds of costs that financial arrangements;andto become versed in the
might typically be expected to fall into each category. procedural and other requirements of such arrangements,
in time to incorporate thoserequirements directly into the
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
importance.Theirevaluation, even though onlyprac- including the financing one: for the latter purpose the bids
ticable in broad terms, should therefore not be neglected should of courseberequired toquote supply prices
(see 2.5). Financialassistance in recognition of such separate from the financingcharges involved, in order that
benefits may of course be sought from government at both such charges may be compared with the cost of financing
national and local levels (e.g. state, provincial, municipal), through any alternativesource. In the financing of costs in
but in so doing the airport should be prepared to demon- sucha mannerthere is, however,a hazard particularly
strate that the particular communities falling within such needing to be guardedagainst,and this is that in the
jurisdictions doin fact derive distinct benefitsadditional to process of selecting bids a firm’s financing capability may
those realized nationally. be allowed to assume an importance disproportionate to
that of other considerations more basic to the project’s
4.2.11 Where an
airport seeks commercial loans successful execution.
directly from banksor other domestic financial institutions
it can expect that forecastsof its future operatingcosts and 4.2.15 Banks, investment houses and other traditional
revenues will be required as a basis for assessing its ability commercialcredit institutionsoperating in theprivate
to repay such loans. Where thatability is judged adequate, sector of the country of the contractor providing goods
such commercialfinancing will probably be obtainable and services for theairportproject, may of course
against an appropriate pledge of future airport revenues, themselves be approached directly for financing assistance
but to theextent that it is found lacking it is likely that the but the cost and other terms of suchcredit as may be
loan will only be forthcoming if repayment is backed by obtainable in this manner are in general likely t o be more
government or some other acceptable guarantor. onerousthanthoseprocurablefromthevarious public
sources which are mentioned hereafter. Commercial
Foreign financing institutions of the kind just mentioned exist in a variety of
forms in differentcountries,andforanyparticular
4.2.12 Project costs payable in foreign funds consti- country the specific ones likely to assist with an airport
tute a demand on the State’s reserves of foreign exchange project areprobably best ascertained directly fromthe
and assuch their financing will usually have to be arranged government concerned.
through, or with the approval of, the appropriate fiscal
authorities of government. 4.2.16 Foreign financing may also be available from
foreign governments in theform of loans negotiated
4.2.13 Depending onthemagnitudeofthe costs directly with the government of the recipient country, or
involved and the state of exchange reserves, it may prove mayotherwise be facilitated by particular agencies of
possible toobtainthe requiredfinancing through such government which have been established for the primary
domestic institutions . a s havealready been mentioned purpose of promotingthenation’s export trade.The
above, but more often than not this will not be thecase and development of transport facilities and the consequential
foreign sources will need to be found. In any event, quite benefits to the national economy as a whole which are
apart from foreign exchange considerations, such sources envisaged as resulting from any given project, may evoke
should always be explored as a matter of course, since the provision of suchassistance forvariousreasons,
financingmay be availablefromthemontermsmore among thembeing the desire to promote trade and cultural
favourable than those procurable from domestic institu- relations between thetwo countries. Additionally, as
tions (i.e. lower interest rate, repaymentoveralonger mentioned, the wish to facilitate the export of technology
period, etc.). and equipment required for theproject and availablein the
assisting State, may be a further reason for interest.
4.2.14 One of the simplest ways of dealing with costs Usually the availability of such assistance, as wel! as any
payable in foreign funds is to place the responsibility for negotiations subsequently involved, will need to be
financing arrangements on foreign contractors
and pursued through the appropriate governmental authorities
suppliers who stand tobenefit directly from the project. In of the State in which the project is being undertaken.
foreigncommercialdealingsit is oftenthe practice for
suppliers to be required to state as part of their bid the 4.2.17 In the case of developing countries in particu-
financing arrangements they are prepared to extend, and lar, suchassistance may be forthcomingthrough the
for contractors to be given the responsibility of securing specific aid programmes which certain governments have
the most favourable terms. When applied, such practices established to promote economic and social development
wiiI not onlyhelp to reduce thefinancing problems in various areas of the world; these programmes extend
encountered in airport projects, but will also enable the assistance in such forms as loans on preferential terms and
acceptability of bids to be evaluated from all aspects, the directprovision of supplies, equipmentand tech-
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
nology. Illustrative of programmes of this nature are those the various development banks, the InternationalDevelop-
administered by the Canadian International Development ment Association or the European Development Fund will
Agency, the Overseas EconomicCo-operationFund of inevitably entail government involvement. In general, this
Japan,andtheUnitedStates Agency forInternational likely will be so for two reasons. First, any loan or grant
Development. For projectsnotqualifyingforaidfrom that may be extended will be made elther to a government
such sources as these, assistance in meeting the require- or government agency, or to a privateentity with the
ments for €oreign financing may otherwise be available support and guaranteeof the government. Second,usually
through the special export-promoting agencies created by the first test of suitability of a project is whether the sector
certain governments: assistance from these sources takes of the economy inwhich it falls, and the project itself, are
various forms, including direct loans by the agency itself, of high priority for development and are so recognized in
guarantees covering private loans, and insurance of the the government’s development plans.
risk assumed by national enterprises in providing goods
and services on credit terms. Examples of agencies of this 4.2.20 The International Finance Corporation, for its
characteraretheExport Development Corporation of part, has a quite distinct role, which supplements that of
Canada,theExport-Import Banksof Japanandthe the International Bank for Reconstruction and Develop-
United States, and the Export Credits Guarantee Depart- ment, its purpose being to further economic development
ment of the United Kingdom. by encouraging the growth of productive private enterprise
in member countries,particularlyinthe less developed
4.2.18 Additionally and, over-all, probablyof most areas. Briefly, the means selected for achieving this aim
importanceamong the possible
sources of foreign are: to assist, in association with private investors,with the
financingavailable to developingStates, arethe inter- financingof suchprivateenterprise by making invest-
national institutions that have been established to assist in ments, without guarantee of repayment by the member
the financing and execution of projects seeking to promote government concerned, in cases wheresufficientprivate
national economic development. Prominent among these capital is notavailable on reasonableterms; to seek to
are
the
International Bank for Reconstructionand bring togetherinvestment opportunities,domesticand
Development and its affiliates - the International foreign capital, and experienced management; and to seek
DevelopmentAssociation andtheInternationalFinance to stimulatetheflow of domesticand foreign private
Corporation; the various regional development banks; and capital into productive investment in member countries.
the Commission of theEuropeanCommunitiesforthe The Corporation’s roleis clearly such that airport projects
European Development Fund.Thelocations of these cannot be expected to attract any direct financing assist-
particular institutions are as follows: ancefrom this source,but conceivably there could be
situations where domesticfinancialinstitutions, endeav-
ouring to find foreign capital for projects of this nature,
International Bank for Reconstruction and
Development, Washington, D.C., United States might find themselves able to benefit from its services.
International Development Association,Washington,
4.2.21 Finally, to beborne in mind by developing
D.C., United States
International Finance Corporation, Washington, D.C., countriesas a source of assistance in financing airport
United States project costs payable in foreigncurrencyas well as in
African Development Bank, Abidjan, C6te d’lvoire nationalcurrency, is theUnitedNations Development
Programme(UNDP).Thevarious kinds of expertise
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Asian Development Bank, Manila, Philippines
Caribbean Development Bank, Bridgetown, Barbados required for the consideration, planning and execution of
Inter-American Development Bank, Washington, D.C. airport development projects, such as will be entailed in
United States the necessary feasibility and cost-benefit studies, in the
Commission of the EuropeanCommunitiesfor the preparation of master plans and in the actual construction
European Development Fund, Brussels, Belgium. phaseitself,mayall be requested fromthecountry’s
programme of UNDP funded technical assistance. As well
as expertise, funding for necessary airport equipment may
4.2.19 As in the case of financing by foreign govern- also be obtained through theUNDP. Where such technical
ment, the possibilities of financial assistance being forth- assistance is to be soughtforanyairport development
coming fromtheaboveinstitutionsforanyparticular project the specificrequirements will need to be formu-
airport development project,andtheprocedures to be lated andsubmittedtothenationalgovernmentfor
followed in applying for such assistance, will need to be approval within the country’sover-all programme of
ascertained throughthe government of thecountry in development projectsfor which technicalassistance is
which the project is being undertaken. Any approach to being requested.
Operational Costs passengers and cargo (often such facilities are not the
subject of separate charges but are included in the cost
4.2.22 Brief mention has already been made in 2.5 of base used for setting landing charges)
the need for carefulconsideration to be given in the
planning process to the future ability of the airport tomeet Parking and hangar charges: covering the use of
the recurring costs which have to bedefrayedonce the parking space and airport-owned charges hangars, and
airport project, or any part of it, becomes operational. the provision of associated aircraft towing service.
Broadly, such costs comprise operating, maintenance and
administrative costs; interest and depreciation or amortiz- 4.2.26 No precise guidance can be given for setting the
ation chargeable in respect of capital assets; interest on level of such “user” charges as the foregoing, since this
investment; and any taxes that may be payable on income will depend in each case on the magnitude of the airport’s
or property. For convenience these may be collectively operational costs, the income it derives from other sources
termed operational costs. They will be found described in (particularly those of a “non-aeronautical” nature dealt
more detail asto their components in 4.3.14 through with later), the volume and character of the air traffic it
4.3.18. serves, and a variety of other considerations. Certain
principles and other guidelines relating in particular to the
4.2.23 Consideration of the means by which such bases on which “user” charges should be established, have
operational costs are tobe financed needs to be undertaken however been developed by ICAO‘for application t o
on the basis of as close an estimation of their expected international civil aviation, and this material, to be found
magnitude, year by year, as can be made in the planning in Statements by the Council to Contracting States on
process. Indispensable to such estimation will, of course, Chargesf o r Airports and Route Air Navigation Facilities
be the traffic forecasts prepared for the project and the (Doc 9082), should in itself prove useful toairport
adjustment of operational costs otherwise needing to be authorities in general when they come to determine which
made on account of anticipated changes in future price costs are to be recovered through such charges and which
levels. With the magnitude of costs established,the sources particular kinds of charges they should establish for this
of revenue available to the airport for defraying them have purpose.
then to be identified and, this done, the yields expected
from such sources will need also t o be estimated as closely 4.2.27 Theother source from which earned income
as possible, with the traffic forecasts again being used for can be derived by the airport consists of what has been
this purpose. collectively referred to above as its ancillary or non-
aeronautical activities. Described in more detail in 4.3.12,
Sources of income the various revenues accruing from these activities include:
4.2.24 The sources of earned income, as distinct from 1) concession fees from aviationfuel and oil companies
any grantsor subsidies forthcoming from governmental or and othercommercial concerns doing business at the
other sources, which are available toanairportare airport;
various. For purposesof considering the financing of costs
it will be useful to classify these according to the two broad 2) revenue from therental of airport land,premises and
kinds of activity engaged in by an airport, namely its air equipment;
trafficoperationsandits ancillary(non-aeronautical)
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
adequately serves the basic requirements for effective involves its own expense which may become substantial,
financial control of the new airport project. If not, the particularly when electronic data processing and com-
decision will have to be made as towhat modifications are puterization are involved. The basic decision to be made in
required so as to enable the extraction of the data required this context is therefore what financial information is a)
for the degree of financial control sought. On the other essential and b) desirable or optional. Thechoice of design
hand, if the project is new, it will then be necessary to of the system to be instituted should focus primarilyon its
design an accounting system that meets the project’s ability to generate theinformation under a). As it is,
requirements. however, always possible to design a basic system in more
than one way, some variant may be found which lends
itself to extension insucha way asto yieldb) type
Purposes of Financial Control and Accounting
information at little or even no added expense. In general,
any basic system can of course be amplified to provide
4.3.7 The purposes of financial control are many, but
additional data, but given that accounting remains a tool
the basic one is to ensure that all the resources are being
of financial control, thecriterionjustifyingmorecom-
prudently, effectively and honestly utilized. Ensuring such
plexity must always be that the addedcost entailed will be
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
control is not only of primary concern for those directly
commensurate with the value of the extra data obtained.
involved in the management of the airport project, but is
also animportant prerequisite for obtaining outside 4.3.10 Accounting data have two primary uses. The
financing for the project on the most favourable terms. If first, and generally the better known, is in presenting the
there is a sizeable difference between theactualand financial position of a project, i.e. to show the profit or
planned (or budgeted) costs of any part of the project, loss situation during a given period and the status of the
management must determine whether the original plan or project with regard to its assets and liabilities. The second
budget contained inaccuracies or was unrealisticin its and equally, if not more, important use is to serve as a
predictions, or whether there were other causes accounting basic tool for financial control of the project, as has been
for the difference, so that steps may be taken to avoid mentioned earlier.
discrepanciesarising elsewhere for similarreasons.Any
substantial divergence from theoriginal budget for a 4.3.11Ageneralstatement which can be made with
specific portion of the project will itself also normally call respect to airport accounting is that the identification and
for review of the whole budget so as to determine whether subsequent recordingof items can, asa rule, be more easily
this divergence will alter the over-all costs of the airport accomplished for revenues thanfor expenses. This is
project. To the extent that such reviews disclose chiefly because airport revenue sources tend to be fewer in
deficiencies in the original planning of capital numberthan expense items, and because each revenue
requirements, they will also be useful in providing lead- item, with few exceptions, is often easily identifiable with
time for procuring the additional financing found to be oniy one source, whereas one expense item can frequently
required. This will be of particularbenefit where the be identified with several major expense categories. The
shortfall would otherwise ultimately
cause delays in information required in an airport accounting system can
execution of the project. vary considerably in detail and layout, but there is a basic
itemization of revenues and expenses that may perhaps be
considereda minimum and this is described in the
Accounting following sections.
2. Ground handling charges 3.3 Rentah: rentals payable by commercial enterprises and
other entities for the use of airport-owned building space,
land or equipment.Suchrentalsshould include those
3. Ancillary operations payable by aircraft operators for airport-owned premises
and facilities (e.g. check-in and sales counters and
3.1 Aviation fuel and oil concessions administrative offices) other than those already covered
(including throughput charges) - under air traffic operations (see item t above).
3.2 Other concessions
3.4 Other revenues from non-aeronautical activities: all other
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
5 . Other revenues 4. Grants and subsidies: any payments received and not requiring
the transfer of assets or provision of services in return.
Total revenues
Expenses
3. I Aviation fuel and oil concessions (including throughput 2 . Supplies and services
charges): all concession fees, including any throughput
charges, payable by oil companies for the right to sell 3. Depreciation and/oramortization
aviation fuel and lubricants at the airport.
4. Interest
3.2 Other concessions: fees payable by other commercial
enterprises for the right to sell goods and services at the
airport. overheads 5 . Administrative
allowances, etc.
taxiways, aircraft parking areas) and
2. Supplies and services: costs of spareparts and consumable their associated lighting
materials actually incorporated or expended in providing all
airport facilities and services and in operating and maintaining 2. Passenger and cargo terminal facilities
fixed assets (including durable equipment such as vehicles,
(owned by the airport)
machinery, furniture and fixtures, tools, etc.). Included also
are the costs of supplies and services required for heating, air-
conditioning, lighting, water, sanitation, postage, etc. 3. Hangar and maintenance areas
Payments made to other agencies or enterprises for provision (owned by the airport)
of airport facilities and services should also be included under
this item.
4. Fire-fighting, ambulance and
3 . Depreciation and/or amortization: the amount by which the security services
value of theassets has decreased during the year due tophysical
deterioration, obsolescence and such other factors aslimit their 5. Air traffic control (including
productive life. Also to be included are amounts bywhich communications)
intangible assets (e.g. developmental and training costs) have
been written off during the year.
6. Meteorological services
4. Interest: interest paid or payable on debt during the year as well
as any interest computed on capital assets. 7. Other expenses
Not mentioned in the notes, but dealt with in 4.3.14 in the expla-
4.3.15 Expenses by area or service. An accounting nation of items 3, 4 and 7 are depreciation and/or amortization,
system design to reflect costs by airport area and service interest and taxes. It should be understood that these costs will also
entails the maintenance of two sets of accounts, namely, need to be redistributed from the main to the subsidiary accounts
main accounts devoted toparticular cost items asjust if a comprehensive record of the full costs attributable to each area
and service is to be established.
described, and subsidiary accounts devoted to the various
areas and services under which it is intended to redistribute I . Aircraft movement areas: all maintenance, administrative and
the costs recorded in the main accounts. Thus,for operating costs attributable to these areas and their associated
example, salaries paid to maintenance staff wouldbe vehicles and equipment, including the expense of all labour
entered both in the main account for salaries and also in (skilled and unskilled), maintenance materials, power and
fuels.
the subsidiary accounts for different areas on a prorated
basis according to the hours of maintenance devoted to 2. Passenger and cargo terminal facilities (owned by the airport):
each. Entries in the main and subsidiary accounts will best all maintenance, operating and administrative costs for
terminal facilities, including, where applicable, such expenses Assets and liabilities
as relate to any airport-operated shops and services located in
the terminals (e.g. staff salaries, costs of stock sold and any 4.3.19 The systematic presentation of assets and
spoilage, and the cost of utilities and general upkeep provided liabilities in the form of a balance sheet is a less common
in such cases), but excluding any costs of work which, under
particular !easing arrangements, are borne by lessees. practice among airports thant h e preparation of statements
ofrevenues and expenses. An importantreason is that
3. Hangar and maintenance areas (owned by the airport): all airports are for the most part not operated as private or
related maintenanceoperating
and
administrative costs, stock companies, but tend to be part of a department or
excluding any costs of work which, under particular leasing agency of government whose accountingrequirements
arrangements, are borne by lessees (e.g. maintenance of
hangars).
normalry d o not call for preparation of a formal balance
sheet.However,airportsrun by public orotherauton-
4. Fire fighting. ambulance and security services: all operating, omous bodies are generally more likely to provide thistype
maintenance and administrative costs attributableto these of information since in many instances there wili exist a
services, including staff salaries and the expense of maintaining statutory requirement for them to do so.
the associated vehicles and equipment.
5 . Air traffic control (including communications, i.e. fixed and 4.3.20 While assets and liabilities may not generally be
mobile services and radio navigation aids): all related as readily availableas revenue and expense data,any
maintenance, operating and administrative costs, including in airportmanagementshouldhavecertain basic compi-
particular the expense of power and anyspareparts consumed lations of such data at its disposal. The most significant
by radars, receiving and transmitting stations, NDBs, VORs,
ILS, and other equipment employed. items would generally be such as indicated below:
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
a) broad determination of the land area required; 5.2.2 The ICAO Aerodrome Design Manual,
Part 1 - Runways, provides anexplanation of the
b) evaluation of factors affecting airport location; parameters
affecting
runway
length
together with
I-34
nomograms for calculation of runway lengths for specific maximum allowable cross-wind depends not only on the
aircraft for airport planning purposes. It also explains the size of the aircraftbut also on thewing configuration and
concept of using a combination of runway, stopway and the conditionof the pavement surface. Transport category
clearway as a stage in long-term development. aircraft can manoeuvre in cross-winds as high as 56 km/h
(30kt), but it is quite difficult to do so; hence lower values
5.2.3 To avoid imposing unnecessary aircraft are used for airport planning.
operating restrictions and incurring disproportionate
construction and maintenance costs, adequate space 5.2.8 Annex 14 specifies that runways should be
should be provided to permit runways to be developed to oriented so aeroplanes may be landed at least 95 per cent
meet long-term requirements. Consequently, the perform- of the time with cross-wind components as follows:
ance characteristics ofbothcurrentandfuture critical
aircraft, i.e. those with the maximum requirements within Cross-wind component Aeroplone reference field length
the broad groupof aircraft anticipated to use the airport,
are significant. Even if aircraft planned for introduction 37 km/h (20 kt) 1 5 0 0 m or over
within the foreseeable future when operating over similar 24 km/h (13 kt) 1 200 m orupto but
stagelengths were nottorequire longer runways than not including 1 5 0 0 m
current large civil aircraft, such factors as the
possibility of 19 km/h (10 kt) less than I 200 m
longer direct flights and relegation of currentlarge aircraft
to secondary routes, with a need for runway extension and An exception to the above forrunways 1 500 m or over is
development, requires consideration. that when poor runwaybraking action owing toap
insufficient longitudinal coefficient of friction is experi-
5.2.4 For long-term planning detailed runway length enced with some frequency, a cross-wind component not
requirements cannot bedefined with certainty. Never- exceeding 24 km/h (13 kt) should be assumed.
theless, planning would be seriously deficient unless
reasonable provision were made for the future. Adequate 5.2.9 After
the maximum permissible cross-wind
landshould be acquired or protected to provide for component is selected, the mostdesirabledirection of
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
possible ultimate
runway
development, including runways for wind coverage can
be
determined by
protection of approachesand provision for associated examination of the wind characteristics for the following
visual and radionavigation (non-visual) aids. When conditions:
consideringlong-termrequirements, advice should be
obtained from the aircraft operators regarding their future a) The entire wind coverage regardless of visibility or
aircraft operating characteristics. Although itis possible cloud ceiling; and
that all the land reserved for long-term use may not be
required, errors of underestimation may prove insoluble. b) Wind conditions when ceiling is between 60 m and
300 m and/or the visibility is between 0.8 km and
Runway Orientation 4.8 km.
5.2.5 Annex 14, Chapter 3 and Attachment A, The first condition represents the entire range of visibility,
provides details of variousaspectsconcerningrunway from excellent to very poor. The next condition represents
orientation. various degrees ofpoor visibility requiring the use of
instruments for landing. It is importantto know the
5.2.6 In broad terms, runways should be oriented so strength of the winds when the visibility is restricted.
thataircraftarenot directedoverpopulated areasand Normally when the visibility approaches 0.8 km and the
obstructions are avoided. Subject to all other factors being ceiling is 60 m, there is very little wind present, the visi-
equal theyshould be oriented in the direction of the bility being reduced by fog, haze, smoke, or smog.
prevailing wind when it blows consistently fromone Sometimes the visibility may be extremely poor, yet there
direction. is no distinct cloud ceiling; for that matter, noclouds need
be present at all.Examples of thiscondition are fog,
5.2.7 As a general rule, theprimaryrunway atan smoke, smog, haze, etc.
airport should be oriented as closely as practicable in the
direction of the prevailing winds. When landing and taking 5.2.10 The “95 per cent” criterion recommended by
off, aircraft are able manoeuvre
to on a runway as long as ICAO is applicable to all conditions of weather; never-
the wind component at right angles to the direction of theless, itis still useful to examinethe data in parts
travel
(defined as cross-wind) is not excessive. The whenever this is possible.
5.2.1 1 Weather records can usually be obtained from data for all conditionsof visibility arethose shown in
government weather bureaux. The velocities are generally Table 5-1. From these data a wind rose can be plotted as
divided into 22.5 degree increments (16 points of the shown in Figure 5-1.
compass). The weather records contain the percentage of
time certain combinations of ceiling and visibility occur 5.2.14 The percentage of winds which corresponds to
(e.g. ceiling, 500 to 274 rn; visibility, 4.8 to 9.7 km), and a given direction and velocity range is marked in the proper
the percentage of time winds of specified velocity occur sector on the wind rose. Optimum runway directions can
frcrn different directions, (e.g. NNE, 4.8 to 8.5 km/h (2.6 be determined from the wind rose by the use of a strip of
:o 4.6 kt)). The directions are ir! reference to true north. transparent material on which three parallel and equally
spaced lines have been plotted. The middle line represents
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
5.2.12 Often wind data for an entirely new location therunway centre line, andthe distance between the
have not been recorded. If that is the case,records of outside lines is, to scale, twice the allowable cross-wind
nearby measuring stationsshould beconsulted. If the component (in the example, 48 km/h or 26 kt).
surroundingarea is fairly level, the records of these
stationsshould indicate the winds atthe site of the 5.2.15 Thetransparentstrip is placedover the wind
proposed airport. If the terrain is hilly, however, the wind rose in sucha manner that the centre line on the strip
pattern is oftendictated by thetopography,and it is passes through the centreof the wind rose. With the centre
dangerous to utilize the records of stations some distance of the wind rose as a pivot point, the transparent overlay
from the site. In that event, a study of the topography of is rotated until the sum of the percentages included
the region and consultation with long-time residents may between the outside lines is a maximum. When one of the
prove useful. outside lines on the transparent strip divides a segment of
wind direction, the fractional part is estimated visually to
5.2.13 The directions of the runways can
be the nearest 0.1 per cent. This procedure is consistent with
determined graphically as follows. Assume that the wind the accuracy of the wind data.
Percentage of winds
7-24 km/h 26-37 km/h 39-76 km/h
direction
Wind (4-13 kt) (14-20 kt) (21-41Total
kt)
N 4.8 1.3 0.1 6.2
NNE 3.7 0.8 ___ 4.5
NE 1.5 0.1 ___ 1.6
0.3 ENE 2.3 --- 2.6
0.4 E 2.4 ___ 2.8
ESE 5 .O 1.1 --- 6.1
SE 6.4 3.2 0.1 9.7
7.7 SSE 7.3 0.3 15.3
S 4.4 2.2 0.1 6.7
ssw 2.6 0.9 ___ 3.5
0.1 sw 1.6 --- 1.7
0.4 wsw 3.1 --- 3.5
W 1.9 0.3 --- 2.2
W NU' 5.8 2.6 0.2 8.6
2.4 NW 4.8 0.2 7.4
NNW 7.8 4.9 0.3 13.0
Total 100.0
5.2.16 The next step is to read the bearing of the to the percentage segment between the 19 km/h (10 kt)
runway on the outerscale of the wind rose where the centre circle and the 24 km/h (13 kt) paral!el lines and added to
line on the transparent strip crosses the direction scale. the percentage lying within the 19 kmih (10 kt) circle.
Because true north is used for published wind data, this
bearing usually willbe differentfromthat used in Low visibility wind analysis
numberingrunways which are based onthe magnetic
bearing. In reference to Figure 5-1, it will be noted that a 5.2.18 The next step is to examine wind data during
runwayoriented 150 te 330 degrees (S30"E true) will the restricted visibility conditions cited previously and plot
permit operations 95 per cent of the time with the cross- a wind rose for this condition. From this analysis it can be
wind components not exceeding 24 km/h or 13 kt. ascertained whether the runways are capable of accepting
aircraft at least 95 per cent of the time when restricted
5.2.17 Thus far the procedure has been illustrated as visibility conditions prevail. The analysis will also yield
it applies to wind records with a velocity break at 24 km/h information on thepercentage of the total time each of the
or 13 kt. However, it can also be used to obtain estimates conditionsprevails. An example of theformon which
of wind coverage for any other velocity break. The restricted visibility data are
tabulated is shown in
concentric circles on the wind rose are drawn to scale and Figure 5-2. Figure 5-2 represents observations of winds in
represent breaks in the wind velocity data. Suppose the one compassdirection only, in this instance fromthe
break was at 19 km/h instead of 24 km/h (10 kt instead of northeast.Thetotalnumber of observations for all
13 kt). Then the twoparallel lines representing the 24 km/h compass directions is 24 081, of which 1 106 are for winds
or 13 kt maximum allowable cross-wind component would from the northeast.To complete the analysis, charts of this
not be tangent to the 19 km/h or 10 kt circle but would lie type would have to be plotted for
other compass
outside of it. Anestimate must then be made of the directions. For the purpose of the example it was assumed
fractional percentage segment between the 19 km/h (10 kt) that a ceiling of 290 m was equivalent to 300 m. Thecircled
circle ahead of the 24 km/h (13 kt) parallel lines and added number 7 means that there were seven observations made
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
10 I 4 I 14
% by
velocity
1 1.6-7 km
10
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
when the wind was fromthenortheast with velocities variations in weather pattern, prevailing winds, fog,
varying from 8-15 km/h (4t o 8 kt), ceiling between 0 and low cloud, rainfall, snow, turbulence, etc.
30 m, andvisibility between 0 and 400 m. The crosshatched
area
conformsto
the ceiling and visibility criteria Accessibility to ground transport- note the location
previously cited. of roads, railways, and public transport routes.
-
1-40 - Airport Planning Manual
:he advantages and disadvantages of eachsite. Airports need t o be avoided. It is important to maintain clearance
should be sited so that aircraft operations can be carried from masts and similar inconspicuous skeletal structures
aut efficiently and safely, so that they are compatible from because,althoughmarking and lighting can assist in
a social viewpoint and so that the cost of development is directingattention to them, it doesnotoffercomplete
kept at the optimum level, taking all factors into account. protectionparticuIariy
during
conditions of reduced
The factors of major importance may be grouped under visibility.
operational, social and cost considerations.
5.5.6 Any objects which limit the available flight path
may limit the efficiency of operations. If tall structures
Operational Considerations exist in, or near, areas otherwise suitable for instrument
approaches, non-standard procedure heights may need to
Airspace beadopted, with consequenteffect on theduration of
approach procedures and the demand of useful altitude
5.5.2 Annex 14 and theProcedures f o r Air Navigation allocations to aircraft in associated holding patterns. Such
Services - Aircraft Operations contain detailed infor- structuresmayfurthermore limit desirable flexibility of
mation on holding and approach-to-land procedures and radar vectored initial approaches and the ability to turn en-
instrument approach systems and aids - procedures and route during the departure climb.
obstacle clearances.
5.5.7 In assessing the potential of any site to provide
5.5.3Adequate airspace is so importantfor
the clear approaches, the approaches should be gauged against
efficient operation of an airport that special attention is the maximum runway lengths envisaged in the master plan.
required t o ascertain that each site is satisfactory in this If the site is suitable for maximum planned lengths, it wili
regard and, if not, to determine the extent and likely effect likely place few restrictions, if any, on earlierphases of the
of any restrictions. A site close to a demand centre butwith plan.
some restrictions on airspace may be preferable to a site
with no airspace restrictions but so remote or difficult of
access that it creates little or notrafficdemand.Such Hazards
factors have to be weighed tc achieve the bestbalance.
5.5.8 Local factors can be important in relation to the
When two airports have to share the same airspace, their
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
locationofindividual sites. For instance,industrycan
combinedaircraftmovementratesmaybe restricted.
producesmoke which maybeconcentrated in certain
Instead of being able to operatecompletely independently
directions by the prevailing wind. As a result, visibility in
of each other to the limit of their individual capacities it
someareas
may be
restricted and VFR operations
will be necessary to phase aircraft movements, each airport
precluded. Sites adjacent to wildlife reserves, lakes, rivers
with the other, in order to maintain the necessary physical
and coastal areas, refuse dumps and sewage outfalls, etc.,
separation between aircraft. Therefore, new airports
may not be desirable because of the danger of aircraft
should be located so that any overlap with the airspace
collision with birds. This is of special importance where
required €or aircraftusing other airports, and the resultant
faster, larger aircraft are involved. The location of sites
limitation of total capacity, is minimized. For the same
relative tothemigratorypatternsandroutes of birds,
reason, potential airport sites need to be studied in relation
to ATS routes so that similar problems are avoided. especially large birds such as swans andgeese a!so requires
consideration.The Airport Services Manual, Part 3,
contains detailed informationon assessing thepotential
bird hazard at a site.
Obstacles
Approach and landing aids inefficient or inadequate transport systems which do not
permit smooth flow of traffic at all times will necessitate
5.5.10 For details of visual aids, see Annex 14, expenditures to overcome these deficiencies. Locations
Chapter 5 and the Aerodrome Design Manual, Part 4. See offering convenient connexion to an adequate
road
Annex 10 for references regarding siting and clearance network, and, as appropriate railways and waterways, are
requirements for radio-navigation (non-visual) aids. Aids preferable, all other factors being equal.
to navigation, approachand landing are an essential
element of the air transportsystem. Non-visual (electronic) 5.5.14 The authorities responsible for
roads
and
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
aids for guidance, especially under low cloud ceiling and public transport systems should be informed of any
restricted visibility conditions, are more significant from proposals for construction ofnew airportsandmajor
an airport siting viewpoint because of the clearances extensions to existing airports during the early stages of
required from objects (power lines, large buildings, investigation. Their assistance should be sought in
moving vehicles, etc.), which can affect their reliability of acquiring details of existing facilities and their planned
operation. They have to be sited relative to the airports, development. This will ensure that these authorities are
airspace and aircraft flight paths to be served and potential fully informed andwill establish an environment for future
sites should include suitable areas for their installation. co-operation.
5.5.12 Airports should be conveniently situated in 5.5.16 Aircraft noise in the vicinityof airports is a
terms of travelling time and distance from both existing serious problem. Factors tobe included in airport planning
andfuture population centres and the commercial and include the measurement and description of aircraft noise,
industrial areas whichthey are intended to serve. The land-use control,ground
run-up
and flight noise
location of potential sites requires consideration, abatementoperating procedures, aircraft noise certifi-
therefore,from the over-all viewpoint of passengers, cation,human tolerance to aircraft noise, the effect of
shippers of air cargo, aircraft operators and staff, labour increased traffic and the introduction of future aircraft
force, erc. The acceptability of the location of a site types on noise in the vicinity of airports.
relative to the areas it serves can be measured in terms of
journey time and cost. As a guide to the relative merits of 5.5.17 It is not always feasible to site an airport
individual locations, time contours for the various travel sufficiently far away from population centres to prevent an
modes can be drawn in relation tothe centres of the adverse social reaction. Remotely located airports are both
various areas of demand. For example, by considering unrealistic and costly and defeat the objective of reducing
road transport and the speed lihits on roads connecting over-all door-to-door travel times. It is important,
the areas of demand, time contours in convenient therefore, to obtain or control sufficient land to overcome
increments of, say, 5 to 10 minutes can be plotted for both or reduce the noise problem for both the airport and the
present and future. population. The potential degreeof noise disturbance
needs to be assessedin terms whichwill indicate the
Ground access relationship between the level and duration of the noise
exposure and human reaction.
5.5.13 Fast and convenient access facilities for
passengers and freight are essential for an airportto 5.5.18 In attempting to assess the extent offuture
provide efficient service. Potential
airport sites with noise disturbance at potential sites, the forecast aircraft
movement rate andtiming of airport development, and the should be located so that the cost of development work is
aircraft types and hours during which aircraft operations minimized. Thus, topography, soil and construction
will take place are important. However, long-term materials, availability of services and land values are of
estimates and assessments of noise disturbance can be particular importance.
expected to be somewhat speculative and less reliable than
those for a short term. More detailed information on noise
Topography
evaluation may be found in Annex 16, Volume I -
Aircraft Noise. 5.5.23 Topography is important because the slope of
the terrain, the location and variation of natural features
5.5.19 The noise level produced by aircraft operations such as trees and water courses, andthe existence of
at and aroundthe airport is generally considered a primary structures such as buildings, roads, overhead lines, etc.,
environmental cost associated with the facility. Most noise can affect the requirements for clearing, filling, grading
exposure lies within the land areaimmediately beneath and and drainage. Natural slope and drainage of the land are
adjacent to the aircraftapproachanddeparturepaths. important from a design and construction point of view
Noise levels are generally measured through some because they determine the earthworks and
grading
formulation ofdecibellevel, duration,and number of operations necessary to produce the desired gradients and
occurrences. A large number of noise measuring thus the cost of preparing the site. Terrain which conforms
techniques exist (see Annex 16). Proper site selection and closely to desirable levels and which is well drained may
adjacent land use planning can serve to greatly reduce, if produce significant cost advantages.
not eliminate, the noise problem associated with the
airport. 5.5.24 In areas where tropical diseases are endemic,
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
5.5.21 In the case of a potential site where changes of 5.5.25 Classification of natural soils at potential sites
land use are necessary, there may be obvious social is important from a cost viewpoint. General soil surveys
problems and also legal and economic difficulties. and sampling are necessary to allow the mapping of
Purchase or compulsory acquisition with theattendant various soil types and tolocate extensive areas of rock. The
legal technicalities and delays may be necessary in certain location of water supplies is also relevant because their
instances, but
arrangements with theappropriate availability and the distance over which they have to be
authorities to exert control of development to preserve carried will affect the cost of construction. Expert advice
existing compatible land use may offer less of a future should be sought in these matters.
problem. The Airport Planning Manuol, Part 2, provides
more detail on land use. Services
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
provided by converting future payments to a common time results of the office study andfield investigation. Based on
basis of present worth. Current land values and this review, sites which are unsuitable and which do not
movements in property prices andthe possibility of warrant further examination should be omitted.
housing, industrial,agricultural or other developments
which may increase values require consideration.
5.6.1 Environmental factors should be carefully Consideration of therelative merits of the remaining sites
considered in the development of a new airport or the requires:
expansion of an existing one, Studies of the impact of the
construction andoperation of a new airportorthe - detailed site surveys, including obstacle surveys;
expansion of an existing one upon acceptable levels of air
and water quality, noise levels, ecological processes, and - preparation of outline airport layouts for each site;
demographic development of the area must be conducted
to determine how theairport requirementscan best be - preparation of broad cost estimates covering the
accommodated. totalcapitalandoperating expenditurerequired
including all associated off-airport items such as determine cost-benefit ratios which serve as a guide to the
access roads, communications to population centres, value of the project and the choice of the best site.
planning control of surrounding areas and estimates
of annual percentage changes in land values for the 5.9.3 Two different types of cost-benefit analysis are
probable life of theairport;andtheanticipated necessary - an operationalcost-tenefit analysis and a
phasing of expenditure. social cost-benefit analysis. The final evaluation requires
a n assessment based on the comparison of operational,
social and cost efficiencies:
- when expansion or abandonment of existing sites is
in question, the determinationof the depreciated and
Operational:
current values of any existing installations together
with the value of all otheroff-airport associated
- land availability;
assets including easements, public utilities, noise
- airspace availability;
zones, etc.
- effect of any restrictions on operational
efficiency;
- potential capacity.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
“Airport Planning Manual”,Part 2 - Land-Use and “Airplane Characteristics”, Manuals published by all
Environmental Control,
ICAO Doc 9184, Second airframe manufacturers, detailing aircraft size,
Edition, 1985. dimensions, operations, etc.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
INTRODUCTORY NOTES runways and taxiways are the first to be considered. After
determination of the dimensional criteria, pavement
strength,and airfieldcapacity andconfiguration,other
Before plans can be developed for facilities for the many
elements of the air side of the airport, namely, the apron
functional requirements which anairporthasto meet,
and navigation and traffic control aids arecovered in turn.
concepts for the various operational systems have to be
considered andcompared.Atthe earliest stagesome The forecasts will have indicated the rate of aircraft
concepts for individual systems may be incompatible but movements for which theairport shouldprovide, the
among
those which are compatible
the
optimum nature of the traffic,type of aircraft, and the other factors
combination canonly be determined asthe individual
which have to be taken into accountin planning the layout
plans and the master plan develop in parallel.
and dimensions of the runways, access taxiways, and
aprons. When over-all layoutsfor runway and taxiway
The principal factorsto beconsidered are outlined systems and aprons have been developed, all the possible
herein butsome aspects of the plan mayrequire more primary schemes should be considered in conjunction with
detailed and intensive study with reference to local passenger and cargo buildings and aircraft maintenance
conditionsandotherfactors. Because of their physical areas so as to choose the best schemes and to identify the
characteristics andthe landrequired and all theother areas where compromise may be necessary to integrate the
factors which affect them and limit free choice of layout, planning of the individual facilities.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
3 1 200 rn up to but
not C 24 m up to not
but 6 rn up to but not
including 1 800 m including 36 m including 9 m
the blast pad, which is an area designed to prevent mass of aircraft by using the length of the runway
erosion of surfaces adjacent to the endsof runways plus the length of the stopway to calculate the total
which are subjected to sustained or repeated jet length of pavementavailablein the event ofan
blast. This area is either paved or planted with turf; aborted take-off. A detailed description of stopway
requirements can be found in the Aerodrome Design
Manual, Part 1.
the runway end safety area is an area intended to
reduce
accidents of
aircraft undershooting or
overrunning the runway.Some of the
runway g) A clearway is an unobstructed, unpaved area also
specifications adopted by ICAO are summarized in beyond the end of the runway which is controlled
Table 6-2. For additional information the planner is andmaintained by theairport
authority. By
directed to Annex 14 andthe Aerodrome Design designating an area off the end of the runway as a
Manual, Part 1. clearway an aircraft
operator can increase
the
allowable take-off mass of an aircraft because the
climb rate requirement of the aircraft can be reduced
a stopway is an additionallength of pavement which because the operator is assured that no obstructions
extends beyond the end of the runway. The stopway exist in the clearway.Adetaileddescription of
pavement must have adequate strength to support clearway requirements can be found in the
occasional aircraft loadings. The length of the Aerodrome Design Manual, Part 1. It should be
stopway is not included in the published length of the noted. that the use of clearways and stopways in
runway; however, the airport authority can specify determining allowable take-off mass for an aircraft
that the stopway may be used by aircraft operators is not common operatingprocedure for most aircraft
to determinethe allowabletake-off mass foran operators; however, they can be effective methods
aircraft.Theadditional take-offpavementlength for increasing allowable take-off mass under certain
will permit aircraft-operators toincrease the take-off conditions.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Code number
I 2 3 4
Width of runway
Code letter A 18 m 23 m 30 rn -
Code letter B 18 m 23 m 30 m -
Code letter C 23 m 30 m 30 rn 45 m
Code letter D - - 45 rn 45 m
Code letter E - - - 45 m
Width of runway plus shoulders Where the code letter is D or E, the over-all width of
the runway and its shoulders shall not be less than 60 rn
Runway
maximum longitudinal slope 1.5% 1.5% 1.25 vo 1.25%
maximum effective gradient 2 Qo 2 070 1vo 1Qo
maximum longitudinal slope change 2 070 2 070 1.5% 1.5%
maximum transverse slope 2% where the code letter is A or B; and 1.5% where
the code letter is C , D, or E
Strip
maximum longitudinal slope 2 Yo 2 070 1.75% 1.5%
maximum transverse slope 3 YO 3yo 2.5% 2.5%
6.2.5 Taxiway shouldersareconstructed because jet 6.2.7 The location of exit taxiways depends on themix
blast from taxiing aircraft cause the areas adjacent to the of aircraft, the approach and touchdown speeds, the exit
taxiways toerode.The requirement to buildtaxiway speed, the rate of deceleration, which in turn depends on
shoulders will depend on the frequency of jet operation, the condition of the pavement surface (wet or dry) and the
the condition of the soil, and the cost of maintaining the number of exits. The rapidity and the manner in which air
grassareasadjacenttothe taxiways. More detailed traffic
control
can process arrivals is an extremely
importantfactor in establishing thelocation of exit
discussion of taxiway shoulders can be found in Annex 14
and the Aerodrome Design Manual, Part 2 . taxiways. The location of exit taxiways is aiso influenced
by the locationof the runways relative to the terminal area.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Over-all width of
taxiway and its
Code letter Taxiway width shoulders
~~~~ ~
A 7.5 m -
B 10.5 m -
E 23 m 44m
increases taxiing time, fuel consumption and aircraft wear, normally muchsmallerin size. Inorderto presenta
and extremely long distances may result in dangerous high perspective of the variety of aircraft which make up the
temperature tire conditions. airline fleet, Table 6-4 summarizes their principal charac-
teristics in terms of size, mass, capacity, and necessary
Pavement Strength runway length. The list is by no means complete, but it
does include the principal aircraft in use. In asimilar
6.2.9 The operation of an aircraft cannot be under- manner some typical general aviation aircraft (including
taken with safety, in so farasground handling is those used for corporatepurposes) are shownin Table 6-5.
concerned, without full knowledge of the loading charac- It is important to recognize that such items as operating
teristics of the aircraft and the load bearing properties of mass empty, passenger capacity, and runway length can be
theairport pavement on which it is tooperate.The approximated only in a very general way since there are
evaluation of pavements is a very complex process, with many variables which can affect these items.
several possible analytical approaches; these are described
in the Aerodrome Design Manual, Part 3. 6.2.11 The characteristics shown in Tables 6-4 and 6-5
are important in the following manner for the design of
airports:
Aircraft Characteristics, Performance and
Runway Length a) Mass. Aircraft mass is important for determining the
thickness of runway, taxiway, and apronpavements.
Aircraft characteristics
b) Size. The wingspan and the fuselage length influence
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
6.2.10 A general knowledge of aircraft is essential in the size of parking aprons which in turn influences
planning facilities for their use. Aircraft used in airline theconfiguration of the passenger buildings. Size
operations have passenger capacities ranging from 20 to also dictates width of runways and taxiways as well
over 500. General aviation aircraft, on the other hand, are as distances between these traffic ways.
~ ~ ~~ ~~ ~~~~~
8747-300 Boeing 59.64 69.80 340 100 255 800 4TF 522-624
8747-400 Boeing (62. )3 (69.8)a (386 000)3 N.A. 4TF N.A.
8757-200 Boeing 38.06 46.97 108 800 89 800 2TF 178-217
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
8767-200 Boeing 47.57 47.24 142 900 123 400 2TF 216-290
8767-300 Boeing 47.57 54.94 159 210 136 070 2TF 254-312
DC-8-63/73 Douglas 45.23 57.12 161 025 117 027 4TF 196-259
DC-9-32 Douglas 28.44 36.37 48 988 44 906 2TF 115-127
DC-9-50 Douglas 28.44 40.23 54 431 49 895 2TF 130
F-27-500 Fokker 29.00 25.06 20 41 2 19 051 2TP 52-60
F-28-6000 Fokker 25.07 27.40 33 112 31 300 2TF 65-85
Ilyushin-62 USSR 43.21 53.11 161 937 105 233 4TF 168-186
L-1011 Lockheed 47.35 53.75 195 045 162 386 3TF 256-330
M D 81 Douglas 32.87 45.06 63 503 58 060 2T F 115-172
MD 82 Douglas 32.87 45.06 67 812 58 967 2TF 115-172
MD 83 Douglas 32.87 45.06 72 575 63 276 2TF 155-172
Optional
PiperPA-28R-201Cherokee
Arrow 111 10.67 7.62 1 247.00 4 1P 488
Piper Twin Comanche
7.67 C 10.97 1 632.93 6 2P 570
Piper PA-31T2 12.40 11.18 4 297.00 a 2TP 896
Piper PA-42 14.53 23 13 5 080.00 9284 11 2TP
Piper T 1040 12.52 11.18 4 082.00 11 2TP a08
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
c) Capacity. The passenger capacity has an important main engine. A fan can be thought of as a small-diameter
bearingon facilities within andadjacent to the propeller driven by the turbine of the mainengine. Nearly
passenger building. all airline transport aircraft arenow powered by turbofan
engines for the reason just cited.
6.2.12 An examination of Tables 6-4 and 6-5 reveals 2) environment at the airport;
the following. Maximum take-off mass of principal airline
aircraft varies from 33 0oO to 351 OOO kg. For small 3) those items which establish the operating take-off
general aviation aircraft the range in mass is from 900 to and landing gross mass for each aircraft type.
3 600 kg, while corporateaircraftvaryfrom 6 800 to
25 800 kg. The maximum number of passengers carried by
airline aircraft varies from 20 to over 500. On the other 6.2.15 Certain conditions at the airport also influence
hand, smallgeneral aviationaircraft seat from 2 to runway length. The more important of these conditions
6 people, andcorporateaircraftfrom less than 10 to are:
nearly 30 persons depending on the configuration of the
interior. Runway lengths for typical airline aircraft vary a) Temperature. The higher the temperature,
the
from 2 100 to 3 600 m, but it is important to note that it longer therunway requiredbecause high temperatures
is not valid to assumethatthe larger the massof an reflect lower air densities,resulting in lower outputof
aircraft, the longer the runway length required. For large thrust. For a more detaileddiscussion of temperature
aircraft, especially, thetrip length has an influence on effect on aircraftperformanceand
definition of
take-offmass andalsotherequiredrunway length. “aerodrome reference temperature” refer to Annex 14 and
Therefore in the analysis of runway length requirements, the Aerodrome Design Manual, Part 1.
an estimate oftrip length is very important.Runway
lengths for small general aviation aircraft seldom exceed b) Surface wind. Thegreaterthe headwind down a
600 m, while for corporate aircraftthey are about 1 500 m. runway the shorter the length, and conversely, a tailwind
increases the length ofrunwayrequired.Forairport
planning purposes, it is desirable to use no wind, particu-
6.2.13 In Tables 6-4 and 6-5, aircraft are referred to larly if only light winds occur at the airport site.
according to the type of propulsion and thrust-generating
medium. The term
“piston engine”
applies to all c) Runway slope. An uphill gradient requires more
propeller-driven aircraft powered by gasoline-fed runway length than a level or downhill gradient;the
reciprocating engines. Most small general aviation aircraft specific amount depends on the elevation of the airport
are powered by piston engines. The term “turboprop” andthetemperature. Reference should be made to the
refers to propeller-driven aircraft powered by turbine average correctionfactors in Annex 14. Forairport
engines. A few twin-engine general aviation aircraft and a planningpurposesonly, Annex 14 uses an“average
few of the earlier airlineaircraftare powered in this longitudinal slope” defined as the difference in elevation
manner.Theterm“turbojet”has reference to those between the highest and lowest points on the actual runway
aircraft which are not dependent on propellers for thrust, centre line divided by the length of the runway.
but which obtain the thrust directly from a turbine engine.
The early jet airline aircraft, particularly the Comet,B707 d) Airport altitude. All other things being equal, the
and DC-8, were powered by turbojet engines, but these higher the altitude of the airport, the longer the runway
were discarded in favour of turbofan engines principally required. For planning purposes an increase from sea level
because the latter are far moreeconomical. When a fan is of 7 per cent/300 m of altitude will suffice for most airport
added in the frontor rear of a turbojet engine, it is referred sites except those that experience very hot temperatures or
to as a “turbofan”. Most fans are installed in front of the are located at high altitudes.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
How much these conditions affect runway length can only Step The payload is 16 330 kg.
be approximated; however, “orders of magnitude” can be
beneficial for planning and are therefore presented in that Step The fuel reserve is 5 443 kg.
context.
Step The landing mass is 61 235 + 16 330 + 5 443 =
Run way length determination 83 008 kg. It does not exceed the maximum
structural landing mass which is 97 522 kg.
6.2.16 Compute runway length at airport “A” based
upon an aircraft flight from airport “A” to airport “B” Step 5 Fuel required to climb to cruise altitude is equal to
as follows: 4 5 6 0 kg; to descend to the airport, 545 kg; and to
cruise at an altitude of 9 450 m at a speedof
1) obtain operating mass empty of aircraft; Mach 0.82, 34 020 kg. Total fuel burnout is then
equal to 4 560 + 34 020 + 545 = 39 125 kg.
2) determine payload;
Step 6 The take-off mass is equal to 83 008 + 39 125 =
3) determine fuel reserve; 122 133 kg. This does not exceed the maximum
structural take-off mass, which is 151 3 17 kg.
4) add items I ) , 2) and 3). This is the landing mass of
the aircraft atcity B. This mass should not exceed the Step The airport conditions are listed in the statement
maximum structural landing mass of the aircraft; of the problem.
5 ) compute fuel requirements for climb, cruise, and Step Using the approved flight manual for the
descent; Boeing 707-320B (advanced), check if the climb-
limited mass is less than 122 133 kg. In this case
6) the take-off mass of theaircraft is obtained by it is not and one can determine the runway length
adding item 5) to item 4). This should not exceed the using the airport conditions cited in the problem.
maximum structural take-off mass of the aircraft; The required runway length is 2 135 m.
8) with the data outlined in items 6 ) and 7), and by 6.3.1 The Federal Aviation Administration (FAA) has
using the approved flight manual for the specific a procedure to compute airport capacity and aircraft delay
aircraft, determine the runway length. for airport planning and design. It defines “capacity” as
the
throughput
rate, i.e. the maximum number of
These steps can be illustrated by an example using a Boeing operations that can take place in an hour, and “delay” as
707-320B for a 3 OOO nautical mile trip between airport the difference in time between a constrained and an
“A” andairport “B”, under the following assumed unconstrained aircraftoperation. These definitions take
conditions: into account that delays occur because of simultaneous
demands on the facility. The acceptable level of delay will
Cruise altitude 9 450 m vary from airport to airport.
En-route, climb, and descent standard conditions
Headwind in cruise 37 km/h (20 kt)
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Background
Speed 0.82 Mach
Airport altitude sea level 6.3.2 Thethroughput method for calculating airport
Airport surface wind zero capacity and average delay per aircraft is derived from
Runway slope level computer models usedby the FAA to analyse airport
capacity and reduce aircraft delay. Calculations of hourly d) when demand reaches or is expected to reach 75 per
capacity are needed to determine average delay. Since cent or more of the capacity of the existing parallel
airportandairport component hourly capacities vary runway configuration within five years, ashort
throughouttheday due to variations in runway use, parallel runway can be extended to increase capacity;
aircraft mix, ATC rules, etc., a number of calculations
may be needed. Figure 6-1 provides the ranges of hourly e) although intersecting or open V rulwaysare not
capacity and annual service volume for different runway generally recommended for the purposeof increasing
use configurations. The values vary within each range capacity, consideration of terrain, noise, obstacles
depending ontheaircraft mix, percentage of arrivals, may make these layouts more practical. It should be
visibility, etc. for each runway use configuration.For shown thattheconfiguration chosen will provide
details refer to FAA Advisory Circular “Airport Capacity sufficient runway capacity t o accommodate demand
and Delay”. into the foreseeable future or will provide a
substantial increase in runway capacity at a much
reduced cost compared to a parallel runway. A
Runway Capacity comparisonof capacities with a parallel runway
configuration should be made.
6.3.3 The annual capacity of a single runway airport
configuration could exceed 195 OOO operations with
suitable taxiway, apron and air traffic control facilities. Taxiway Capacity
An airport runway system that is primarily used by locally
6.3.5 The addition of taxiway facilities to the runway
based aircraft will probably not attain an annual demand
of more that 150 OOO operations if its based aircraft total configuration increases airport operational efficiency by
is less than 200. However, the development of an allowing the runway to realize its maximum capacity
additional runway based on capacity requirements may be potential.
considered for airports with a current demand level below a) A stub taxiway to the apron and turnaroundpads or
150 OOO, if traffic is increasing. Besides the capacity turnaroundsat
both ends of the runway are
requirements, importance of the airport to thecommunity recommended for the minimum taxiway system.
itserves (e.g. airport for State capital) may warrant an
additional runway to avoid total airport closure in case of b) Parallel taxiways may be justified when any one of
accident, runway repair, snow removal, partial unlawful the following criteria is forecast to be reached within
seizure of an airport, etc. five years. (The normal peak hour referred to below
is the peak hour of the week averaged for one year;
6.3.4 The following criteria may be used to determine however, as applied to instrument approaches it is
the need for an additional runway to increase capacity: the average of the highest 10 per cent of the hours
during which time instrument approaches are being
a parallel runway may be planned when the demand made):
is forecast to reach the existing runway capacity 1) there arefour instrumentapproaches (those
during the ensuing five years; which are countedtowardannual instrument
approaches) during the normal peak hour;
a short parallel runway may be justified at an airport
forecast to have, within five years, a demand greater 2) the annual operations total 50 OOO;
than 60 per cent of existing runway capacity. Taxiing
distances between the new runway and the terminal 3) the normal peak hour itinerant operations total
area must be favourable. Otherwise the extra long 20; or
taxiing distances will result in reduced demand for
4) the hourly total (itinerant plus local) operations
the new runway. A “short” parallel runway should
are:
be long enough and wide enough to provide
sufficient capacity so thatadditional construction - 30 operations per normal peak hour - for
for capacity purposes due to changes in airport runways serving more than 90 per cent small
population would not be required within five years; aircraft and where there are less than 20 per
cent touchandgooperations; 40 operations
a short parallel runway to serve small aircraft may be per normal peak hour where there are more
planned for anairport having 75 000 operations than 20 per cent touch and go operations(each
consisting of 30 OOO or more transport type aircraft; touch and go is considered two operations).
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Hourly capacity
ops/ h Annual service
volume
Number Runway use configuration VFR IFR ops/h
;i
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
- 30 operations per normal peak hour - for applied in determining the need for holding bays and
runways serving 60 percent to 90 per cent by-pass taxiways, once a parallel taxiway has been
small aircraft. justified.
- 20 operations per normal peak hour - for When activity is forecast to reach 30 total operations per
runways serving 40 per cent to 100 per cent normal peak hour, or 20 0oO annual itinerant operations
large aircraft. or 75 OOO totaloperations,a holding bay should be
planned, giving due consideration to other factors. These
Parallel taxiways provide safety benefits in addition factors are:
to increased efficiency. These safety benefits cannot
be easilyassessed. However, the criteria given are 1) Mixture of types of aircraft such as air carrier or
based on having stage development following the military aircraft operations simultaneously with
construction of taxiway turnarounds. general aviation aircraft.
If the construction cost of a parallel taxiway does not 2) The airport layout (i.e. from the standpoint of
exceed the cost of turnarounds by more than one “as built” conditions).
third, it should be the preferred development. A
partial parallel taxiway, or equivalent (as can be 3) Location of navigation aids (i.e. the critical area
obtained by intersecting runways), provides satis- surrounding a NAVAID - existing or proposed
factory efficiency as well as safety to aircraft - in relation to possible holding bay locations).
operations. In many instances, adequate capacity
can be attained by the construction of apartial There is insufficient economic justification for construc-
parallel taxiway. This solution can prove especially tion of a holding bay to accommodate fewer than two
desirable where construction costs are high. A partial aircraft. Also provision for more than four aircraft is not
parallel is generally economically justified at activity usually justified. If the traffic density is such that more
levels equal to 60 per cent of the values given for full than four holding positions appear necessary, investigation
parallel. If a full or partial taxiway is strongly will generally disclose that another solutionto the problem
preferred over taxiway turnarounds may it be is in order.
pIanned if current operations are 20 OOO per year, if
there are no turnarounds existing, and if cost is less
than half the average costs. 6.4. TYPICAL PHASED DEVELOPMENT PLAN
c) Exit taxiways beyond a basic layout of one at the Figure 6-2 shows a typical phased development plan for an
runway ends and one in between are usually justified airport thatmay be obtained by the use of the concepts and
if demand is forecast to exceed 40 per cent of the methodology presented in this section. A cross reference,
runway capacity providing taxiway costs are locating the type of development with the applicable
average, and at 75 per cent of capacity if costs are criteria, is also presented on this diagram.
high. A sufficient number of exits should be planned
so that additional exits would not be required within References
five years following the completion of construction.
“Planning
and Design of Airports”,
Third
Edition,
d) Holding bays and by-pass taxiways enhance airport Robert Horonjeffand Francis X. McKelvey, 1983 -
capacity. These facilities seldom, if ever, constitute McGraw-Hill Book Company.
restraints on the attainment of full airport capacity
within the existing airport property since land areas “Airport capacity and delay”, U.S. Federal Aviation
are normally always available to permit their con- Administration, AC 150/5060-5, 1983.
struction. However, the need for these facilities
should be determined sufficiently in advance to Annex 14 - Aerodromes.
prevent delays that would occur due to a lack of
these facilities. The following criteria should be Aerodrome Design Manual (Doc 9157).
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
7.1 ABOUT THIS CHAPTER e) minimize adverse effects such as engine blast, noise,
air pollution, etc. OR the apron and the surrounding
An apron is defined asan airsidearea onanairport environment.
intended to accommodate aircraft for purposes of loading
or unloading passengers, mail or cargo, fuelling, parking, Apron Sizing
or maintenance. Aprons canbe classified according to
their main purpose and function. This chapter describes 7.2.2 The planning of a particular apron depends on
characteristics of various types of apronsand aspects its purpose and function.However, basic parameters to be
related to theirplanning. Not all of theapron types considered are as follows:
presented here are required for every airport but the need
for them and their size should be estimated based on the a) number of aircraft stands required at present and in
type and volume of forecast traffic at the airport.Besides the future;
aircraftstands,the associated apron taxiways, apron
service roads and parking for ground service equipment b) aircraft mix, both present and future;
shouldall be included as a part of anapron system.
Further guidance related to apronsis given in 9.8 and 10.6, c) aircraft dimensions and manoeuvring capabilities*;
since apronsare only a part of the over-all terminal
complex. Other useful references are listed at the end of d)aircraft parking configuration including shape of
this chapter. terminal andthesurroundingarea available for
development*;
I-59
ANGLED NOSE-IN
BUILDING LINE
ANGLED NOSE-OUT
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Disadvantages
Requires
tractor
for Requires
larger
apron
Requires
larger
apron
Requires
largest
apron
push-out operation area
than nose-in
area
than
angled
nose-
area
given
for
aircraft
configuration in configuration
Push-out operation Relatively severe engine Breakaway engine blast Limits aircraft
requires time and skilled blast and noise is and noise are directed servicing activity at
operator directed at terminal at terminal neighbouring stand
when aircraft taxi in
and out
the short, medium and long term and an orderlytimely and task and should be done by studying world trends and
developmentscheme prepared. -Staged expansion of the consultingairport user airlines toarriveatthe best
apronshouldbeplanned when appropriatebutsuch estimate.
requirements mayvary. For example, in planning medium-
term requirements,it may happen that despite increased
an
volume of passengers the estimated number of required 7.3.4 Thegateoccupancytime is thetimeforan
aircraftstandsmayremainthesameduetotheintro- aircraft to manoeuvrein and out of an aircraft stand, load
duction of larger aircraft. In such a case, it may be wise to and
unload passengers,baggage andcargo,
refuel,
construct a larger apron during the initial stage. performcabin cleaning, and receive various routine
services and minor repairs. The gateoccupancy time varies
7.3.2 The peak hour passenger aircraft movements by depending on aircraft size, flight type such as domestic
aircraft typemay beestimated by thetwoprocedures orinternational,andstationtypesuchasoriginating/
shown in Figure 7-2. The ratios of aircraft peak day/hour terminating,through,ortransferkransitstations (see
movements should be derived from past records as well as 9.2.21 to 9.2.31). One typical example of the gate
by takingintoconsiderationfactorsparticular to local occupancy time is shown in Table 7-2.
-
a)
Peak hour
Forecast annual Peakday
passenger aircraft
passenger aircraft t passenger aircraft
movement movement
aircraft type
(--)Aircraft peak
day ratio
Aircraft peak
hour ratio aircraft mix
lour
lger aircraft
aircraft type
7.3.5 The next step is to categorize present and future where S = required number of aircraft stands
aircraft serving attheairportinto groups according to
their required stand size.Since the purpose of categor- Ti = gate occupancy time in minutes of
ization is to enable common use of a particular stand by aircraft group i
different aircraft types, consideration should also be given
to the common use of the fixed apron facilities such as Ni = number of arriving aircraft group i
passenger loading bridges, hydrant systems, etc. An during peak hour
example of categorization is given in Table 7-3.
a = number of extra aircraft stands as spare.
7.3.6 The required number of aircraft stands at a 7.3.7 The number of arriving aircraft can be obtained
passenger terminal maybe estimated by the following either by simply dividing the previously calculated
formula: passenger aircraft movement by two or by applying a
heavy direction factor particular to the airport, which may
be in the order of 0.6 to 0.7. This value of 0.6 to 0.7 means
that arriving aircraft represent 60 to 70 per cent of the total
peak hour arriving and departing aircraft movements.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Table 7-2. Typical gate occupancy time (in minutes)
~~ ~~
Domestic international
Aircraft Through flight ' Turnaroundflight Turnaround flight
B-737, DC-9, 25 45 -
F-28
B-707, B-757 45 50 60
B-747 - 60 120-180
~~
Group Aircraft
S F-28, B-737
When the airport is planned to have different passenger Pier (finger) concept. As seen in Figure 7-3, there are
terminals dedicated exclusively for domestic, national flag several variations of this concept, according to the
carrierinternationaland foreign carriers, the above- shape of the pier. Aircraft can be parked atgate
mentioned formula should be applied individually for each positions on both sides of the piers, either angled,
case. parallel or perpendicular (nose-in). Where there is
only a single pier, most advantages of the linear
concept would apply for air side activities except for
a limited incremental expansion capability. When
Apron/Terminal Relationships there are two or more piers, care must be taken to
provide proper space between them. If each pier
7.3.8 As previously mentioned, apronarrangements serves a large number of gates, it may be necessary
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
are directly interrelated with the passenger terminal to provide double taxiways between piers to avoid
concept. Details of various passenger terminal concepts are conflicts between aircraft entering and leaving the
described in 9.2.37. This section presents various concepts gate positions.
pictorially in Figure 7-3 and briefly describes the character-
istics of each concept from the viewpoint of the apron.
Satellite concept. The satellite concept consists of a
satellite unit, surrounded by aircraft gate positions,
Simpre concept. To be applied at low traffic volume separated from the terminal. Thepassenger access to
airport. Aircraft are normally parked either angled a satellite fromthe terminal is normally via an
nose-in or nose-out for self taxi-in or taxi-out. underground or elevated corridor to best utilize the
Consideration should be given to providing adequate apron space, but it could be on the surface.
clearance between apron edge and terminal frontage Depending on the shape of the satellite, the aircraft
facing air side to reduce the adverse effects of jet are parked in radial, parallel or some other configur-
engine blast. Where this is not done, jet engine blast ation around the satellite. When aircraft are parked
fences should be provided. Apron expansion can be radially, which used to be common, push-back
done incrementally in accordance with demands, operation is easy but requires larger apron space. If
causing little disruption of airport operation. a wedge-shaped aircraft parking configuration is
adopted, it not only requires unfavourablesharp
Linear concept. This concept may be regarded as one turns taxiing to some of the gate positions but also
creates traffic congestion of ground service
of the advanced stages of a simple concept. Aircraft
equipment around the satellite.
can be parked in an angled or parallel parking
configuration. However, nose-idpush-out parking
configuration with minimum clearance between Transporter concept. This concept may be referred
apron edge and terminal becomes more common in to as an open or remote apron concept. As aprons
this concept for more efficient utilization of apron may be ideally located foraircraft close tothe
space and handling of aircraft and passengers. Nose- runway and remote from other structures, it would
in parking affords relatively easy and simple provide advantagesforaircraft handling such as
manoeuvring for aircraft taxiing in to gate position. shorter over-all taxiing distance, simple self-
Push-out operations cause little disruption of apron manoeuvring, ample flexibility and expansibility of
activities in neighbouring gate positions. However, aprons,etc. However, as it requires transporting
towing tractors and skilled operators are required. passengers, baggage and cargo for relatively longer
At busy traffic airports, it may become necessary to distances by transporters (mobile lounges/buses) and
provide double apron taxiways to lessen the blocking carts to and from the terminal, it can create traffic
of the taxiway by push-out operations. The corridor congestion problems on the air side.
between the apron edge and terminal frontage can be
used for circulation of apron traffic and the area
around the nose of the parked aircraft can be used Hybrid concept. The hybrid concept means the
for ground service equipment parking slots. When combining of more than one of the above-mentioned
apron depth is planned from theoutset to cater to the concepts. It is fairly common to combine the
longest fuselage length, the linear concept has as transporter concept with one of the other concepts to
muchflexibility and expansibility asthe simple cater to peak traffic.Aircraftstands located at
concept and almost as much as the open apron remote areas from the terminal are often referred to
concept. as remote aprons or remote stands.
_.
a) Simple concept
-- -c31-----
1 r1 -
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
II
r+I
I
1 - 1 I
I
I
I
I-----
I
- -I
1
I
7.4 CARGO TERMINALAPRON 7.5.3 As maintenance may be carried out during the
night, it is preferable to locate the maintenance terminal
7.4.1 Atairports where theamountofair cargo is area close to the parking apron (see 7.6) located adjacent
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
relatively small and mostly carried by passenger aircraft, to thepassenger terminal apron. Care shouldbe exercised,
there is no need toconstruct acargoterminal apron however, to reserve future expansion areas for both
exclusively for freight aircraft,andthecargo terminal passenger and maintenance terminals
including their
building is best located close to the passenger terminal aprons.It is generally recommended thatmaintenance
apron to minimize the travel distance, with due consider- terminal apronsbe located at a fairly remote area from the
ation given to the future expansion of both areas. passenger apron;
located so that:
Aircraft Guidance
a) satisfactory clearances are available from therunway
and from aircraft using the taxiway; 7.11.1 A proper guidance system on aircraft stands is
necessary for safe manoeuvring of aircraft 03 the stand
b) propeller wash and jet blast are not directed at other and positioning of aircraft. Apron markings are a widely
aircraft; used means to provide guidance; however, some airports
have inset pavement lights in addition to painted guidelines
c) interference with theoperation of approach and to assist pilots in the dark and poor visibility conditions.
landing aids is not caused; and
7.11.2 With theadoption of the nose-in parking
d) aircraft on a bay cannot be subjected to illegal inter- configuration and the use of passenger loading bridges,
ference from a public area. precise positioning of aircraftisimportant. There are
several types of visual docking guidance systems currently
See also the Aerodrome Design Manual, Part 2. inuse but not all of themmeet agreed operational
requirements. Reference should be made to the Aerodrome
Design Manual, Part 4. for further informationon suitable
systems.
7.8 GENERAL AVIATION APRON Aircraft Servicing
When an airport is also intended to serve general aviation 7.11.3 Fixed aircraft servicing installations reduce
aircraft, a general aviation terminal including a separate apron congestion and permit shorter servicingtimes.
apron and other related facilities maybe required. The Possible installations include:
general aviation terminal and its apron, however, should
be located so as to minimize conflict with the scheduled a) hydrant fuelling;
aircraft operations.
b) fixed ground power;
8.1 ABOUT THIS CHAPTER surface conditions. It is therefore prudent to install more
than adequate duct capacity during initial construction.
Planning of airports must include provision for facilities Similarly, if in the near future it is planned t o upgrade a
which will supporttheairtrafficcontrol system, for runway to precision approach CategoryI1 or 111, involving
navigation aids for aircraft approaching the airport and, in-pavement lights, then itmay be found moreeconomical
finally, for control of aircraft and vehicles on the surface and convenient to include ductsfor theselights in the
of the airport. The purpose of this chapter is to describe initial pavement construction.
the requirements for such control aidsas pertain to airport
master planning. Specific information on performance of
equipment and on siting of navigation and control aids,
among others, may be found in Annex IO, Annex 14 and 8.3 RADIO NAVIGATION AIDS
the Aerodrome Design Manual, Part 4.
8.3.1 Most modern airports are likely to have all or
some of the following navigation aids:
I-69
8.3.3 It is very difficult to specify exact sizes for the When planning buildings forradio navigation aids,the
buildings for the sites, because the choices andthe following points should be taken into consideration:
combinations of the navigation aids are quite numerous.
The rapid developments and advances in electronic a) Size. Particularattention should be paid to the
technology and the consequential miniaturization of future needs and possible extension or modification
equipment may offer radically different concepts, so far as of the facilities. In the case of localizers and glide
the installation of navigation aids atthe airport of paths, provision of space for dualinstallations
tomorrow is concerned. Up-to-date information should be should be considered, from the pointof view of both
obtained from experts in each field to allocate appropriate the future construction at the airport and the up-
areas for the required facilities. However, some general grading of performance to accommodate faster and
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
guidance is provided in the following paragraphs. larger aircraft. Additional space should be allocated
for
standby powerplants or air conditioning
8.3.4 Parts of the instrument landing system (i.e. equipment where called for by virtue of equipment
markersand non-directional beacons) arenot usually design or local climatic conditions.
located ontheairport; however, thecontrolfor all
facilities and power for the middle and inner markers are
usually provided fromtheairport.The required power b) Power supply. At those sites where an independent
self-contained unit power station cannot
be
supply can be provided more economically from the
provided, the power supply transformers and
airport than by separate individual power sources at each
of the facilities, with the exception of outer markers and associated accessories have to be instalIed inside the
non-directional beacons. building. Appropriate isolation and ventilation of
theradio equipment isnecessary to dissipate the
additional heat generated by the power equipment.
8.3.5 The number of instrument landing systems at an
Where standby plants are employed, diesel engine
airport would depend on the precision approach runways
noise is also a factor which should be considered.
required. Usually the ILS/MLS is planned to serve the
prevailing bad weather wind direction, but since the fair
weather use of ILS/MLS is becoming more common for c) Drainage. Provision should be made to drain the site
safer operation, especially for large aircraft, some runways adequately. Poor drainage, particularly at the glide
are planned to have instrument landing systems at both path sites, can cause appreciable changes to the
ends. Since the integrity of theradio signals in space signal in space and accumulated water in the vicinity
depends on the reflecting properties of the terrain of the building could even cause equipment
surrounding the antennas, minimal roughness and slope shutdown. Drainage ditches in the vicinityof the
with adequate drainage and soil stability highly is glide path antenna must be of such dimension that
desirable. The roughness of localizer course and glide path they do not adversely affect the signals in space.
depends onthe number of unwanted signal reflections
received by the aircraft. The number and magnitude of
unwanted reflections depend onthenumber, size and d) Access roads. Restoration of a facility to normal
material of objects (e.g. buildings, hangars, vehicles, etc.) operation depends a great deal on fast and easy
and distance of the objects illuminated by the antennas. At access to the building. For those facilities which are
those sites where the number of significant objects is located on the airport, access via the runways could
unavoidably large, the signal quality can be improved with caus.e considerable delays if the traffic is heavy and
the help of directional antennas, which are usually more separate access roads should therefore be considered.
costly and much larger than the standardtype of antennas. If proper planning precedes the choice of the
building sites, the cost of construction and
8.3.6 Most of the site grading work, construction of maintenance of the access road could be reduced
access roads and provision of ducts under the runways for considerably.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
flight information centre. It is importantthat these
requirements be determined at an early stage in consul- Area Control Centre/Flight Information Centre
tation with the appropriate air traffic services authorities
and that theplanning of buildings on the airport takethese 8.6.4 The areacontrolcentre or flight information
requirements fully into account. It is also important that centre, where required, should preferably be located
flexibility in the arrangements of air traffic services units conveniently close to the airport control tower room and
andadequate expansion possibilities be reflected in the the approach control office. The centre should be large
planning. enough to accommodate control desks, associated devices
and operating personnel, and provision should be made
for equipment rooms, office space and rest facilities near
by. Requirements for special lighting, noise protection, air
conditioning and special accommodation of sensitive
Airport Control Tower equipment such as radar and computer equipment should
be taken into account.
8.6.2 The effective provision of airport control service
requires a clear and unobstructed view of the entire
movement area of anairportand of air traffic in the Air Traffic Services Reporting Office
vicinity of the airport. The airport control tower should
therefore be so located and be of such a height that aprons, 8.6.5 If required to be established as a separate unit,
taxiways, runways and the airspace surrounding the rather than as a part of another air traffic services unit or
airport, particularly approachanddepartureareas,are aeronautical
information service unit,the
air
traffic
clearly visible from the controlroomandthatfuture services reporting office should be located in close
proximity to other briefing andreportingoffices, e.g. by radio, remote transmitter and receiver buildings are, in
meteorological briefing office, aeronauticalinformation most cases, required. In siting such buildings, several
services unit, etc. The office should be easily accessible to factors should be taken into consideration, such as radio
flight crews of departing and arriving aircraftand toflight interference, adequate and appropriatespace for antennas,
operations officers of airlines. It should be sufficiently accessibility, reasonable distance fiom the central instal-
large to accommodate necessary staff and equipment and lation in thecommunicationscentre (usually accommo-
to enable flight crews and other personnel to prepare flight dated in o r near the passenger building), availability and
plans and reports. Additionalinformation relating to reliability of power sources, etc.
briefing offices may be found in the Aeronautical
Information Services Manual. 8.9.2 The size of the transmitter and receiver buildings
should be adequate to accommodate the ultimate point-to-
point
(and possibly aeromobile)radio
equipment,
8.7 SEARCH AND RESCUE SERVICES workshop,stores,offices, emergency power plant,and
other facilities required for efficient operation. In many
At some airports there may be a need to accommodate a cases, it may not be possible to site the transmitter and
rescue co-ordination centrecollocated with or conveniently receiver buildings within the airport boundaries, but they
close to the area control or flight information centre or a should nevertheless be considered as part of the airport
rescue sub-centre collocated with or conveniently close to installation as far as control and operational aspects are
an appropriate air traffic services unit. For information on concerned.
the accommodation of rescue co-ordination centres and
rescue sub-centres see Part I of the Search and Rescue Aeronautical Mobile Services
Manual.
8.9.3 Air-ground communications for airporttraffic
control, surface movement control and approach control
8.8 APRONMANAGEMENTSERVICE are operated by the corresponding air traffic services, and
the associated terminal equipment should be suitablysited
The number and complexity of aircraft and vehicle in relation to these services. If air-ground communications
movements on an apron may create a need for an apron for en-route air traffic control or other services are to be
management service and thus separate accommodation for provided,the associated terminalequipmentshould be
the staff, with clear sight to all parts of the apron in their suitably sited in relation to the corresponding area control
charge. Requirements for special lighting, noise protec- centre/flightinformationcentre or other services con-
tion,airconditioningandcommunications should be cerned, Therelative inflexibility of these installations, once
taken into account. established, is comparable to thatof the aeronautical fixed
services, and similar planning provisions should be made.
The radio transmitters and receivers associated with the
8.9 COMMUNICATIONS aeronautical mobile service are frequently located at the
remote transmitter andreceiver buildings mentioned under
Aeronautical Fixed Services the aeronautical fixed services heading.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
INTRODUCTORY NOTES
1-73
9.1 ABOUT THIS CHAPTER certain circumstances, particular functions such as aircraft
maintenance may be situated at locations remote from the
This
chapter deals with planning for facilities to main passenger building.
accommodate those activities associated with the transfer
of passengers and their baggage from the point of inter- 9.2.5 In keeping with the objectives of airport master
change between ground transportation and the passenger planning, the development of passengerbuildingplans
building to the point of connexion with the aircraft, and should be limited to conceptual studies and
drawings. Such
with the transfer of connecting and in-transit passengers drawings should not be so detailed as to preclude adjust-
and their baggage between flights. Planning principles, ments which evolve later in the detailed planning phase.
factors affecting the type andscale, and specific planning Such changes frequently occur as an airport development
details of various passenger building functions are project moves beyond the master planning phase to final
presented in this chapter. design and construction.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
passengers’ physical and psychofogica1 characteristics to
9.2.2 Aircraft operations will be less costly and more make the passenger area a most sensitive part of thewhole
efficient if the passenger building is as close as possible t o air transport system. In considering the planning of these
the runways. This reduces taxiing distances, and hence fuel facilities any preconceptions about the result should be
consumption, and helps to avoid congestion by reducing eliminated, except that the facilities should provide
the time spentby aircraft in ground movement. Care must comfortable, convenient and speedymovement of pass-
be exercised, however, toensurethat expansibility and engers and baggage between air and ground transport at
flexibility are notcompromised. Therefore, thelocation of the lowest effective cost and should be able to accom-
passenger facilities is inseparablyassociated with the modate expanding traffic without extensive modification.
planning of the over-all runwaylayout andthetotal
airport plan. Characteristics of passenger areas
9.2.3 The type and size of the passenger building and 9.2.8 Well-designed passenger buildings are usually
the various components within the building will evolve the result of close co-operation between all &hemembers of
from land-use requirements activity forecasts (Chapter 3, the planning team concerned, both those whose task it is
3.2 to 3.4), and site evaluations (Chapter 5 , 5.2). to lay downthe requirements and those,particularly
architects and engineers, who have totranslatethe
9.2.4 For many airportsto which this manual is requirements into detailed designs. Although each group
directed, passenger building facilities will be contiguous, hasits own primaryresponsibility, it can also help the
with one generallocation on theairport. However, in other in many ways. In what follows there is no attempt to
t-74
lay down principles of design but only to set out some which canaccommodateaircraft parking positions for
planning principles that are likely to influence design. high runway capacities and still maintain passenger
walking distances within reasonable limits. A walking
a) For general layout, passengers should be thought of distance of about 300 m from the centre of the air side of
as forming a homogeneous flow, whether constant the passenger building to thefarthestaircraft parking
or intermittent. position has been generally accepted as the reasonable
limit. However, even this can result in passengers having to
b) The majority of passengers are content to form part walk long distances tomake connexions between one
of the main flow and require clear indications of aircraft, althoughjudicious allocation of stands can reduce
what they are expected to do andthe flow routes they such cases to a minimum. The size of the modular
should follow. passenger unit is very important and should be the best
compromise responding to the physical limitations of
Passengers have individual needs, preferences and passengers and the economics of construction and oper-
(sometimes) disabilities. Some of these requirements ation of the passenger building andapron.Further
involve the airport in extra expense (e.g. facilities for discussion on factors affecting passenger terminal size may
invalids, disabled and elderly persons); otherscan be found in 9.2.32 through 9.2.39.
bring in revenue (e.g. concessions).
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
A system thatattracts passengers to theroutes Layout of passenger buildings
required by the flow pattern will often give better
results than one that appears to offer no
alternative, 9.2.11 Passenger buildings should be associated with
particularly if it also gives some freedom for carparks and aprons, etc., ofthe necessary capacity.
individual requirements. When the passenger movement rate exceeds the capacity of
the optimum size building, additional buildings should be
provided, each complete with its own associated full
complement of facilities. Thelayout of these modular
Separation of functions
passenger units within the passenger building plan should
9.2.9 The key to achieving the planning objectives include the necessary apron space, car parking and road
is simplicity. In the context of passenger planning it circulation space in the most compact arrangement
means simple, obvious flow routes. Complex flow routes to minimize transfer distances between the passenger
usually arise from complex plans and buildings. Complex buildings, and between the associated facilities within each
buildings are usually costly, inflexible and not readily modular unit.
expansible as a logical extension of the plan and operating
system. The facilities may still be costly if so desired, but 9.2.12 These units should be arranged in the simplest
this will not be an unavoidable consequence of the plan manner possible to provide an easily comprehensible
and operating concept. Separation of functions is the environment to facilitate free flow of vehicles and people,
principal aid to achievement of simplicity. If other and to provide a flexible and expansible layout capable of
facilities, such as multi-storey office blocks, car parks, adaptation to
future possible requirements. Transfer
control towers, etc., areincorporated withpassenger routes will be required for passengers and baggage on the
buildings, not only does the flow plan tend to be distorted air side, within customs bond, and land side. The nature of
but flexibility is seriously compromised by the presence of these transport systems should be considered in conjunc-
these facilities, and also by thestructuralfeatures they tion with town centre/airport public transport systems to
impose on the building. Figure 9-1 illustrates each of which all the passenger buildings should be conveniently
the important functions of a passenger building and gives linked.
anapproximation of various passenger and baggage
processing interrelationships. Planning requirements for FIOW principles
each of these components are described, in turn, in
subsequent sections of this chapter. 9.2.13 The following flow principles should be
considered, to the extent itis practical, and evaluated
Size of passenger buildings against local circumstances. Particular regard should be
paid to the separation of functions. The passenger flow
9.2.10 For passenger convenience, a large area in the plan should be the first to be considered. Baggage move-
passenger building should be broken down into units or ment is of equal importance since it should be integrated
modules, since it is difficult to construct a single building with the passenger flow but, because baggage is inanimate,
it is easier to make the baggage flow compatible with the consists of the time taken to realize that a control has
best passenger flow. In practice the flow plans should be to be passed, to understand its nature and to find the
tested against one another at all stages. necessary documents. This time will be increased for
some passengers by lack of understanding of foreign
9.2.14 Flow principles to consider with respect to languages, illiteracy, or confusion. These effects can
passengers include: be reduced minimizing controls and concentrating
them at the fewest number of points. This can also
a) Routes should be short, direct and self-evident. They improve utilization of staff by permitting great
should not, as far as is practicable, conflict with not flexibility.
cross the flow routes of other passenger, baggage or
vehicular traffic. h) Passengers should not have to pass through the same
type of control more than once. Thus, if procedures
b) Changes in level of pedestrian routes should be or controls areestablished in more than oneplace the
avoided as far as is practicable. flow routes should be planned to permit passengers
to bypass all subsequent controls of the same type.
c) Passengers should be able to proceed through a
building without the need to rely on guidance or
i)
The last control which passenger should pass
instruction from staff. Theflow system should be for
through is security. Any controls established at an
‘‘trickle flow” rather than controlled movement in
airport for screening of passengers and their hand
groups.
baggage should be sufficiently remotefromthe
boarding gate as to provide maximum restriction of
d) In heavy traffic conditions, mass flows can only be
unauthorized access to aircraft. Moreover, provision
achieved by the use of trunkroutes.Particular
should be made for a “sterile” buffer area between
categories of passengers should be diverted from the
the security controlpoint and theaircraft. See
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
main flow route to pass through specific controls
Doc 8973 and Annex 9 for further information.
only at the last point on the main flow route where
the character of the traffic changes.
j) Flow routes should be planned to give visual
e) Departing passengers should have an opportunity to continuity tothe maximum possible extent. As a
check their baggage at the earliest possible point. minimum it is essential that there should be visual
continuityfromonefunctional stage of the flow
f) Each flow route should, as far as is practicable, be route to the next, e.g. from baggage claim to customs
in one direction only. Where a reverse flow has to be or from check-in to immigration. Such continuity
provided it should bevia a self-contained and assists passengers’ understanding of the flow system
separate route. Flow routes and milling spaces (areas and draws them on in a steady flow through each
of random movement) are necessarily complemen- successive stage. A visual blockage, such as exists
tary to each otherbutareseparatefunctions. where each function or authority is contained in a
Therefore, milling spaces should be adjacent to but separate room, is confusing and creates the need for
not part of the flow routes. signs, broadcast instructions or staff supervision of
passengers.
g) Free flow through all parts of the routes between air
and ground transport should be interrupted as little k) Features which cause hesitancy, such as ambiguous
as possible. While government controlauthorities terminology on signs, flow routes which appear to
andaircraftoperatorsdetermine their own pro- lead in the wrong direction,and multi-directional
cedures, the plan should provide for them in the best junctions should be avoided.
manner to achieve passenger convenience, maximum
security, optimum utilization of staff and minimum 1) The speed of flow and capacity of the passenger
cost for aircraft operators and control authorities. routes should be matched to that of other systems,
such 9s baggage flow and aircraft turnaround time,
Every control pointin the flow system has a potential andto the over-all capacity of theairport.The
to delay and also to irritate and confuse passengers. fastest possible passenger flow or highest possible
The delay is caused not only by the time needed for capacity, far from being an advantage, will create
officials to carry out their procedures but also the frustration, delay, congestion and criticism if it is not
reaction time d‘ passengers. This reaction time bdanced by all parts of the airport system.
OTHER
RESTAURANT LEFT BAGGAGE CURRENCY
TELEPHONES PASSENGER
STORE OR LOCKERS EXCHANGE
AMENITIES
L
LOBBY
A
CUSTOMS
BAGGAGE
INSPECTION
A
* ENPLAN ING
CURB - * TICKET
t
COUNTERS
DEPARTURES
u
AIRPORT I
ACCESS I
SYSTEM
, b
A
TRANSFER
BAGGAGE
-
7
I
DEPLANING
CURB -
ARRIVALS
fi CUSTOMS
BAGGAGE
INSPECTION
H '%EE 1 INBOUND BAGGAGE
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
FRONTIER
CONTROLS
- GATES
I
PASSENGER WAITING
AMENITIES AREA
V
AIRCRAFT
I-
TRANSIT
TRANSFER
t
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
PASSENGERS
IND BAGGAGE MANAGEMENT
- GOVERNMENT FACILITIES
t I PASSENGER
AMENlTlES
a I FRONTIER
CONTROLS
!D BAGGAGE
-1
~
AIRLINE
AIRCRAFT SERVICING
OPERATIONS FACILITIES
11 LEFT BAGGAGE
STORE OR
A
a) single level road/single level terminal
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
b) single level road/doubIe level terminal
D Departing passengers
4 Arriving
passengers
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
within a customs union, economiccommunity of
Signing considerations free trade area, in which the national governments
have agreed on thefree passageof people and goods.
9.2.16 In order to realize the full capacity potential of Depending on the details of such agreements traffic
the passenger building, an orderly flow of both passengers may be domestic inone direction and internationalin
and baggage must be achieved to assure this orderly flow. the other. Thus, the classification between domestic
Prudent use of the system of international signs is necess- and international applies to the aircraft route and
ary in orderto assist airtravellersinlocating various not
the origins and destinations of individual
facilities and services (See Doc 9430). passengers
indicated
as below under “Service
Characteristics.”
d) Transfer. Some passengers arriving at an airport by originating/terminating stations, thereby reducing depar-
air may do so simply to connect with a flight for ture lounge space requirements.Typical domestic peak
anotherdestination.For most planningpurposes conditions will show hourly aircraft movements per gate
these passengers can be considered as transit averaging 1.5 to 2.0. Experience in planning for these
passengers except that their baggage needs to be characteristicsindicates theimportanceof identifying
transferred to anotheraircraft.
Some ticketing originating passengers separately from total enplanements.
facilities are required specifically for their use, and
planning should therefore take account of this type 9.2.24 A “transfer/transit station”
airport
has a
of traffic. significant proportion of passengers transferringfrom
arriving flights to departing flights or arriving and
e) General aviation andair taxis. There maybea departing on the same aircraft(at least 30 per cent of total
demand for general aviationand a careful cost- enplanements, including onlineandofflinetransfers).
benefit
analysis should
be
made to determine Aircraft
ground servicing times will average 30 to
whether to intermix thistraffic with commercial 60 minutes, dependingupon connecting patternsand
aviation or to keep it separate. While air taxis may operating policies. By determining the relative proportion
be a problem at large airports, this is not usually the of online and offline transfers for each carrier, adjacency
case at small- or medium-sized airports. of carriers with a high proportion of interchange may help
reduce over-all in-terminalcirculationrequirementsand
Service characteristics - scheduled airlines between-flight connecting times. Typicaldomestic peak
conditions will show hourly aircraft movements per gate
9.2.21 Airline service characteristics are directly averaging 1.3 to 1.5.
related totheroute certificates,bilateralagreements,
andstructureof eachscheduled airline’s system. They 9.2.25 Comparedtothesamevolume of enplane-
can generallybe
categorized intothree basic types: ments at an OriginatingAerminating stationairport,the
originating/terminatingstation,
through station,
and transfer/transit station airport will have:
transferhamit station. An airport may be identified as
one type for theairline industry ingeneral and at the same - less groundtransportation activity and a lower
time serve as a different type for an individuai airline. The requirement for curb frontage;
characteristics of a particular airport may change as an
airline is awarded new routesand develops different - less need for airline counter positions serving normal
connecting patternsandasthe results of new bilateral ticketing and baggage check-in, although
more
route negotiations are instituted. positions may be required for flight information and
ticket changes;
9.2.22 An “originating/terminating station”airport
is usually characterized by a high percentage of originating - less requirement for baggage claim area, but more
passengers (over 70 per cent of total enplanements) and a space needs for baggage transfer(onlineand/or
preponderance of turnaround flightswith ground times interline baggage);
ranging from 45 to 90 minutes or more. Another character-
istic is in the primary flow of passengers between aircraft - increased requirements for concessions and public
and ground transportationvehicles, generating a relatively services because of passengers remaining in the
high requirement for ticket counter,curb length and terminal while waiting for connecting flights. This is
parking spaces per enplaned passenger as compared with generally related to aircraft ground servicing times;
transferkransit or through stations. Passengers will and
usuallyrequire maximum baggage-handling services for
checking and claimingbaggage.Typicaldomesticpeak - increased need for centralizedsecurity control
conditions will show hourly aircraft movements per gate locations to assist passengers transferring tG other
averaging about 0.9 to 1.1. flights.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
carriers which operate similar types of non-scheduled to service charteroperations when seasonalpeaks or
service. The certificatedsupplemental carriers generally recurring operationpatterns exceed the capabilities of
operate aircraftsimilar to those of major international flag facilities leased for their own scheduled operations. Any
carriers, although seating capacities may be higher. Since suchproposalshould beevaluated thoroughly with the
the supplementals do not lease facilities at most airports, airlinesinvolved,since a separatecharter facility may
their operations are oftenhandled by a certificated carrier involve considerable inefficiencies in logistks,staffing,
or by a fixed base operator (FBO), who may be located ground equipment utilization, and other costs.
outside the passenger building complex.
Service characteristics - international airlines
9.2.27 Air-taxi operatorsconstituteanother class of
non-scheduled/charter service using aircraft that
are 9.2.30 Depending upon the geographic
locations
generally smaller than those operated by other airlines. At involved, one characteristic of international service is a
manyairports, air-taxi service is provided outsidethe tendency toward higher scheduled peaks dueto heavy
passenger building complex. dependence on schedules for city pairs related to timezone
crossing. Another characteristic is that of relatively long
9.2.28 Airline facility planning for non-scheduled ground service times (two to three hours for turnarounds,
operations involves consideration of the following: and one hour for through flights) required for long-range
aircraft servicing.
- Frequency/volurnes. Collectively these usually
suggest facilities that are moremodest and utilitarian 9.2.31 Governmentalcontroland clearance (or pre-
than those for scheduled operations. clearance)requirements aremajor planningconsider-
ations, particularly thoseforthefrontiercontrolsand
- Group processing. May permit “batch loading” and customs baggage facilities. The techniques and procedures
bypassing
otherwise
congested elements of the used in implementing governmental regulations vary from
passenger building apron-terminal. Buses ‘can one location to another and may change periodically.
transport passengers and baggage directly between
off-airport locations(hotels) andaircraftremote
from the passenger terminal. Factors Affecting Scale of Facilities to be Provided
- Processing times. May differ substantially from 9.2.32 The final stage of passenger building planning
scheduled service. Some charterlgroup-tourpro- involves assessment of the size of the facilities and their
cedures call for passengers to arrive at the airport arrangement in the optimumrelationship to each other and
two to three hours prior
to
departure, which in accordance with the flow principles. The facilities
increases the number of peoplein the passenger required will vary according to the number ofaircraft
building well beyond that for scheduled operations. operators tobe accommodated, their proportionate shares
The early arrival requirement is sometimes relatedto of the traffic, the typeof aircraft operated and the nature
airline staffing and fewer counter positions, thereby of the operations.
producing longer queues and more congestion in the
ticketing lobbies. Number of aircraft operators
- Operational reliability. For many reasons, charter/ 9.2.33 For a given volume of trafficthe minimum
group tour departures and arrivals
tend to be delayed ‘facilities would be required if only one aircraft operator
more than scheduled flights. This usually increases had to be accommodated.The scale and variety of
the number of persons in the terminal or departure facilities required increases where there are a number of
lounge areas beyond the norms and patterns typical operators. In these circumstances continuity of utilization
of scheduled operations. of facilities tends to decrease.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
areas or buildings to their individual use. While aircraft adaptable to airports with low airline activity and is
operators do need fairly localized areas of operation in also
adaptable
to general aviationoperations
orderto be abletoconcentratestaffandequipment, whether it is located as a separate entity on a large
separation of operators canlead to anover-all reduction in airline-served airport or is the operational centre for
utilization of facilities and a consequent increase in their anairport used exclusively 'by general aviation.
total size and cost. Where the simple building serves airline operations,
it will usually have an apron which provides close-in
9.2.35 Minimum cost for the airport will be achieved parkingfor a few commercial transportaircraft;
by the most continuous and homogeneous use of facilities, however, due consideration should be given for jet
and passenger convenience will be enhanced by reduction blast effects against the building when a nose-in or
of interchange between various sections of the passenger nose-out parkingconfiguration is adoptedfor jet
area or buildings. But certainty of the location of their transport aircraft. Where the simple building serves
chosen aircraft operator is also a passenger requirement. general aviation only, it should be within convenient
So between the partly conflicting interests of the airport walking distance of aircraftparkingareasand
authority,aircraftoperatorsand passengers, a compro- should be adjacent to an aircraftservice apron. The
mise is necessary to determine the optimum allocation of simple building concept will normally consist of a
facilities. single-level structure where access to aircraft is by
walking across the apron. The layout of the simple
Developing criteria for the passenger building plan building should take into account the possibility of
linear extension for future expansion.
9.2.36 Specific planningcriteria, related todemand
and capacitycited below, should be developed forthe b) Linear concepf. The linear building concept may be
abovefactorsandforthosemajor passenger building regardedas an extension ofthe simplebuilding
components affecting thescale of facilities to be provided. concept, that is, the simple building is repeated in a
Information for determining passenger buildingrequire- linear extension to provide additional apron front-
mentsshould be obtained from allpresent or potential age, more gates and more space within the building
users ofthe facilities including, inter alia, the airlines, for passengerprocessing.Passenger and baggage
general aviation interests,
concessionaires, airport processing cantake placeina centralarea of a
management, and special technical committees which may terminal(centralization),but when theterminal
be organized to act asadvisors to the airportplanners. The becomeslarger with increased number of aircraft
criteria should be analysed and agreed upon by all parties gate positions the problem of longwalking distances
involved before being incorporated into the master plan. arises. This problem can be solved by installation of
mechanical devices, such as people movers,or by
Determination of passenger building concepts decentralizationofsome passenger and baggage
processing
facilities. Complete
decentralization
9.2.37 The selection of a passenger buildingconcept wouldallowpassenger and baggagecheck-in and
must be made jointly with the selection of the aircraft baggage claim at the individual gate and thus afford
parking system discussed in 7.3.8. Through careful study very short walking distance between curb-side and
and analysis, the planner should reduce the possibilities to aircraft,butconstructionandoperation become
those few concepts which will be most compatible with the costly. The degree of decentralization of processing
planned airport configuration. Thesemost
desirable facilities must be determined after careful study of
concepts should thenbe presented to airport management, volume and type of traffic, and of construction and
airline and general aviation interests, andairportcon- operation costs.
cessionaires for their considerationandappraisal.It is
essential that co-ordination with airport interests and users The linear configuration lends itself to the develop-
be effected beforethefinal selection of a passenger ment of adequate close-in public parking. Ample
building concept is made. If this is not done, the plan may curbfrontageforloadingandunloadingground
well be rejected at the time of its official presentation. The transportation vehicles can be provided with each
following concepts should be considered in the develop- extension of the linear building. Linear buildings can
ment of the passenger building plan. beexpanded with almostnointerference to pass-
engerprocessing or aircraft operations. Expansion
a) Simple concept. The simple building concept consists may beaccomplished by linear extension of the
of a single common waiting and ticketing area with existing structure's air-side corridor orby developing
several exits into small
a parkingapron. It is two or more linear building units connected by an
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
air-side corridor.Theloading of aircraft may be Because the distance from the main building to a
accomplished by nose-idpush-out operations with satellite is usually well above the average distance to
or without passenger loading bridges. gates found with the pier concept, a people-mover
system or some other mechanical devices are often
c) Pier (finger) concept. The finger or pier concept used to reduce walking distances between terminal
evolved in the 1950s when gate concourses were and satellite. There is no direct relationship between
added to simple central buildings. Since then, very the number of gates and curb space so that special
sophisticated forms of
the concept
have been care should be taken in the planning of enplaning
develcped with the addition of hold rooms at gates, and deplaning roadways serving the central building
passenger loading bridges, and vertical separation of to prevent curb overloads.
the ticketing check-in functionfromthe baggage Buildings developed under the satellite concept are
claim function. However, the basic concept has not difficult to expand without reducing apron frontage
changed in that the main central passenger building or disrupting airport
operations. Increases in
is used to process passengers and baggage (a central- building capacity are therefore usually effected by
ized system, although waiting lounges in most cases the additionof new units rather than expansion of an
are dispersed at each gate position along piers) while existing unit.
the pier provides a means of enclosed access from the
central building to aircraft gate. Aircraft are parked Other concepts. Other passenger terminal concepts
at gates along the pier as opposed to the satellite include the transporter concept (also known as the
concept where they are parked in a cluster at the end remote aircraft
parking concept) and the unit
of a concourse (see Figure 7-3). terminal concept. T i e former involves the vehicular
transportof
departing
and arriving passengers
Walkingdistances through pier buildingstend to discussed in Chapter 7, and may be combined with
become long. Curb space must be carefully planned other concepts to cater for peak hour demands. The
since it depends on the length of the central building latter is one where the individual compact module
and is not related to thetotalnumberof gates units are built around a system of interconnecting
afforded by piers. This is particularly true of access and service roads. The buildings are spaced
deplaning curbs near centralized
baggageclaim some distance apart under this concept, with each
facilities. Although the pierconcept hasafforded buildingproviding complete passenger processing
one of the most economical means of adding gate and aircraft parking facilities. Consideration of the
positions to existing buildings, its use for expansion unit terminal concept is usually feasible only for the
shouldbelimited.Existing piers shouldnot be larger airports.
extended at the expense of taxiway manoeuvrability
nor should new piers be added withoutproviding 9.2.38 Passenger building concepts can also be
adequate space for passenger processing in the main considered by the level(s) on which passenger arrival,
building. Most successful additions are effected by processing anddeparture
takes place. Four typical
extending the main building and then increasing the configurations are as follows (see also Figure 9-2):
number of piers.
Single-level road/single-level terminal. Arrival and
d) Safellite concept.The primary feature of the satellite departure processing in the terminal is done at same
concept is the provision of a single. centralized level but is separated horizontally. Passenger
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
terminal with all ticketing, baggage processing, and boarding to aircraft is by means of stairs.
ancillary services except waitinglounges, which is
connected by concourses toone or more satellite Single-level road/double-level terminal. Arrival and
structures. The features of the satellite concept are departure processing in the terminal is normally at
very similar to those of the pier concept except that grade (road level) with departure lounges on a higher
aircraft gates are located at theend of a long level, permitting the use of passenger loading bridges
concourse rather than being spaced at even intervals or of transporters with level change capabilities.
along it. Satellite gates are served either by common
or by separate hold rooms. The concourse can be Double-level road/double-level terminal. Access
elevated or located underground, thereby providing roads and curb-side are on different levels, to allow
space for ground service equipment and aircraft taxi vertical separationofarrivalanddeparture pro-
operations between the main building and
the cessing in the terminal (usually, the upper level is for
satellite. departure and the lower level for arrival).
d) Single-level roadddouble level terminal. This is a concept is one of a number of movements (of passengers,
variationof c), with access roadand curb-side bags or vehicles) per unit of time, the appropriate unit of
forarrivalanddepartureseparated horizontally time depending upon the particular application. In some
(laterally) but not vertically. cases itmaybedesirable to plan capacity to satisfy an
estimated peak demand, but normally a figure somewhat
9.2.39 In the process of developing a terminal below this will be more realistic due to costs involved and
concept, planners must also pay attention to the desired space required. What is important is to match the capaci-
degree of centralization or decentralization of the pass- ties of different segmentsin the processing,because
enger and baggage processing facilities(passengerlbaggage inadequate capacity in one operationwill restrict the over-
check-in,government and security control, baggage all flow.
sortingandmake-up,departing passenger holding, and
baggage claim facilities) within a terminal. A centralized 9.2.42 The capacity of the
public
corridor in
design means that allpassenger and baggageprocessing passengerbuildings is a function of walkingspeed, the
facilities are centralized forcommon use by allgate width occupancy expressed as a lateral distance per person
positions at a terminal: (There are variations and excep- (passenger or visitor), and headwaydistancebetween
tions to this, such as the pier concept which is basically persons in the direction of flow.While variations in speed,
centralized yet normally provides
passenger holding width and distance are bound to occur, averages can be
lounges for exclusive use by each gate position.) In selected in order to arrive at average
an flow of persons per
contrast, eachof the processing facilities in a decentralized unit of time per unit of width of public corridor, using the
design is dispersedover a number of centreswithin a following equation:
terminal. In a completely decentralized concept, all of the
processing facilities are available at each gate position for ws
its exclusive use. Complete decentralization affords cc =
WO x HD
advantages such as shorter walking distances,efficient
passenger and baggage flow, iess chances of mishandled where:
baggage, etc., but it may turn out to be uneconomical due
to under-utilization of personnel, equipment and terminal CC = corridor capacity (number of persons per minute,
space. Thus the planner should analyse the efficiency of per one metre width);
WS = walking speed (normally 75 m per minute);
-
the processing system as a whole, its economy in terms of
total requirementsof floor area, equipment and personnel, WO = width occupancy (0.6 ,r. 0.8 m per person);
and passenger convenience to achieve optimum degree of HD = headway distance between persons (1 2 m).
centralizationor decentralization of the passenger and
baggage processing facilities. 9.2.43 Inordertodeterminethe width of a facility
such as a pier, the total flow rate per unit of timemust be
known. Arriving aircraft create a much greater concen-
tration of passengers in a relatively short period of time
Capacity and Demand thandodepartingaircraft, a problem which is com-
pounded when large capacity aircraft use the airport. The
9.2.40 In planning, the aim should be to ensure that size ofthissurge will depend primarily onthe size of
capacity satisfies demand within practical economic limits aircraft, their arrival schedules, and the number of exits
and to providecapability for increased capacity as demand that are used. Therefore, in the planning of space for a
increases with traffic growth. Because of the time required pier facility, a flow rate of passengersper hour is not
to construct additional facilities, it is normal practice to appropriate; a much shorter time period, such as five to
plan capacity which will be in excess of demand during the ten minutes, may have to be used. The appropriate time
initial life of the facility.Statistical forecasts to be used for period forall parts of the passenger building will not be the
planning are discussed in Chapter 3 . sameandmustbe assessed individuallydepending on
function.
Movement rate
Capacity to be provided
9.2.41 For planning purposes, the capacity of a
passenger building or of its segments is usually expressed 9.2.44 Airport authorities may be faced with a
in terms of achievable movement rates or, in some cases, number of alternatives in deciding the capacity for which
of actual populations for a given area. Although there are passenger facilities should be planned. The introductionof
different criteria used to describe movement rate, the basic new very high-capacity aircraftmade it
much more
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
important to consider these alternatives, because their be provided should be determined by the over-all cost-
passenger capacity may represent a very large proportion benefit analyses. If provision of passenger capacity for the
of the hourly capacity of many passenger buildings, forecast flow conditions cannot be economically justified,
accentuating the concentration of passenger flow. Four e.g. because of the infrequency of occurrence or very high
alternatives are outlined below; all four have disadvan- cost, it maybe necessary to combine some degree of
tages andthe choice should be made by progressive limitation of aircraftoperators’ schedules with some
elimination of the least desirable. passenger congestion of a limited duration.
First alternative: estimate the building area required for Processing rates
the maximum passenger capacity of the runways (that is,
assume that all runways will be used to their maximum 9.2.45 The appropriate measurement of capacity may
capacity andthat all aircraft will be the largest type not be the same for all individual facilities. The rate at
forecast to use the airport). In actual practice, the forecasts which passengers flow to a facility is determined by the
of passenger demand and probable aircraft mixture will rate at which they flow through the previous part of the
usually produce a passenger flow rate below this maximum route. For example, the rate at which passengers leave an
passenger capacity, allowing a downward adjustment of aircraft i s determined largely by the number andsize of the
the building area required. aircraft doors used. The rate at which they flow into the
passenger building depends uponthe method used to
Second alternative: allow delays and congestion caused transport them to the building. Passengers flowing
by surges in the flow to rectify themselves within one hour, through a pier will spread out according to their walking
as provided for by the standard busy rate which assumes speeds and will arrive in a stream at thefirst control point,
that peaks of up to20 per cent will occur for short periods. i.e. port health or immigration for international passengers
As traffic increases at busy periods, however, and with and baggage reclaim for domestic passengers. Passengers
high capacity aircraft, it may be expected that congestion conveyed to the passenger building in a vehicle, either from
in any one hour would spread to succeeding hours and it the aircraft or population centre, will arrive at the frontier
would soon benecessary to restrict the traffic demand. controls or check-in position in groups.
Acceptance of such excessive delays is most undesirable.
9.2.46 The average time required to process one
Third alternative: spread the traffic evenly throughout passenger at any specific facility depends upon the nature
the hour by specifying a capacity for a shorter period, for of the procedures; these vary, both in content and method,
example 15 minutes. This would restrict aircraft scheduling between States. The processing time for each facility and
so that the passenger flow is evened out over the hour. This control on the flow routes can be determined by obser-
is practised by some airportauthoritiesand has the vation. It is not possible to define standard processing
advantages of spreading the airport’s utilization and times for all airports, although the times achieved at other
permitting more efficient and economic use of facilities airports are often agood guide to the flow rate which can
andstaff. It may not be favoured by some aircraft be achieved. For example, at some airports immigration
operators because it limits the use of any preferred officials undertake health document inspection or prelimi-
departure and arrival times. However, every airport and nary customs control. At others each of the controls is
passenger building has a finite capacity which, when carried out by different officials atseparate locations.
reached, requires schedules to be spread. The disadvantage Sometimes customs controls are established for clearance
of this procedure is that it cannot be applied to arrivals of passengers and baggage separately. At others both are
traffic. Conditions en-route, such as winds and delays at cleared at the same point. Similarly, some aircraft
otherairports, can introducea considerable element of operators checkin passengers and their baggage at one
irregularity in arrival times and small variations can point, others check in baggage at one point and passengers
accentuate surges and have a large impact on the passenger at another.These are only examples of the wide differences
flow. in existing passenger control procedures and a comparison
of processing times is invalid without analysis of the
Fourth alternative: plan the passenger facilities on the methods and procedures used.
flow rate indicated by the size, duration and frequency of
the passenger surges. This would produce an hourly 9.2.47 The nature of the control also determines the
capacity significantly higher than the capacity necessary period of delay or degree of congestion which is acceptable
for an even distribution of traffic throughout the hour. at that point for the efficient operation of the passenger
The cost of providing capacity for the passenger surges building. The standard busy rate, being less than the peak
within the hour should be considered and the capacity to rate, assumes that it is exceeded for a small proportion of
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Similarly, the baggage reclaim lobbydimensions, pre- taxis at the deplaning road sections can be controlled by
dominantly thereclaim device arrangement, will determine dispatching from a designated queue line.
the number and spacing of building openings andthe
effective passenger building frontage available. Building 9.3.9 The loading and unloading of passengers by
conceptsproviding curb areasgreatly in excessof the private vehicles and unloading by taxis cannot be tightly
building length or providing an excess of building controlled. Orderly performance therefore depends on the
entrances and exits with little direct relationship to either arrangement and organization of the curb lanes, building
ticket counter or baggage reclaim should be analysed for openings and signs.
their economics, efficiency, and passenger convenience.
9.3.10 Vehicular curb manoeuvring lanes are provided
9.3.6 The curb-side baggage check-in system was once
for the purpose ofloading and unloading passengers with
considered to beideal for departing passengers as they
bags. The dimensions in length and width need to be such
could drop their baggage at adesignated areaof the
that traffic volumes generated for the design year during
enplaning curb frontage for an airline agency to check-in,
peak periods will be processed without undue delays. The
thus becoming free of their baggage prior to checking in
curb manoeuvring lane width should be approximately 1.6
for their seats. However, for security reasons this system
of a regular traffic lane, to permit manoeuvring to take
is no longer considered practical for international flights.
place without interfering with the flow of traffic.
In this regard it is worth noting that ICAO Annex 17 calls
for a State to establish measures to ensure that operators
providing service to or from that State do notplace or keep 9.3.11 Thecurb manoeuvringlaneshould be used
the baggage of passengers who have registered, but who only for loading and unloading, and not as a waiting area
have not reported for embarkation, on board the aircraft, for vehicles. Each vehicle should occupy a curb space only
without subjecting it to security control. for the time it takes to load or unload passengers and
baggage, and to manoeuvre into and out ofspace. the This
total time is identified as the “dwell timehehicle.” Strict
Capacity and curb space utilization policing, as ,done at many high-volume airports t o
minimize dwell time, will promote anefficient traffic flow.
9.3.7 Thecurb length required is affected by the
numbers, average size and characteristics of vehicles. The
9.3.12 Thenumberof building entrances and exits
use of cars by passengers may be influenced by any public
signs, and sign programme both for public information
transport systems which areprovided, particularly an
and airlineidentificationshould be arranged in sucha
exclusive town centre/airport system. The distribution of
manner thatthe effective curb length thusformed will
passengers by travel modes and the numbers and types of
closely approximate the required curb length.
vehicles to be accommodated can be obtained from the
operational and economic forecasts. The minimum time
necessary to unload passengers and baggage depends upon 9.3.13 The required curb length can be calculated as
the averagenumber of passengers per vehicle andthe follows:
averagenumber of pieces of baggage per passenger.
Occupancy time should be limited to ensure that there is Determine design hour passengers enplaning and
always space to unload passengers and baggage without deplaning. Identify the design period for deplaning
congestion or delay. This limitation will depend upon the passengers within the peak-hour - peak 10 or
rate of arrival of vehicles and the total number of spaces 20 minutes (a 20-minute peak can be equivalent to
available - many airport authorities have found that a 50 per cent of the peak-hour traffic).
waiting period of three minutes for cars is sufficient for
unloading and is consistent with provision of a number of Determine the percentage of transfer passengers of
car spaces which is economicallyreasonable and com- thetotal,and deduct fromthetotal design hour
patible with the passenger flow principles. requirement to find the number of passengers
entering the airport using the road system.
9.3.8 Ananalysis of curb spaceutilization by the
various types of vehicles shouldbeperformed. It is Determine the modal preference by vehicular type.
assumed that curb areas forbuses, limousines and courtesy
cars will be designated areas and, asa consequence, can be Determine the percentage of passengers thatgo
completely controlled. Similarly, queue lines for taxis will directly to the parking facility and do not use the
be designated and controlled. Pick-up of passengers by curb system.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
e ) Determine the visitor ratio of passengers to visitors, check-in; separation of functions is most important in this
and apply tothe percentage of passengers using area t o ensure that this primary flow is not compromised
private vehicles. (see Figure 9-3).
T O D E P A R T U R E S CONCOURSE
CHECK-IN P O S I T i O N S
t t t t
CHECK-IN CONCOURSE
t t --```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
A I R C R A F T O P E R A T O R S ’ T I C K E T S A L E S . S T A N D - B Y R E S E R V A T I O N S , ETC.
9.4.4 The space between the land side entrances and 9.4.9 The number of check-in positions required is a
check-in positions should be sufficient to provide free function of the time required to process one yassenger and
access to check-in and other facilities. Check-in concourse the rateof flow to thecheck-in positions. Average check-in
sizing is a function of total length of airline ticket counter process times vary according to the route and category of
frontage, queuing at counters, and allowance for lateral traffic and should be determined in consultation with
circulation without undue congestion. For small- and aircraft operators. Based on the process time, asustainable
medium-sized airports,adepth of approximately 10 m check-in ratecan be defined and the capacity for each
should be adequate for the check-in concourse. However, position required can be defined. Surges within the hour
airports having a high visitor/passenger ratio may require occur onthe same basis asfortheland side vehicle
additional depth. unloading positions and the unit period for rate of flow
measurement should similarly be obtained by research
9.4.5 Although check-in is the primary activity in this measurement. It is necessary to ensure that passengers
area, a number of allied functional facilities, i.e. aircraft arriving just before the designated final check-in time can
operators’ ticket sales, stand-by passenger registration, be processed without delay.
aircraftoperators’informationand currency exchange
facilities may also have to be accommodated. 9.4.10 The type and number of counter positions
required are usually determined by the airport authorityin
consultation with each airline or handling agency accord-
Aircraft operators’ ticket sales, ing to itsstaffing criteria and company standardsfor
stand-by registration and information processing passengers and baggage. Individual airport
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
variables that influence the number of positions include
9.4.6 Passengers purchasing tickets or making stand-
one or more of the following:
by registrations must do so before they can check in.
Similarly, passengers may require information from
Design hour enplanements. These are usually derived
aircraftoperators before purchasing tickets o r making
from projections of peak hourlaverage day of peak
reservations. To ensure unobstructed flow to the check-in
month enplanements plus consideration of the
positions these facilities should be located clear of the
number of gate positions, the seating capacity of
primary flow streams.
aircraft that those gate positions can accommodate,
and boarding load factors considered representative
Currency exchange for the airport.
9.4.7 Passengers making payments for ticket purchase Contact ratio. This ratio is usually projected from
orairport tax mayneed to cash cheques or change historical data and shows the relationship between
currency, and a bank or currency exchange facility is, the number of passengers who contact counter
therefore, required in the check-in concourse. In choosing agents andthe total number of enplanements or
the location, careshould be taken to ensure thatpassengers originating passengers. Separate contact ratios can
using this facility do not interfere with the free flow of be determined for each type of counter position:
passengers through the building. ticketing, baggage check-in, multipurpose, infor-
mation, and future ticketing.
Airport tax or passenger service charge
Passengerarrival distribution patterns. This is the
9.4.8 Where airport taxes or service charges are rate at which enplaning passengers arrive at check-in
imposed on departing passengers, methods should be counters for processing, sometimes presented in
developed whereby passengers may pay them when tables showing the percentage of passengers arriving
purchasing tickets. When this cannot be done, arrange- in 5- or 10-minute increments during a period up to
ments should be made for payment of these charges in the 120 or 150 minutes prior to departure. Twodifferent
vicinity of check-in counters. The fullest advance warning patterns may be applicable at some airports where
should be given to ensure that passengers are aware of any the passenger arrivals for early morning flights occur
payment to be made before they arrive at the point of during a shortertime span than do passenger arrivals
collection or pass the currency exchange. duringother times of theday. Figure 9-4, which
I-90 --```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Airport Planning Manual
Line A - Percentage distribution of passengers arriving for flights departing between 1000 and 0400.
Line B - Percentage distribution of passengers arriving for flights departingbetween 0405 and 0955.
illustrates these points, can be derived for individual positionforanyflight.Utilizationofthe facilities, and
airports by time-coding passenger tickets at contact hence the total capacity required, will depend on whether
with theagentand then relatingthistime to the particularpositionsaredesignated for specific purposes
scheduled departure time of the passenger’s flight. (for example, sperific check-in positions for domestic as
opposed to international services, or separate positionsfor
d) Average process time for each type of counter each operatorortlight).The check-in capacity to be
activity. provided is a matterforbothaircraftoperators’and
airport authorities’ judgement.
e) Service goals of an individuai airline for specific
types of counterpositions. Theseare generally 9.4.13 Use of the land sidevehicle unloading positions
expressed asthepercentageof passenger contacts andentrances to the passenger buildinghasalso to be
who will wait for service “x” minutes or less. related to any allocation of check-in positions for specific
purposes.Homogeneous use of all check-inpositions
Thecombinationofenplanements,contractratiosand provides the greatest passenger convenience and ensures
arrival patternsdescribes the passenger flow to a given type highest utilization of land side vehicle unloading positions
of counter.Passengerflow,processtimeand airlines’ and check-infacilities and, therefore, requires minimum
service goals are used to determine the number of agent provision of these facilities and building space. The more
positions required. that facilities areallocatedto specific uses themore
difficult it becomes to provide balanced capacity over all
9.4.1 1 Late check-in can be effectedattheaircraft parts of each flow stream,with passenger routes becoming
gate in circumstances where passengers would otherwise less straight and cross-flows developing along the length of
miss :heir flights. This places on passengers the burden of thebuilding.Theoptimumbalance is oftendifficultto
transporting their baggage to the gate, but the system is define butit will be achieved by close adherence to the flow
permissive and it is for the passengers to decide whetherto principles and cost-benefit assessment.
accept theburdenor miss theflight.Thisarrangement
should, however, only be used to supplement the provision Check-in systems
of appropriate check-infacilities in the check-in con-
course. If the terminal is designed following a completely 9.4.14 The check-in system used by airlines or
decentralized concept (gate check-in concept), late check-in handling agencies can exert a major influence on planning.
can beeasily accommodated. However, consideration shall The conventional check-in system of manual ticket control
be given totheeconomicaspectsincepersonneland and baggage weighing and labelling is still in use, but only
facilities tend to be underused when decentralized. at smallairports.Manyoperators firid it economically
justifiabletoinstallcomputer check-insystems, and
9.4.12 Furtherconsiderations
influencing check-in alreadycomputerized departure
control systems with
capacity are the number of aircraft operators, their shares inputs from check-in desks at airports and elsewhere are
of the traffic and frequencyof operation, the allocationof being widely used. Airport planners should be aware of
check-in positionsandoperating system adopted.The common use terminalequipment (CUTE) which is a
minimum facilities will be required when allare used generic airlineindustrytermfor afacility which allows
homogeneously and any passenger can check-in at any individual airlines to access their host cornputer(s), and to
share passenger terminal handling facilities. Full details in Split check-in concept. The check-in function is split
respect of CUTE systems are contained in IATA between two or more locations within the terminal
Recommended Practice 1797 which is available from complex, e.g. baggage may be accepted at check-in
Senior Manager, Passenger Services, IATA, 2000 Peel counters on the lower level and seat assignment takes
Street, Montreal, Quebec, Canada, H3A 2R4. A place at the waiting lounge on the upper level of the
concurrent development is the elimination of baggage terminal.
weighing and thus theneed for scales. This already applies
on manydomestic routes, where the passenger baggage Gate check-in concept. Gate check-in is normally
entitlement is fixed as a specified number of pieces of directly
related to
the decentralized passenger
defined size. terminal concept. By this system passengers and
baggage are processed at check-in counters located
9.4.15 These new operational systems can affect very close toanaircraftgate position (or a few
passenger building planning by imposing different space positionsin case of semi-decentralized passenger
requirements for the check-in positions. They may also terminal concept) andits waiting lounge. This
reduce the passenger service time so that thecapacity (flow concept
can afford advantagessuch as
short
rate) of the check-in positions would be very considerably distances, simple check-in handling for both
increased. The capacity of any particular section of the passengers and baggage, etc.However,economic
passenger flow routesshould bematched by acorre- aspects should bewell taken intoconsideration, since
sponding capacity in the other sections. Failure to d o so the facilities and personnel tend to be under utilized
merely causes congestion and consequent delay in the during off-peak hours,
subsequent lower-capacity sections of the route, or under-
utilization of the high-capacity section, because passengers 9.4.19 The check-in counters, on the other hand, may
cannot flow to it fast enough. be divided into three types of configuration:
9.4.16 Changes in check-in systems canalsoaffect a) Linear counter. This is the mostfrequently used
their utilization and the systems of allocation. The extent ticket counter configuration. Atlow-volume airports
to which new high capacity check-in systems can, or need multipurpose positions are common where an agent
to be adopted, will vary among aircraft operators and the can
perform
any ticket transaction, check in
routes and types of traffic which an airport serves. The baggage, and provide such other service as anairline
appropriate balance between numbers for eachtype of maydeem appropriateto its operation. Multi-
system and the appropriatesystem of allocation should be purpose positionsreduce thenumber of servicing
determined by the airport authority in consultation with stops for some passengers and afford flexibility in
operators, in the light of local circumstances. staffing, especially during non-peak periods.
passengers queue along the baggage input, complete 9.4.22 The check-in positions should be grouped into
their transactions with the agent, and walk through units of sufficient size to maintain acceptable staff costs
to a lobby or circulation area beyond. The principal and utilization compatible with efficient passenger flow.
advantagesare reducing
cross-circulation and Too many positions in each group would compromise the
increasing baggage take-away capability, by provid- flow principlesto anunacceptable extent, and theflow rate
ing oneinput for one or two positions at linear would be reduced by congestion and confusion. Thelarger
counters. This increased capability can be beneficial the number of positions the more the passenger flow is
at high-volume stations havinga relatively high distorted.
percentage of “baggage-only” transactions.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Layout 9.4.24 Passengers havetobeinformed when their
aircraft is ready for boarding andwhen delays occur. This
9.4.20 Check-in facilities should belocated so as to has generally been done by loud speaker annoucements,
enable passengers to check in atthe earliest possible but at busy airports such arrangements can
cause
moment, thusreducing the effect of delays at earlier stages problems: duetotheconstant flow of annoucements
of the flow route and permitting the latest possible arrival passengers tend to miss those applying to their particular
at the airport before flight departure. This also enables flight andthe high ambient noise level inbuildings
passengers to be relieved of their baggage at the earliest containing a lot of people necessitates a high volume for
opportunity. theloudspeakerannoucements which cancause severe
discomfort for staff working in the building.
9.4.21 Check-in positions should be immediately
obvious on entering the building. Passengers flow to the 9.4.25 Visual presentation of flight information
check-in positions in a number of parallel streams formed should,therefore, be considered.Flight information
by the layout of the land side vehicle unloading positions, display systems should be considered at the same time as
and the passenger building land side entrances. The layout the check-in cmcourseand waiting areasare being
of the check-in facilities is influenced by two consider- planned. They should be located so that flight information
ations - preservation of the straightness of the parallel is visible from all principal parts of these areas, and also
flows acrossthe check-in concourse through to theair side, to ensure that they do not create visual obstructionor
and minimum distance to the air side. Examples of check- cause passengers to obstruct the primary flow routes. In
in layoutsare shown in Figures 9-5, 9-6 and 9-7. For large buildings, the size of indicators necessary for viewing
straight, direct flows passengers should pass between the from all parts of the check-in and waiting areas may be
check-in positions asthrough a comb,as depictedin incompatible with these considerations and more than one
Figures 9-5 and 9-7; long continuous lines of check-in indicator at each location may be necessary (refer to the
positions at right angles t o the flow can conflict with the ICAO publication Dynamic Flight-related Public Infor-
flow principles. mation Displays).
TO DEPARTURES CONCOURSE
t t
CHECK, TIOYS
CHECK-IN CONCOURSE
I
TO D E P A R T U R E S C O N C O U R S E
P O S I T ICOHNESC K - I N
4I
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
CHECK-IN CONCOURSE
4
t-t-t-t4- t+
Figure 9-6. Passenger check-in positions and check-in concourse
TO DEPARTURES CONCOURSE
t t
6 t n. OFFICE
C H E C K - I N POSITIONS
I
I
I
I
I
.
I
rn I
rn I
ija
rn
g;> a 4...................... =
i.............................................. 1.......4
rn rn
Copyright International Civil Aviation Organization
Provided by IHS under license with ICAO Licensee=Mng Airlines/5932817001, User=Sevik, Hulya
No reproduction or networking permitted without license from IHS Not for Resale, 04/06/2013 15:42:18 MDT
1-96 Airport Phnning Manual
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Customs accommodation
9.5.21 Where the numbers of baggage or passengers in
9.5.19In association with the baggage inspection the claim area at any one time are fairly small, simple
control, customs may require offices for their admin- manual systems which rely on passengers moving to their
istrative procedures, as well asfor interview or search bags are satisfactory. However, this can lead to confusion
rooms for passengers found in contravention of regu- when too many passengers claim their baggage simul-
lations. The same considerations apply to the siting and taneously. As passenger flow rates and aircraft sizes
form of these offices astothe airline check-in offices increase, baggage claim systems should be arranged to
described previously. Office accommodation for customs eliminate milling; this can only be achievedby having
in this area should be restricted to the absolute minimum passengers remain in the principal flow streamsand
necessary for application of baggage inspection; sup- presenting their baggage to them, on equipment arranged
porting administrative offices, rest rooms, etc., should be in a “comb” across the line of the flow. For high flow
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
provided elsewhere in the building. rates, reduction in milling can be realized by presenting
BAGGAGE INSPECTION
-
-t -1 BAGGAGE CLAIM
AREA
t t’
4
FRONTIER CONTROLS
TO ARRIVALS CONCOURSE
t 4
t
DECLARATION
t
FREE
FLOW
C U S T O M SI N S P E C T I O N
DECLARATION
‘t D
FREE
FLOW
t
F R O MB A G G A G EC L A I M
t
Figure 9-10. Customs inspection
baggage on a moving display, such as arevolving turntable of import duties and taxes andwhich are not subject
or belt, which passes in front of the passengers. to import prohibitions or restrictions; and
9.5.22 Space should be provided, behind the frontier b) the other channel (red) for other passengers.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
controlsand in front of the baggage claim, in which
passengers can wait if baggage delivery from aircraft is
delayed.Facilities shouldalso be provided in theclaim I t is possible to apply random or selective checks to these
area for the storage of baggagebelonging to passengers streamsas may be requiredwithoutinterruptingthe
who are delayed by health or passport controls. Misrouted normal fast, unimpeded flow. The streams in the second
or unclaimed baggage should
be
stored in facilities category should flow past customs officers in the normal
provided adjacent to the passenger processing areas, rather way.
than in the claim area.
9.5.24 Once“red”
and
“green”
channels
are
adopted, the number of streams can easily be altered in
Customs Inspection accordance with the specific need at the time, as long as the
(see Figure 9-10) totalnumber of streamshas been properlydetermined
based on local conditions.
9.5.23 At international airports, passengers flow from
baggageclaim to customsbaggageinspection.Various
inspectionsystems are possible,with the choiceusually
being dictated by the statutory regulations t o be enforced. Arrivals Baggage Flow
As for all passenger control, the customs inspection should
be arrangedasa“comb.” Flow streamsthroughthe 9.5.25 The considerations to be taken into account in
control should be arranged so that passengers with goods respect of the containers and vehicles onto which baggage
to declaredonotholdup passengerswithout dutiable is loaded and transported between aircraft and passenger
goods to declare. Annex 9 recommends that
States building are the same as described in the departures section
introduce, at their major in:ernarional airports, in close in 9.5.7 through9.5.15.Afterarrivalat the passenger
co-operation with the airport operators and other agencies building, baggage has to be unloaded from vehicles and
concerned,
dual-channel
a system forthe
clearance containers and delivered to the baggage claim system or
inwards of passengers and their baggage. The system shall transferred to the departures areain the case of transit and
allowthe passengers tochoose between two types of transfer passengers. Sufficient space and height for easy
channels: manoeuvring of vehicles is required a n d also for storage
and removal of empty containers. Sufficient space is also
a) one channel (green) for passengers having with them required adjacentto eachbaggage delivery facility to
no goods or only goods which can be admitted free enablesimultaneous use of several or all such facilities.
Convenient connexion with outwards baggage sorting area according to thelevels of comfort considered appropriate,
and wide storageareasforeitheremptycontainers or and should take into account the average time spent in the
baggage should be provided. A one-way vehicle flow is area, climate and local custom.
desirabletoprovideunobstructed access for vehicles
arriving from aircraft. Delays in baggage handling often 9.6.3 Thecapacityrequired is
a functionofthe
occur at this point and delivery of baggage to the claim passenger rate of flow, the average period spent in the
area ata rate comparablewith the passenger flow is one of waiting areaandthefunctionscarriedon there. The
the most important elements of airport operation. capacity should be sufficient to absorb the difference in
flow rates between check-in and aircraft boarding. The
flow rate out of thewaiting area is determined by aircraft
Transfer baggage apron movement rates and aircraft operators'procedures.
The flow into the area may reflect influences from land
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
9.5.26 Passengerstransferring between international side ground transport systems. Each should be separately
flights should not have to claim their baggage until they assessed where either of these influences is dominant.
reach theirfinaldestination.The baggage of all such
passengers shouldbe identifiedin the baggage vehicle
unloading area and transferred directly to the departures Layout
baggage sorting area
for
integration with all other
departuresbaggage.Therouteand system oftransfer 9.6.4 To maintain the straightest possible flow routes,
should be as direct and fast as possible to enable baggage the waiting area shouldbe of the samegeneral length as the
to connect between flights with the least possible delay. departures concourse. Entrances should be provided for
Passengers transferringfrominternationaltodomestic each mainflow stream (where frontier controls are applied
flights are usually subject to customs inspection and their see also 9.7). For passengers proceeding directly to their
baggage is, therefore, treated as normal arrivals baggage aircraft, straight, clear routes, unobstructed by any other
and delivered to the baggage claim area. This also applies flows or functions, should lead directly from the entrance
to transit passengers on flights changing category. to the air side exits.
A I R SIDE EXITS
t-t-t-t-tj
A A A d
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
large. Passengers are attracted t o positions from which
there isa view of theapronandaircraft,and visual 9.7.2 The location of frontier controls and the stage in
continuity is difficult to achieve when distances become the passenger processing system at which they are applied
too great. Thus, if the distance from land side t o air side are
important in maintaining free
and
continuous
is toogreat,thelandsideofthearea will tend to be passengerflow(see F’igure 9-12). Controlsshouldbe
underused while the air side will be overcrowded and the located between the departures concourse and the air side
exit flow obstructed. For large passenger buildings, it is waiting area, as this is the point where the rate of flow is
particularly difficult to achieve a satisfactory compromise most regular. Controls located at theexit from the air side
because the space necessary for the number of passengers waiting area would be subject t o large surges and would
to be accommodated may make the distance from side land delay passenger flow to aircraft.
to air side greater than desirable. In such circumstances,
one solution which might be consideredis the provision of 9.7.3 Afterpassingcontrols,passengersmaynot re-
a balcony above the main waiting area.
enterthelandsideareasandaresegregatedfrom all
persons, other than staff authorized to enter .the air side
areas.Thecontrolsshouldbegroupedtogetheratone
location and should form the entry control to the air side
9.7 GOVERNMENT FRONTIER CONTROLS waiting area,therebyavoidinganyadditionalcontrol
positions which would be an irritation to passengers and
9.7.1 Departures frontier controls are contrary to the
a hindranceto flow and involve additionalspaceand
International Standards and Recommended Practices of
staff costs.
Annex 9. For States which still find it necessary t o retain
them, these controlsshouldbe executed atlocations
between the departure concourse and the air side waiting 9.7.4 The most frequentlyappliedgovernment exit
lounges.This section also includes preclearanceunder controls are immigration and police, but some States also
bilateralagreements between States which providefor imposecustomsinspection of passengers or their hand
arrivals inspections to be carriedoutattheairport of baggage. Such customs inspection should be before check-
departure. in, for baggage handling reasons.
4
OTHER GOVERNMENT CONTROLS IF REQUIRED
t-
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
I
PASSENGERS ONLY BEYOND THIS P d N f
of, the frontier control. A circulation route between the passengers. A faster over-all flow and some economy in
passport control and medical facilities should be provided the number of positions can beachieved if some positions
which is compatible with the main arrival flow. areallocatedforthe use only of thosecategories of
passengers whoaresubjectto minimal inspection.The
capacity of these positions would a5 a result be very high,
Immigration and Police allowing more positions to be allocated exclusively t o the
categories of passengers subject to more detailed inspec-
9.7.8Passportclearanceoften includes, or is associ- tionand which, therefore,have a slower rate of flow.
ated with, police inspection. Opening passports and other Where such arrangements are applied it is important that
documents,andsearchingfor visas andentrystamps the positions for each category are proportionatelyrelated
represents a considerable proportion of the total service to, and evenly dispersed among, the paralielflow streams.
time. It is, therefore, a helpin maintaining rapid passenger
flow to reduce the number of occasions on which this has
tobedone, for instancebyimmigrationand police Control Authorities’ Accommodation
officials inspecting documentstogether.Whereimmi-
grationand police controlcannotbeoperated with 9.7.10 Thecontrolauthorities usually requireoffices
simultaneous inspection, the controls should be arranged and search and interview rooms in conjunction with the
consecutively on the line of theairside/landside flow frontier
control
inspection points.
These should be
route. If the service rates are different it is preferable for restricted to those essential for passenger processing and
the inspection requiring thelongest time to be placed first. should be arranged on the flanks of the control position to
Thus delays at the second control will not cause obstruc- maintain the widest unobstructed area for the controls.
tion at the first control, and minimum distance may be This ensures flexibility forfuturerearrangementand
provided between the two controls. operational changes and the clearest, unobstructed flow
routes. Search and interview rooms will probably need to
9.7.9 Thestraightest flow routesareobtained when ensureabsolute privacy ofbothsoundand vision;in
the inspection positions areentirely homogeneous and any providing this it is most important that visual continuity
positioncan be used by any passenger. However, some throughthe passengerflow route is notobstructed.
States require varying degrees of inspection of documents, General administration, etc., should be located elsewhere
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
depending on the category of traffic and nationality of in the building (see Figures 9-1 3 and 9-14).
TO BAGGAGE CLAIM
IMMIGRA-
TlON AND
POLICE
OFFICES
INTERVIEW
IMMIGRATION CHECK ROOMS
+
I
HEALTH DOCUMENT INSPECTION AS REQUIRED
t t
ARRIVALS
FROM AIRCRAFT
t
Figure 9-13. Control authorities’ accommodation
CONNEXION FROM
PASSENGER BUILD!NG
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
b) Passenger processing area. Thenumberofagent 9.8.8 The system for moving passengers between the
positions is normallydetermined by theairport passenger building and the aircraftis an integral element in
authority in consultation with the user airlines and is the choice of the aircraft parking system and apron plan.
The most appropriatesystem will depend on the traffic for primaryfactorstobetakenintoaccount inpIanning
which the individual airport is provided and other local passenger loading bridges areaircraftdoor sill heights
conditions.
Themostimportantconsideration is to (which range from 2 to 5 m) and door positions. The size
maintainfreemovementofaircraft, vehicles and pass- and form ofpassenger loading bridges should be chosen to
engers while avoiding conflict between them. providesufficient flexibility to serve different types of
aircraftotherthanthoseindicated in thc. operational
9.8.9 A number of different systems can be used to forecast, and for resiting at new gate positions in accord-
connectthe passenger building totheaircraft. These ance with changes in apron plans.
include having passengers walk up boarding stairs or along
a passenger loading bridge, or conveying themin a 9.8.15 The capacity of the passenger loading bridge is
transporter.Theroutes maybe overtheopenapron, determined by using the same density and width criteria
through enclosed routes at or below apron level, or at applied t o aircraft stairs. For the best passenger flow the
passengerbuilding andaircraftfloor levels. Any speci- interiorwidthof passenger loading bridges should be
fically defined route over which passengers walk, other sufficient for at least two people to walk side by side so
than over an apron, is a “pier”. Thus a pier can be at, that children andthe aged orinfirmcanbesuitably
above or below apron level. assisted. Floor slopes should generally not exceed one in
ten.
9.8.10 For closest compatibility with the flow
principles, the choice should be determined inconsider- 9.8.16 The width oftheloadingbridgedoesnot
ation of thepassenger building floor levels: for multi-level usually constrain the flow as much as does that of the
passenger buildings the connexion between building and aircraft door, which generally ranges from 84 to 107 cm.
aircraft should keep to a minimum any changes in level, As with aircraft doors, another constraint on the flow rate
but because of the variety of aircraft floor heights it is could be the pointwhere the passenger loading bridge joins
impossible to define a single suitable level. the building. For example, a 90 cm wide doorway will
allow a flow rate of 37 passengers per minute. Another
Aircraft boarding stairs constraint on theflow rate of thepassenger loading bridge
is the aisle width of the aircraft cabin. Studiesin the United
9.8.1 1 Integral aircraft stairs are used with aircraft in States support the flow rate of 30 passengers per minute
the 50-120 seat capacity range, such as B727, B737, DC-9, identified inBoeing document D6A 10305-1, “SST
BAC111, CV580, and YS11B. Ground Services Time and Motion Study”.
9.8.12 Inthe case ofstairs, whether integral or 9.8.17 The passenger flow rate may
be
reduced
mobile, the width and relative density in terms of persons slightly if stairs rather than ramps must benegotiated.
per squaremetre serve asthe limiting constraintfor Stairs result in a 20 to 22 passenger per minute rate, similar
calculatingcapacity. Ascending or descending rates will to that of a mobiie passenger stair. The stairo r ramp may
not be significantly different in handbook references. Flow be provided with an enclosure for weather protection when
will be in one direction, enplaning or deplaning. a single-level connector is provided.
9.8.13 Passenger flow rate for aircraft in the 40-210 9.8.18 The passenger route should be
clear and
seat capacity range is approximately 20 to 22 persons per unambiguous and, if possible, should avoid multi-
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
minute, and 25 persons per minute for the 2.20-420 seat directional functions where the passenger loading bridge
capacity aircraft. In the lattercase, the rate of boardingor joins thebuilding. The passenger loading bridges should be
disembarking can be increased by the use of more than one arrangedtoleadarriving passengers, whomaynotbe
door, but this may create traffic conflicts on the apron familiar with the route, directly to the main flow routes
with the ground service equipment operation. into,the passenger building.
Passenger loading bridges 9.8.19 The type of passenger loading bridge - fixed
pedestal, apron drive, or suspended - and its length are
9.8.14 Passenger loading bridges can provide quicker, functions of variables including apron dimensions, wing
more even passenger flow between aircraft and passenger span,doorlocations, fixed aircraft services, adjacent
buildings and protect passengers from weather, noise and aircraft positions, and economics. For example, a certain
fumes.Theinstallation of passenger loading bridges, ramp drivebridge may extend up to35 m from the faceof
however, should be economically justified by traffic the building, and may be capable of servingfive or six
volumes andotherconsiderations (refer to 7.2). The different types of aircraft. In a practical application of the
passenger loading bridge, only two or three aircraft may 9.8.25 In general, although transporters afford almost
use the bridgebecauseof fixed service locationsand ideal flexibility from the apron planning point of view,
positions of adjacent aircraft.A pedestal-type bridge could they tend not to be compatible with the passenger flow
be more appropriatein that case, particularly inview of its principles. They may, however, be useful as a supplemen-
lower capital, operating and maintenance costs. tary system to handle peak hour denands only or to serve
aircraft which differ from the general types of aircraft for
9.8.20 A ramp drive bridge,
when in a stowed which the airport is planned.
position, will allow a taxi-out operation where the pedestal
or suspendedtypes are limited to pushoutoperations. Transporter loading and unloading positions
Judgements as to which passenger loading bridge design to
apply to each case will be based on the specific charac- 9.8.26 The specific form of transporter loading
teristics of
the
aircraft mix and airline
operating positionsdependsuponthetype of transporters to be
requirements. accommodated. Generally, the positions should be
consideredasaircraft gates andthesameplanning
9.8.21 Normally only one passenger loading bridge is considerationsapplied, except thattransporters will
required to serve any one aircraft up to and including the generallyoccupy theloadinggatesfor a muchshorter
B-747. This may,however, be affected by theairport periodthanaircraft occupy thestands.Therefore,the
involved and the typeof traffic using that airport (i.e. possible degree of trickle flow to the transporter loading
originating/ terminating or transit). For very high density positionsmaybe much less, andthetimespentinthe
routesoratairports where airlines requirefastturn- waiting area may be correspondingly short.
around, as well as for maintenance of approved standards
for business and first class passengers, installation of two 9.8.27 Loading positionsshould be as close as
passenger loading bridges maybepreferable. If two possible to the passenger building air side waiting area, to
passenger loading bridges are to be used, there should be reduce the walking distance and hence the time required
a separatetunneltothe terminal for eachbridge or, for passengers to get from the waiting area to the aircraft.
alternatively, a double width corridor from the junction of The specific location of the loading positions will usually
the two bridges to the terminal building. The minimum be determined by the air side vehicle traffic circulation and
width for this double corridor should be 3.2 m. the need toprovideunobstructed access between the
loadingpositionsandtheapronroads.Thenumberof
Transporters positions required depends upon theutilization of aircraft
stands, size of aircraft, etc.
9.8.22 Transporter vehicles may be used when aircraft
are parked remote from the terminal. Transporter types 9.8.28 As with aircraft gates, it is possible to use the
range from a bus in combination with stairs to a speci- transporter gate positions for both departures and arrivals,
fically designed vehicle with an elevating capability. but because the vehicle movement rate is higher than that
of aircraft at the aircraft stands and thus the movement
9.8.23 When buses are to be used to transport rate of passengers is also higher, it is advisable to separate
passengers between remote standsandthe
terminal, thedeparturesandarrivals flows and provide separate
consideration should be given to specially designed airport transporter
positionsfor
each.
Thisseparation
also
passenger buses. These vehicles should have a low floor permits the unloading positions to be located as close as
height (preferably one step above the ground), wide doors, possible tothearrivals flow routes in the passenger
and minimum seating around the sides of the cabin. The building, thus reducing walking distances.
capacity and dimensions of the bus should be in accord-
ance with the conditions prevailing at each airport where
I t will be used. IATA has developeda functional speci- Air Side Entrances
fication (AHM 950) on airport passenger buses, which is
also included in 1ATA’s “Airport Handling Manual”. 9.8.29 From piers or transporter unloading positions
passengersflow intothe passengerbuilding. Although
9.8.24 When a specifically designed vehicle with two-way flow of departuresandarrivals passengers is
elevating capability is used, special attentionshouldbe unavoidableandtolerable in piers, in no circumstances
paid to their relatively slow speeds, lack of easy manoeuvr- should arrivals flow routes pass through departures areas
ability and the potential hazard they may be to aircraft in the passenger building. The air side entrances should,
operations. Thesevehicles have high capital, operating and therefore, give access directly to the arrivals areas of the
maintenance costs and require highly skilled drivers. building.These may be on alower floor in multi-level
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
buildings or by the side of the departures areas in single in these circumstances transitpassengers may be subject io
level buildings. In multi-Ievel buildings the descent should frontier controls. Their requirements arethen the 5ame ;is
be direct, obvious and easy. transfer passengers and the same facilities can be used for
both.Transit passengers who arrive
anddepart
on
9.8.30 Passengers entering the building include transit international flights should never be subjected to frontier
and transfer passengers as well as passengers ending their controls and should remain in the air side area, where all
air journey. The air side entrances should be arranged to amenities which they may requireareprovided.On
separate passengers into the appropriate flow streams (see departure of their flight, they follow the normal routes and
Figure 9-15 ) . The entrances for each category should be proceduresofdeparture passengers,includingsecurity
arranged consecutively alongthe flow route SO that check, if required.
passengers do not have to choose from more than two
alternatives at any time. Confusion will arise if special Transfer Passengers
categories are not segregated from the main flow before
the first control point. Thus all arrivals passengers should 9.9.2 The flow route for transfer passengers depends
flow through a common route as far aspossible; when on whether the transfer is between flights of the same or
transfer and transit passengers are not subject to controls, different categories,
i.e. domestic to domestic,inter-
they should be diverted before the main route reaches the nationaltointernational, or between internationaland
frontier controls. domestic. When the traffic is between international and
domestic,transfer passengers are subject to the normal
arrivals controls and should follow the main arrivals route
to the land side, where they then pass through the main
9.9 TRANSITAND TRANSFERPASSENGERS departures flow route and follow the normal departures
procedures.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
requirements beyond those of arrivalsanddepartures waiting area,. usually following the same route as transit
passengers. Usually they should follow the main arrivals passengers (see Figure 9-16). Unlike transit passengers who
route, until being diverted directly into the departures air leave the airport on the same flight on which they arrive,
sidewaiting area or into a sterile “in-transit” waiting however, transfer passengers change flights, and it may be
lounge. However, some transitflights change category and necessary for them to check in for the connecting flight.
TO
FRONTIER FROM AIRCRAFT
CONTROLS
TO FRONTIER CONTROLS
0 D EPA R TU R ES
A I RS I D E
TRANSFER WAITING
AREA CHECK-IN
CONTROL
___)
0
TRANSIT
PASSENGERS
t AIRCRAFT
This can be undertaken either at the gate, if such facilities Passenger Amenities
are provided, or preferably on the route to the departures
waiting area. At airports servinga numberofairlines, 9.10.2
Amenitiesshouldbe sited toensurethat
some form of shared use of transfer check-in positions is passengers using them do not interfere with the primary
necessary t o avoidthe provision of facilities which are flow streams and they should not obstruct visual conti-
excessive and thus uneconomical, and which distort the nuity throughout the area. The location of amenities can
building plan. Nowadays many airlines provide boarding affecttherate of flow throughthebuilding,andthe
passes for on-line transfer at the originating station, so appropriate siting of the amenities relative to each other
that transfer passengers do not need to check in for the and the flow routes can be of considerable assistance in
connecting flight at the transfer station. distributing passengers throughout the whole of the
waiting area and in reducing circulation within the area.
9.9.4 For international flights at airports where there The nature of each amenity provides a general indication
is morethanoneinternational passenger building, a of the degree and type ofuse it will receive. For example,
passenger transfer system that operates on the air side is duty-free goods and liquor shops can with advantage be
desirable for thetransfer of passengers andbaggage adjacent to the main flow routes for easiest access by a
between international flights. Requirements for the vehicle large number of passengers and to provide fast service.
unloading and loading positions are the sameas for other
transporters, and the same positions canbe used for both. 9.10.3 Dependinguponthe size of the passenger
buildingandthecategoryoftraffic,thedepartures
concoursecan be theappropriatelocationforsome
passenger amenities. If they are also provided in the air
9.10 PASSENGER AMENITIES AND sidewaiting areatheremaybe a reduction in thetime
OTHER PASSENGER BUILDING SERVICES passengers remain in the departuresconcourse
and,
therefore, in the space required.
9.10.1 Airport master planning also includes consider-
ationof passenger amenities, concessions, andother 9.10.4 The greatest use of other amenities is generally
services usually located in the passenger building. made by passengers with the longest waitingperiods.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Passengers whose aircraft boarding is imminent tend to discussion as a distinct sub-element of the passenger
gravitate to those parts of the waiting areas nearest the building because the quantitative aspects involve more
exits. It is important, therefore, to site amenities so that than a simple relationship to annualenplanements or daily
the passengers who are likely to remain in the area for the passenger averages.
longest period are attracted away from the busiest areas
nearest the flow routes. These areas of least activity, which
aretheappropriate sites for passenger amenities, are 9.10.9 The basic service offered at the small airports
between the main flow routes and adjacentto the land side is a coffee shop, although a separate restaurant can be
boundary of the waiting areas. successful, depending on the surroundingcommunity.
Only very large airports can justify several locations for
snack bars, coffee shops, bar-lounges and restaurants.
9.10.5 The siting should also be related to service Requirements for more than one of each type are greatly
accesses for supplying goods, and storageareas. To influenced by the building concept involved, particularly
preserve flexibility and economy in the use of space, all for linear terminals at very large airports.
main storageareas should be located elsewhere inthe
building and only sufficient for immediate purposes
9.10.10 One approach to sizing involves “use factors”
should be provided in the waiting areas.
(average daily transactions divided by average daily
enplanements) and“turnovers” (average day users or
9.10.6 At some airports, planning efforts have transactions divided by thenumber of restaurantand
suffered because of conflicting views on priorities for the coffee shop seats available). Based on available data, the
location and size of revenue-producing services in relation following ranges can provide general approximations for
to basic airline services for passengers. One example food and beverage service operations:
involves inbound baggage or claim facilities that are
constrained by thelocation of concessions or another turnover rates: average daily 10 to 19 persons per
ancillary functions.The
resultant delays in baggage seat. Some operators appear satisfied averaging 10 to
delivery and display end up inconveniencing passengers, 14 daily;
and the by-product of such delays can often be congestion,
not only in the baggage claim area, but alsoin the adjacent space per seat: 3.3 to 3.7 mzper coffee shop/
circulation elements and at the curb. restaurant seat, including support space;
any specific airport must be based on discussions wiLh both Other Passenger Building Services
existing andpotentialoperators
and
concessionaires.
9.10.14
Passenger
building services also include
Representative guidelines are summarized as follows:
facilities common to mostpublic buildings andothers
common to many airports, regardltss of traffic volumes.
a) Newspapers/books and tobacco: physically separate
at most airports where annual enplanements exceed Such facilities include:
200 000 per year, and may be combined with other Public toilets:must be sized for buildingoccu-
services at airports with lesser traffic. Allow 14 m2 pancies in accordance with codes applicable to the
minimum,andaveraging 56 to 65 mz permillion local community, state, etc. Space allowances vary
annual enplanements. greatly,from 139 to 167 m2per 500 peak-hour
passengers (in and out) down to 120 m2 per million
b) Gift and apparel shops: some items are sold at the annual enplanements at large hub airports.
newsstand at smaller airports, but separate facilities
Airportmanagementoffices:spacerequirements
normally become viable when annual enplanements
exceed one million. Allow 56 to 65 m2 per million vary according to thesize of staff and the extent to
annual enplanements. which airport authority headquarters are locatedin
the terminal.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Information: public address, flight information, getting u p this gradient. One in twelve ramps are difficult
signs and graphics, courtesy phones, and security forotherthanthe strongest wheelchair users; one in
alarm system are included under this heading. sixteen is better. Difficulties can also be experienced if
ramps have to be approached from an angle. Curbs atsides
Government offices: these facilities may require a of ramps can be a problem, and the location of handrail
considerable amount of space,dependingupon supports and the finish of both ends of handrails need to
individual State practices. be carefully designed.
Contract service facilities and others. 9.11.5 The height generally accepted for ramp curbsis
10 cm, although 5 cm minimum seems to be more
Letter post. acceptable. Curb edges need to be rounded and the finish
at the top and bottom of the ramp carefully designed.
Stairs
9.11 CONSIDERATION OF DISABLED
AND ELDERLY PEOPLE IN PASSENGER 9.11.6 The termination of handrails at the topand
BUILDING PLANNING bottom of flights of stairs need to be individually designed
to suit the circumstances.
9.1 1 . I The speed andcomfort of air travel is
becoming more and moreappealing to people who are
physically handicapped and the use of air transport by
disabled and elderly people, including the chairbound, is
Terminal Approach and Departure Areas
likely to increase. For many,particularly the severely
disabled, the mostconvenientmethod of long-distance
travel is by air, provided the transition facilities match the Car parking
convenience of the aircraft.
9.1 1.7 It is desirable to provideidentified reserved
parking areasfor physically disabled people, using the
9.1 1.2 Both disabled and elderly passengers as well as access symbol. Directional signs shouldindicate access
visitors have rights to safety and convenience. It should be routes to reserved parking areas, which should be located
remembered that a person with a disability is not different close to the terminalentrance. Regulations should be
in allaspects of behaviour.Their special problems and enforced to ensure exclusive use of reserved parking spaces
differences need to be recognized so that the by the disabled.
planner/designer may accommodate them satisfactorily.
airport passenger buildings. The following .paragraphs should be within the limited reach and grasp of a disabled
include planningconsideration of disabled and elderly driver. Wheelchairs should be available for people to move
people in airport passenger buildings based on the totaxi, bus or private car loadingareas. This service
practices advocated by one State. should be clearly advertised.
External circulation
Planning Consideration for
Access by the Disabled 9.11.9 People using wheelchairs find ramps essential
to negotiate changes in level and these are helpful for the
Ramps ambulant disabled. Both ramps and stairsshouldbe
provided at every change in level. Ramps shouldnot
9.11.4 Unless the surface leading to a one in six ramp exceed one in twelve and should have non-slip surfaces.
is flat or sloping down, wheelchair users have difficulty Handrails should be provided at least to one side.
Internal Circulation
Elevaiors
9.11.14 All interior public spaces should be connected
by ramped paths or identified lifts, and public corridors 9.1 1.20 The only really effective way of moving
should be free of obstructions. All abrupt changes in floor chairbound people from floor to floor is by elevator.
level should be clearly identified by audioand visual Where elevators areprovided,at least one should be
means. accessible to and usable by the disabled, including those in
wheelchairs, both at the entrance level and at all upper
levelsusedby the public. The elevator should be large
Doors and doorways enough to accommodatea wheelchair andone or two
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
9.1 1.23 Directional signs androom identifiers are Telephones and post boxes
normally useless to blind people. It is desirable that
identification of certain rooms, e.g. rest rooms, res- 9.11.29 At least one in a group of telephones should
taurants and gatepositions by raised or depressed letters be be accessible by wheelchair users, with the handset and
placed on walls beside doors, not ondoors, as sudden coin slots approximately I m above floor level. Telephone
opening may result in injury. Audible andvisual signals to books should be located so they can be read from a seated
indicate a hazardous area, e.g. a door to an area used by position. Telephone operatinginstructions withraised
baggage trucks, are desirable to protect blind and deaf lettering is desirable. Post boxes should have an opening
people. Curbs, which serve as a warning to blind people which can be operated by one hand, not more than 1 m
using a cane, should be provided at any change from a above floor. Splayed legs should be avoided. Tables 71 cm
pedestrian area toa roadway for vehicles.Visual .and high with 71 cm between the legs are suitable.
audible passenger information is desirable.
Baggage storage
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
“Airport Terminals Reference Manual”, published by the “Airport Master Plans”, U.S. Federal Aviation Adminis-
International Air Transport Association. tration, AC 150/5070-6A, June1985.
“The Apron andTerminal Building, Planning Report”, “Airport Planning Manual”, Volumes 1 and 2, Depart-
U.S. Federal Aviation Administration, Report ment of Housing and Construction, Australia, 1985.
NO.FAA-RD 75-191, July 1975.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
1-115
f> the requirements of all-cargocarriers and combi- - provide adjustable or flexible connexions at air side
nation carriers vary widely. As more high capacity and landside t o accommodate fixed loading bridges,
aircraft are phased into route structures, the ratioof mobile ramp equipment and variable delivery/
air cargo carried in passenger aircraft to thatcarried collecting vehicle heights;
in cargo aircraft will also change.
- provide terminal building bypass means to transfer
10.2.4 As with passenger terminals, a single design unitized loads or large single pieces between air side
concept cannot meet the varying needs of all carriers or all and land side; and
geographical areas. There are, however, common guide-
lines that a cargo terminal planner should follow: - make adequateprovision for holding o r staging areas
for unitized loads, including cargo containers and
- collect all possible information related topast, lower deck containers, both of which have special-
present and future cargo traffic from
airline sources; ized handling requirements. In the case of lower deck
containers, particular attention should be paid to the
- determine the impact of cargo, mail and company necessity of ensuring that such facilities will enable
stores upon the facility; thecontainers tobe handledexpeditiously at all
times,
including
periods of unavoidable multi-
- determine the desired material handling system based operations, as it is essential to keep aircraft ground
upon the nature and volume of the forecast traffic times to a minimum.
and the operating method best suited to the parti-
cular locality;
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
storage areas; and
e) handling systems should be so designed as to obtain
d) at the larger airportsfor which this manual is the maximum utilization of equipment (e.g.
written, adequate provision should be made for the maximum standardization in methodsand in the
handling of large containersand pallets between types and sizes of equipment, maximum flexibility in
trucks and cargoterminals, and between cargo the use of equipment, minimum turnaround times of
terminals and aircraft. mobile equipment);
The schematic in Figure 10-1 is abroad depiction of f) infrequently used equipment should be as inex-
principles for achieving a continuous and direct flow of air pensive as possible;
cargo within the cargo terminal.
g) it is economically best if cargo in movement can, as
faras possible, continue in movement without
10.4.3 In planning air cargo facilities, two types of interruption; and
flow should be considered, namely, the flow of documents
and the flow of cargo itself. The means by which the flow h) the design of storage systems should besuch that
of documentation will move between the processing and maximum utilization of space is accomplished,
administrative areas of the cargo terminal will have an measured in terms of cubic content, together with
effect upon the ultimate building design selected. The basic ease of selection with the minimum effort.
6-
PASSENGER CARGO CARGO PASSENGER
AlRCRAFT
EXPORT OUTPUT
0 AIRCRAFT
EXPORT OUTPUT
DIRECT TRANSFER -C
INPUT
IMPORT
INPUT
AIRCRAFT
lMPORT
i) AIRCRAFT 9
I .
----_------- ---------------- ------------- 1
I
I
I
PRE DISPATCH PRE CHECK-IN
I STAGING AREA HOLD AREA
I
I
I
I
I
I
ASSEMBLY
PASSENGER
AIRCRAFT
I0I FLIGHT
ASSEMBLY
CARGO AIRCRAFT
I CARGO SORTING
ANDCHECK-IN
I1
I t
I 4 7
r
I
ONLINE *
I
I
PRE FiiGHT ASSEMBLY
LINE-UP -0 IN BONO
*
I
I
AND HOLD AREA 0 CACHOGNONETXdZE
FLIGHT ASSEMBLY
STORAGE
I
I
I
4
4 -
I CUSTOMS
WEIGH,MEASURE
I EXAMINATION
AND
I
& LABLE
CLEARANCE
I 0
I
I
'I T i
I
I
1 I 1 1I 1
I - -
I
INSPECT,COUNT,
I PRE DELIVERY
IDENTIFY TO OTHERS HOLD AREA
I HOLD AREA
I
I A
':i;k!h;
HOLD AREA
0 C:EARED BOND D/
I
I
I
I I b t I
EMERGENCY I
I ORIGINATING
I
I
CARGO
RECElVlNG
0 iNTiRLlNE
RECEIVING 0 INTERLINE *
DELIVERY 0 DOMESTlC
DELIVERY
0 CLEARED BOND
DELIVERY
0 SHIPMENT
IMMEDIATE 0 ;
CLEARANCE
I
____ __ - _ _ _ _ + _ _ _ _ _ _ _ _ _ +_ _ _ _ _ _ _ _ _ _ _ _f _ _ _ _ J
I
-
!-'_ 9 - - - - - _ - _ _ --j ---+ _ _ _ _ _ '
I 1
1
EXPORT tNPUT 101
I I
I IMPORT OUTPUT 101
KEY TO SYMBOLS
El
An operation occurs when a unit of cargo is lifted up or put down or moved during a process. Marking and labelling is
OPERATION 0 considered an "operation". An "operation" also occurs when
information
given
is or received
when
or planning or
calculating takes place (e.9. input or extraction of information from/to electronic data processing systems).
DELAY
0 A delay occurs to a unit of cargo when it is prevented from progressing to its next planned activity
According to local circumstances, this may apply to alr side, land side or both
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
=
Part I . Master Planning 1-1I9
10.4.6 Thereare two principal factors which will 10.5.3 Any cargo processingfacilitymustbe capable
govern the actual space required in the cargo terminal and of supporting thefollowing activities relativeto export and
the layout of thisspace. One is the rate of flow,which will import functions:
depend upon the handlingsystem employed and the cargo-
carrying capability of passenger and all-cargo aircraft, as export (outbound) - acceptance
well asfrequencyof services. Theother relates tothe staging
future storage requirements in the cargo terminal, which load makeup
will depend largely upon the proceduresused by airlines in
preparinggoodsforshipmentand delivery, and on the import (inbound) - load breakdown
implementation of new procedures as the volume of air storage
cargo increases. delivery
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Multiple Occupancy Cargo Building the apron in line with intended expansions of the cargo
terminal, and to accommodate increases in aircraft size or
10.5.6 Airport master planning frequently requires changes in characteristics.
that a cargo building be developed which can accommo-
datea number of users. In planning such a building, 10.6.3 Eachapron layout and associated handling
detailed consideration should be given to
potential system analysis should include the following elements:
expansion of each individual user’s space and operation.
Such expansion may be handled by locating the largest a) types of aircraft shown on forecast;
cargooperatorattheend of the building so that its
operation can be expanded without disrupting the other b) airline requirements as to ground time;
tenants, constructing the building so that internal walls can
be relocated to allow one tenant to expand into adjacent c) airline emphasis on schedule departure time;
space, and locating truck docks so that all tenants have
access to land side transportation. d) airline consideration as to capital cost (equipment)
vs. labour cost (workforce);
10.5.7 A mere summing up of individual airlines’
space requirements and provision of a building to meet the e) labour resources available for operational purposes;
total demand will not be an acceptable solution.The and
building must be shaped so that individual users’
requirements are met in accordance with the principles laid f) land resources available.
down previously. In particular, the adoption of a common
depth building is known to produce great difficulties
caused by excessive distortion of the smaller terminal
units.
10.7 CARGO FACILITY REQUIREMENTS
10.5.8Whenuser agreements or leases are entered
into particular attention should be given to the ability of 10.7.1 As a guide to basic facility requirements in
the
airport
operator to relocate users to allow for cargoterminals,the following requirements should be
expansion of the other building tenants. taken into consideration:
-storage space for human remains; a) adequacy of the road system to cope at peak periods
with the volume of pick-up and delivery vehicles, in
- accommodation and specially designed holding areas addition to othertraffic.A truck access road,
for animals and livestock (specific details regarding separate
from passenger vehicle roads may be
construction of facilities and other requirements are necessary when air cargo volumes are expected to be
contained in the IATA “Live Animals Manual”); heavy;
- parking and storage space for loading vehicles and b) requirement for roadways to have sufficient bearing
other equipment; strength and height clearance to handle existing and
projected cargo-carrying road vehicles, including
- public reception counters; container transporters;
d) at existing aerodromes, special consideration of any and according to the type of vehicle used, and this
new clearance requirements which may result from factor will require careful evaluation at each airport.
the introduction of high capacity aircraft. In all cases, however, the depth provided should be
at least 30 m.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
11.1 ABOUT THIS CHAPTER 1 1.3.2 To calculate vehicular traffic and its required
facilities, the Design Year/Average Day/PeakMonth/
11.1.1 Thischapter deals with the planning of that Peak Hour forecasts (including base year data) based on
element of the airportnecessary for the accommodationof information developed in Chapter 3, will provide the
ground transport of passengers, baggage and employees volumes of passengers. The specific information necessary
to, from, and within the airport. Cargo movement and to transform the passenger forecast traffic volumes into
handling has been treated separately in Chapter 10. volumes of vehicular traffic includes:
1-123
the terminal, and, after aircraft departure, return to short- 11.6 VEHICLE PARKING
term parking and exit the airport. Taxis and private cars
may have to make recirculation trips if they miss terminal
entrances or exits. Planning Principles
11.6.1
Vehicle parking should be considered in
relation to the area it serves rather than any particular
11.4 INTERNAL AIRPORT ROADWAY category of traffic, although theprinciple of separation of
CIRCULATION functionsoften leads tothe vehicles associated with a
particular areaalso being of a specific category, e.g.
11.4.1 Atthe larger airportsto which this manual passenger cars, cargo vehicles, etc. Two basic principles
applies it may be desirable to separate service vehicles and should govern the provision of vehicle parking: it should
trucks fromthe passenger and visitor vehicular traffic, be located as close as possible tothearea served and
either before or shortly after entering the airport property. should, other things being equal, occupy the least possible
This can be accomplished by three types of roadway ground area. The smaller the ground area the closer all
systems: parts of it will be to the functional area.This is particularly
important when pedestrian movement between the vehicle
1) the principal public airport road for use by pass- parking andfunctionalarea is necessary, but it is also
engers, visitors and employees; important in reducing vehicle movements, and thus road
requirements, and speeding up service times. These
2) public service roads with security control points objectives can be achieved by developing multi-level car
permitting access only to authorized vehicles (e.g. air parking.
cargo delivery, flight kitchen supply, etc.); and
11.6.2 With the aim of locating vehicle parking as
3) non-public service roads with security control points close as possible to the various functionalareas, an
for use by authorized vehicles such as maintenance, analysis should be made of the types and numbers of
fire and rescue, fuel, etc. vehicles generated by each area.The extreme physical
characteristics of some vehicles may prohibit them from
The public road system accommodating servicevehicles using multi-purpose or multi-level parking facilities, and in
needs to connect with the terminal only for delivery of these cases separate provision should be made for them.
goods at designated locations. The non-public service road The cost-effectiveness of structures necessary for multi-
system accommodating vehicles serving the aircraft parked purpose use should be the determining factor in the siting
on the terminal apron needs to be completely secured from and use of vehicle parking.It will, however, often be
the public road system. found best to locate buses, coaches, taxis on the lower
levels and private cars on upper levels. Adequate access to
11-4.2 Through the use of surveys, traffic volumes by curbs should be provided. Parking can often be sited to
vehicle type can be determined for peak hours on specific provide simultaneous access and exits from several points
roadway segments as well as at points of entry and exit. while maintaining segregation between categories of
The number of traffic ianes required can be estimated traffic.
from this basic information.
Location
11.5 PASSENGER BUILDING CURB 11.6.3 The location and use of vehicle parking should
normally be determined by the vehicle parking period. As
The passenger building curb space requirements are the parking period increases consideration should be given
an important part of the aerodrome complex. The to locating the parking at more remote positions, such as
main features of this element of theaerodrome are on the airport perimeter. This is especially relevant in the
vehicular traffic lanes, through lanes, bypass lanes, case of staff car parking, although short-term parking for
curb/manoeuvring lanes, sidewalk platform directional staff cars should be provided in operational areas for those
and identification signs, curb-side baggage check-in points staff for whom a vehicle is essential in carrying out their
and pedestrian crossings. Additional planning information duties. Simiiarly, passenger cars and buses, which remain
with respect to curb-side dimensioning may be found in only for the period necessary to deliver or collect pass-
9.3.3 through 9.3.14. engers, should be parked as close as possible to passenger
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
buildings. Short-termparkingfor passenger vehiclesis returnthe passenger’s car is transferred back to the
required in the passenger area for drivers meeting arriving passenger building by thecarpark management and
passengers, as well as for many of the wellwishers handed over to the passenger at the land side vehicle pick-
accompanying departing travellers. The appropriate up positions. An alternative is for passengers to park
parking period for these vehicles may vary according to and collect their cars at the remote car park and to be
local conditions and theclimate, which may affect aircraft transported between it and the passenger hilding by a
arrival times. A period of 30 minutes has often been found shuttle service operated by the car park management.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
INTRODUCTORY NOTES
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
1-126
Buildings fora variety of operational purposes are Facilities should be provided to staff and passengers for
required at an airport. These include accommodation for treatment of medical emergencies (first aid), for aircrew
meteorological, air trafficcontrol, communications, medical inspection and for emergencies and rescue. The
rescue andfire fighting services, fuel depotand all the scale of facilities and their purpose should determine the
facilities for
administration
and maintenance, staff, location, which, however, should be chosen whenever
aircraftoperators, general aviation facilities and police. possible within walking distance of the passenger area(s).
Sometimes there is an hotel. Facilities should be strategically located for easy accessi-
bility in case of an aircraft accident and be capable of
expansion to serve on short notice as an enlarged aircraft
accident first-aid receiving station.The usefulness and
efficiency of any medical emergency and rescue organiz-
12.2 ADMINISTRATION AND ation on an airport may be greatly enhanced if itis in
MAINTENANCE BUILDINGS continuous use dealing with day-to-day medical activities
during the normal routine working of the airport.
12.2.1 Only functions which are essential for day-by-
day operations should be accommodated in passenger and
cargoareas, as their space is limited, and their size
becomes unnecessarily and disadvantageously large if they 12.4 GROUND VEHICLE FUEL STATIONS
are used to accommodate functions and staffwhich can be
located atmoreremote positions. A separateareafor A fuel station for land side ground vehicles can be a good
administrationand miscellaneous purposes should be source of revenue for an airport authority and maybe
provided; this can frequently be on the perimeter of the necessary where fuelling facilities are not closely available
airport or incorporated with the maintenance areas. Such on the main public routes from the airport. It should be
areasas these, which employ large numbers of staff, sited where traffic entering and leaving it would not cross
should be located as close as possible to primary public or slow down the fast continuous flow of other traffic on
transport facilities and should have good access to the the main vehicle routes. A separatestation for airport
operational areas. vehicles may also be justified.
1-127
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
13.1 ABOUT THIS CHAPTER preclude their improvement, or construction of new roads
or railways. Thus the options are largely a question of
The handling of fuel at airports is an importantsubject to economy and require a careful cost/benefit analysis.
be takenintoaccount when planningairport facilities,
since special requirements have to be met with regard to:
13.2.1 Storage
capacity requirements
must be 13.4 FUELLING OF AIRCRAFT
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
1-131
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
other vehicles, and aircraft. Whena truck is empty, it must
return to the storage area for refuelling before it can be valves shouldbe established in consultation with the
used again. Thus extra trucks must be provided for use airlines,asthenumberofhydrantsrequired per gate
duringthetime when othertrucksare being reloaded. position will depend not only on the type of aircraft but
When refuelling trucks are not inuse, parking space must also on the number of grades offuel required (each grade
be provided for these vehicles. of fuel requires a separate hydrant).
- Fuel piping shall not run under buildings or pass- - Fuel-resistant pavements should be used on aprons
enger loading fingers (excluding movable loading wherever refuelling operations or engine shut-downs
bridges)exceptwhen run in buried steel casings are likely to take place regularly.
enclosing only the fuel piping.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
is desired to achieve. They should be implemented in such be a sufficient distance from the aircraft boarding areaso
a way as will cause a minimum of interference with, or as to permit adequate time for security procedures to be
delayto, passengers, crew, baggage, cargo and mail. It initiated in the event of asecurityalert.The Security
should be recognized that the airport design is relatively Manual f o r Safeguarding Civil Aviation Against Acts of
inflexible once the structures are completed and should the Unlawful Interference describes the basic plansforthe
security requirements become greater in the future, it may inspection/screening of passengers at gates, hold areas and
be difficult, if not impossible, to modify the buildings and concourses, and sets out the advantages and disadvantages
structures at a reasonable cost. of each. A room or other facility should be provided in
close proximity to each inspection/screening point where
14.1.4 Concurrently with determiningthe level of manual or other special search of persons may be carried
security to be provided, there is a need to define the areas out in privacy.
on the airport to be protected. As a minimum, this would
include the airside, but at some airports, protection of the 14.2.4 Regardless of theplan selected it is essential
entireairportpropertymay need to beconsidered.In that the design provide for:
addition, other functionsvital to air navigation which may
not be located on the air side, such as air traffic services, a) the physical separation of persons who have been
radio navigation aids, petroleum storage areas, water and subjected to inspection/screening from others at the
electrical power supplies, will also need t o be protected. airport; and
1-134
b) the prevention of unauthorized access from land side Baggage Handling Facilities
o r air side to passenger waiting (sterile) areas in
which passengers are waiting after they have been 14.2.9 Adequate space will be required to enable the
inspected/screened and prior toboarding an aircraft. airline operator toestablish procedures t o ensure that only
checked baggage for which a passenger is on board will be
allowed to be transported on the aircraft. The exception to
VIP Lounges this would be if the airline operator has authority forsome
other
formof security control for unaccompanied
14.2.5 VIP lounges should be so designed that they do baggage, such as X-rays.
not permit unauthorized land sidelair side access. Persons
boardinganaircraftfrom a VIP lounge shouldbe 14.2.10 Anotherfeature which should be considered
subjected to the passenger and cabin baggage inspection/ in terminal design in relation to baggage handling is'the
screening process. ability to control access from land side to air side through
the baggage conveyor system. If direct access is possible,
a method of locking or otherwise controlling the access
areas should be provided.
Visitors' Observation Areas
14.2.11 Many States have prohibited the use of off-
14.2.6Consideration may need t o be given tothe airport check-in or curb-side baggage check-in. Terminals
desirability of providing observation areas for thepublic to should be designed in such a way that checked baggage can
overlook aprons. If observation areas are tobe provided, be handledin the normal fashion if it is necessary to
consideration should be given t o enclosing them with glass prohibit off-airport or curb-side check-in.
or providing for surveillance by security guards. In cases
where persons in the observation area would be able to
passmaterial t o departing passengers, the observation
areashould be made sterile by subjectingeveryone to Storage of Mishandled/Misrouted Baggage
inspection/screening prior to being permitted access.
14.2.12 Consideration will need to be given to
providing a secure storage area in the passenger terminal
building where mishandled baggage may be stored until
Airport Emergency Operations/Security
Services Centre forwarded, claimed or disposed of.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
14.3 AIR SIDE SECURITY points should be kept to a minimum and equipped so that
they can be securely closed should conditions require it. If
a gate is used frequently, a security guard will be required,
Location of Operational Areas together with a shelter for protection against the elements.
The shelter shouldbe designed in sucha way so as to
14.3.1 Security ofoperationalareas, where aircraft permit maximum visibility over the immediate area of the
may be present, will be materially advanced by the physical gate and to provide easy access for the guard to carry out
separation of runways, taxiways and aprons from public the duties of inspecting vehicles and their contents. When
areas. In any case, separation should be ensured between night use is anticipated,theareasurroundingthegate
public and operational areas, although the extensive area shouldbeilluminated. Discreet communicationsshould
required for the latter and the need for public access to beprovided between the security postandtheairport
passenger terminal buildings makesthisdifficult. to security services office as well as a discreet and audible
achieve. No precise distances can be given but the greater alarm by which assistance may be summoned in the event
the separation, thehigher the level of security. A particular of emergency.Securityof anairport will requirethat
problemmay berunwaysand taxiways which overpass underground service ducts, sewers andotherstructures
public roads. Where such overpasses are planned, special which provide access to the airside or other restricted area
measures may be needed to restrict access to runways or bebarred. If access to thesefacilities is requiredfor
taxiways at this point and to counteract the possibility of maintenancepurposes, locked doors or gates should be
sabotage to the structure of the bridge. Other potential provided.
dangerareasaretheapproachanddeparturepaths
to runwayswhere aircraft fly at low altitude. If it is 14.3.5 Buildings may be used as a part of the physical
considered necessary to protecttheseareas, it will be barrier
andincorporated in the fenceline provided
expedient to extend theairportboundariesduringthe measures are taken
to restrict unauthorized passage
initial design of the airport to include them in the land through the buildings. Care should also be takento ensure
acquired as airport property. that the roofs of the buildings do not provide a possible
route
for
unauthorized access to theair side. For
14.3.2 To adequately protect air operation areas from additional security,flood-lighting of the perimeter fencing
unauthorized access, it is important to consider physical and/ortheinstallation of analarm system maybe
securitymeasuresincludingfencing or otherbarriers, considered.
lighting,locks, alarms, guards and guard houses in the
planning process of air side facilities.
Isolated Parking Position
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Security Parking Area planned so asto avoid aprons used by commercial air
transport aircraft.
14.3.8 In addition to the isolated parking position,
consideration may need to be given to the provision of an
aircraft stand where an aircraft likely to be the object of Explosives Holding Area
an act of unlawful interference may be parked until it is
required or for the loading and unloading of passengers. 14.3.11 A holding area should be provided for any
The objective in the selection and design of this area is to suspicious articles found on the airport or on an aircraft.
eliminate the possibility of persons physically reaching or It should be located in a remote area, andin order to allow
being able to launch an attack against the aircraft. bomb disposal experts to deal with any devices, the
provision of a shelter, bunker or building is recommended.
This should be constructed in such a way that vehicles used
General Aviation Parking Area totransport explosive devices can be driven inside for
unloading.
14.3.9 It is advisable to designate a parking area for
general aviation aircraftseparatefromthat used by References
commercial air transport aircraft. This practice safeguards
against the possible use of a general aviation aircraft as a Annex 17 - Security - Safeguarding International Civil
means of circumventing security control at the airport. Aviation Against Acts of Unlawful Interference.
14.3.10 Taxiways to such general aviation parking Security Manual for Safeguarding Civil Aviation Against
areas should be identified and should, where possible, be Acts of Unlawful Interference (Doc 8973 (Restricted)).
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Terms which are defined in the ICAO Lexicon (Doc 9294) Baggage sorting area. Space in which departures
and theAnnexes are used in accordance with the meanings baggage is sorted into flight loads.
and usages given therein. A wide variety of terms is in use
throughout theworld t o describe facilities, proceduresand Baggage storage area. Space in which baggage is stored
concepts for airport operations and planning. As far as pending transport to aircraft.
possible the terms used in this document are those which
have the widest international use.
Cargo area. All the groundspace and facilities provided
for cargohandling. It includes aprons, cargobuildings and
Administration area. All the groundspace and faciIities warehouses, vehicle parks and roads.
provided for administration and management purposes of
airport management, aircraft operators
andairport Cargo building. A building through which cargo passes
tenants. It may include control tower, estate maintenance between air and ground transport andin which processing
facilities, contractors’depots, vehicle parks,staffand facilities are located.
aircraft catering, etc.
Cargo warehouse. A building in which cargo is stored
Aircraft maintenance area. All the ground space and pending transfer to air or ground transport.
facilities provided foraircraft maintenance. It includes
aprons, hangars, buildings and workshops, vehicle parks Check-in. The process of reportingtoanaircraft
and roads associated therewith. operator for acceptance on a particular flight.
Aircraft stand. A designated area on an apronintended Check-in concourse. The space between the passenger
to be used for parking an aircraft. building land side entrance and the check-in positions.
Air side. The movement area of an airport, adjacent Check-in position. The location of facilities at which
terrain and buildings or portions thereof, access to which check-in is carried out.
is controlled.
Air side waiting area. Space between thedepartures Departure concourse. The space between the check-in
concourse and air side exits from the passenger building. positions and the air side waiting area.
i-139
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
immigrationcontrol. The immigration and/or police Transport link. Any form of transport system provided
inspection of arrivals passengers. exclusively for operation between an airportandurban
population centres.
Land side. That area of an airport and buildings to
which the non-travelling public has free access. Transporter. Anyvehicleused io convey passengers
between aircraft and passenger buildings.
Movement area. That part of an airport to be used for
take-off and landing of aircraftandforthesurface
movement of aircraft. Terms Related to Airport Capacity
Obstacle. All fixed (whether temporary or permanent) Aircraft traffic demand (at an airport) (for a particular
and mobile objects, or parts thereof, thatare located on an hour). The sum of:
area intended for the surfacemovement of aircraft or that
extend above a defined surface intended to protect aircraft a) the number of aircraft desiring to land at the airport
in flight. during that hour plus
Off-airport processing facilities. A passenger or cargo b) the number of aircraft desiring to depart from the
transport link terminal at an urban population centre at aerodrome during that hour.
which processing facilities are provided.
Busy hour aircraft traffic demand (at an airport). The
Passenger amenities. Facilities provided for passengers aircraft traffic demand which is reached, or exceeded, in
which are not essential for passenger processing. the forty (or thirty)most active hours of the year, averaged
over two consecutive hours.
Passenger area. All theground space and facilities
provided for passenger processing, including aprons, Current movement rate (for a particular hour). The sum
passenger buildings, vehicle parks and roads. of:
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Passenger building. A building through which a) the number of aircraft which land during that hour
passengers pass between air and ground transport and in plus
which processing facilities and amenities are located.
b) the number of aircraft which depart during that
Passenger loading bridge. A mechanically operated, hour.
adjustable rampto provide direct passenger access between
aircraft and buildings. Hourly airport capacity. ,The maximum number of
aircraft operations that can take place in an hour. Once it
Passenger processing. The reception andcontrol of is estimated that the hourly airport capacity will be reached
passengers during their transfer between air and ground in the near future, prompt and careful investigation of the
transport. terminal area capacity is required to determine whether the
delays are due to runway congestion, airspace conflicts,
Passport control. The immigration and/or police ATC facilities, or a combination of these andother
inspection or departures passengers. factors, and what remedial action is needed.
Pier. A corridor at, above or below ground level to Peak aircraft traffic demand (at an airport). The
connect aircraft stands to a passenger building. aircraft traffic demand which will be reached in the most
active hour, averaged over two consecutive hours.
Port health control. The medical inspection of docu-
ments and/or passengers, baggage, cargo. Saturation of an airport. Reached when theaircraft
traffic demand equals, or exceeds, the corresponding
Transferpassengerdbagguge.Passengers making direct airport capacity.
connexions between two different flights.
Note.- The terms “demand” and “,,pOcity” refer
Transit passengers. Passengers departing from an to a single airport or acomplexofairports serving a
airport on the same flight as that on which they arrived. particular community.
Service rate. The maximum aircraft movement rate Sustainable capacity (of an airport). The highest
which could be reached at an airport with: movement rate which could be continuously maintained
for three hours or more under defined conditions.
a) the mix of aircraft andof take-offs and landings for
the conditions being analysed, and Theoretical airport capacity. The maximum movement
rate which could be reached with the mix 01 aircraft and
b) thedistribution of service times between aircraft of take-offs andlandings under defined conditionsfor that
movements typical of the aircraft traffic demand at airport, minimum separation being maintained between all
which saturation occurs. aircraft.
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
Volume I1 - Aircraft Engine Emissions Part 2 - Land Use and Environmental Control
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
training.
Systems (SMGCS) (Doc 9476)
Part 2 - Pavement Surface Conditions
Provides information on the provision of guidance to,
Describes methods for clearing contaminants and debris and controlin question of,all aircraft, ground vehicles and
from the movement area, snow removal techniques and personnel on the movement area of an aerodrome.
how to measure and report runway braking action onwet
and snow or ice-covered surfaces. Security Manual for Safeguarding Civil Aviation Against
Acts of Unlawful Interference (Ddc 8973 (Restricted))
Part 3 - Bird Control and Reduction
recent years. In response to agrowing need for such Volume 1 of the Lexicon brings together a number of
signing a set of signs was approved by the Air Transport terms, in English, French, Russian and Spanish, which are
Committee and the Council and are contained in Section relevant to the work of ICAO.
I of this document. Section I1 of the document contains In addition to strictly aeronautical terminology related
certain information concerning the use of the signs, their to aircraft and their operation, the vocabulary presented
!ocation, and colours to be used. thereinextendstovarious allied fields to which an
important part of ICAO’s work is devoted,particularly
meteorology and telecommunications.
Miscellaneous Publications The Appendices in Volume I contain lists of abbrevi-
ations and data on variousscientific and technical subjects
E40 Lexicon (Doc 9294) connected with aviation.
Volume 11 contains a list of definitions, most of which
Volume I: Vocabulary are from the Convention on International Civil Aviation
andthe Annexes thereto, while othersarefromthe
Volume 11: Definitions Procedures for Air Navigation Services.
- END -
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---
The following summary gives the status, and also regarded as not yet having attained a sufficient degree
describes in general terms the contents of the various of maturity for adoptiona5 International Standardsand
series of technical publications issued by the Inter- Recommended Practices, as well as material of a q a r e
national Civil Aviation Organization. Itdoes not permanent character which is considered too detailed
include specialized publications that do not fall spcifi- for incorporation in an Annex, or is susceptible to
ca!ly within one of the series, such as the Aeronautical frequent amendment, for which the processes of the
Chart Catalogue or the Meteorological Tables for Convention would be too cumbersome.
International Air Navigation.
Regional Supplementary Procedures (SUPPS) have a
International Standardsand Recommended Prac- status similar to thatof PANS in that they we approved
tices are adopted by the Council in accordance with by the Council, but only for application in the respective
Articles 54, 37 and 90 of the Convention on Inter- regions. They are prepared in consolidated form, since
national Civil Aviation and are designated, for certain of the procedures apply to overlapping regions
convenience, as Annexes to the Convention. The or are common to two or more regions.
uniform application by Contracting States of the speci-
fications contained in theInternationalStandards is
recognized as necessary for the safety or regularity of
internationalair navigation while the uniform appli- Thefollowing publications are prepared by aufhority
cation of the specifications in the Recommended of the Secretary General in accordance with the
Practices is regarded as desirable in the interest of principles and policies approved by the Council.
safety, regularity or efficiency of international air
navigation. Knowledge of any differences between the Technical Manuals provide guidance and infor-
national regulations or practices of a State and those mation in amplification of the International Standards,
established by an International Standard is essential to Recommended Practices and PANS, the implemeo-
the safety or regularity of international air navigation. tation of which they are designed to facilitate.
In the event of non-compliance with an International
Standard,aStatehas, in fact, an obligation, under Air Navigation Plans detail requirements for Pacili-
Article 38 of the Convention, to notify the Council of ties and services for international air navigqtion in the
any differences. Knowledge of differences from respective ICAO Air Navigation Regions. They are
Recommended Practices may also be important for the prepared on the authority of the Secretary General on
safety of air navigation and, although the Convention the basis of recommendations of regional air navigatiqn
does not impose any obligation with regard thereto, the meetings and of the Council action thereon. The plans
Council has invited Contracting States to notify such are amended periodically to reflect changes in require-
differences in addition to those relating to International ments andin the status of implementation of the
Standards. recommended facilities and services.
Procedures for Air Navigation Services (PANS) are LCAO Circulars make available specialized infor-
approved by the Council for world-wide application. mation of interest to Contracting States. This includes
They contain, for the most part, operating procedures studies on technical subjects.
I C A O 9 3 8 4 PART*kL X* 4 8 4 L 4 L b 0058662 0 5 2
PRICE: U.S.$15.75
(or equivalent in other currencies)
0ICAO 1987
1187,EIPII~OOO;
3/92, EIPZ1000
--```,,,`,,`,,`,,``,,````,,`,,-`-`,,`,,`,`,,`---