Professional Documents
Culture Documents
Variable Nonlinear Tie-Line Frequency Bias For Interconnected Systems Control
Variable Nonlinear Tie-Line Frequency Bias For Interconnected Systems Control
3, August 1988
Authorized licensed use limited to: AMRITA VISHWA VIDYAPEETHAM AMRITA SCHOOL OF ENGINEERING. Downloaded on August 17,2023 at 08:22:20 UTC from IEEE Xplore. Restrictions apply.
1245
Bfs. as used by most control areas. is a fixed, linear value for an external imbalance, the response would be to 1 and
s e t in t h e AGC t h a t remains t h e same throughout remain a t 1 until the external system corrects frequency back
the year. On the other hand, B,, is a variable and non-linear t o 0. A reduction in AGC movement should not only improve
value which is continuously calculated and used in the AGC. the ACE performance but should also reduce generator and
B,, is modeled to match SRC through monitoring the system tie-line regulation.
load and on-line generation.
The SRC varies with t h e amount of synchronized genera-
As Stated above, the tie-line frequency bias curve is a tion and with t h e load level. If B is too large or small, the result
control parameter which simulates the control area's SRC in will be excess regulation under normal conditions. For exam-
the control loop. Any tie-line frequency deviation point on the ple, if B is too small the AGC will tend t o drive frequency
tie-line frequency bias curve will result in no control action, deviations larger and tie-line deviations smaller than t h a t re-
while for a point above the curve the AGC will reduce genera- sulting from the SRC. If B is too large t h e AGC will tend t o
tion and for a point below the curve the AGC will increase drive frequency deviations smaller and tie-line deviations larg-
generation. A properly set B will match the SRC so t h a t a er than that resulting from the SRC.
system will not control t o correct load-generation imbalances
in external systems. It will simply allow its actual net inter- Figure 1 shows t h a t control t o B,, allows full governor
change t o deviate from the scheduled amount until the exter- response to take place for major frequency deviations beyond
nal system corrects its imbalance. points F1 and F2. while control to Bf, can limit governor re-
sponse beyond these points and actually cause additional fre-
The control improvement t h a t is possible by using B,, quency deviations. This aspect of B,, is important t o
instead of Bfs is shown graphically by the analysis in Fig. 1. interconnected systems reliability because it tends t o dampen
The SRC of control area A is a time variable curve comprised of wide frequency excursions.
load response and generator response to frequency deviation,
including a distributed generator deadband. The SRC of the Even though the SRC is composed of both load and gener-
rest of the interconnection is represented by a straight line. ator response to frequency deviation, the governor response
When a load generation imbalance occurs outside of control of the generation is the largest and hardest component t o
area A. resulting in low frequency, it will respond according to estimate. Therefore, estimating governor characteristics. es-
its SRC t o Point 1. If the AGC has a Bfssetting as indicated, the pecially the dead band value, is most important in determin-
AGC will control generation to Point 2 (moving along the exter- ing the bias value. Dead band values vary as t o size and
nal interconnection SRC). By this time, the deficient external distribution around the operating point throughout the load
control area begins correcting and corrects t o Point 3 (moving cycle. Since governor slopes vary the composite system gover-
along A's SRC) after which contwl area A's AGC drops genera- nor effect can vary. Each control area should address these
tion back from 3 t o 0. Control area A's AGC moves from l t o 2 concerns when determining its bias value. ,
and 3 to 0 were in the opposite direction and unnecessary.
These unnecessary moves would have been reduced or elimi- Details of Union Electric frequency bias modes are de-
nated if the SRC were better simulated by Bvn. This is because, scribed in the Appendix.
Authorized licensed use limited to: AMRITA VISHWA VIDYAPEETHAM AMRITA SCHOOL OF ENGINEERING. Downloaded on August 17,2023 at 08:22:20 UTC from IEEE Xplore. Restrictions apply.
1246
THE UNION ELECTRIC SYSTEM Among the data collected were daily averages per hour of
t h e raised and lowered pulses sent t o each controllable unit.
Control Area Description The averages are calculated separately for the pulses sent in
the fixed bias and variable bias mode. The data was combined
The Union Electric Company is an investor-owned utility t o show the difference between average pulses sent in the
with corporate headquarters located in St. Louis. Missouri. It fixed or variable bias mode. Figure 3 shows information plot-
serves over 1,000,000industrial, commercial and residential ted for the Rush Island #2 600MW unit. The solid line on t h e
customers in the states of Missouri, Illinois and Iowa. a service plot represents a cubic regression fit of the data. The results
area of more than 24,000 sq. miles. show that the B,, mode sent less pulses t o t h e regulating
The Union Electric Company has had a gross instantane- unit. Other regulating units had similar results. These pulsing
ous summer peak load of 6810 MW. The present summer reductions for the B,, mode were coincident with the ACE
gross capacity is 8031 MW. Most of the system's load is served excursion reductions discussed above.
a t 60 Hz with a small fraction, some 50 MW. served a t 25 Hz.
System generation is made up of a combination of fossil, nu-
clear, run-of-the-river hydro, stored hydro, pumped storage 50 I
hydro and combustion turbines. Union Electric is intercon-
nected with 21 other utilities. The company is a member of
the Illinois-Missouri Pool, the MAIN Reliability Council and t h e
North American Electric Reliability Council (NERC).
Energy Management Computer System
Union Electric's energy management system is a Control
Data (CDC) digital computer based system consisting of four
CDC System-17 computers and two CDC Cyber 170-7303.
There are approximately 10,000 data points that are scanned
every two seconds. Automatic Generation Control, A X . is
initiated every four seconds.
Some of the major applications performed by the com- ~.
puter system are Supervisory Control and Data Acquisition AW Now MUIS JMS SEPBS JM
DATE
(SCADA). AGC, state estimation, contingency analysis and en-
ergy accounting. The digital computer system was installed in
early 1983. Installation of this system provided Union Electric Figure 2.-ACE Performance
with ability t o make the necessary calculations for determin-
ing B,,.
Authorized licensed use limited to: AMRITA VISHWA VIDYAPEETHAM AMRITA SCHOOL OF ENGINEERING. Downloaded on August 17,2023 at 08:22:20 UTC from IEEE Xplore. Restrictions apply.
1247
The third effort was directed a t improving generating 4. Charles Concordia. “Performance of Interconnected Svs-
unit response. This effort, in coordination with the power tems Following Disturbances:’ IEEE-Spectrum. June,
plant personnel, resulted in much improved generator re- 1965. pp. 70-71.
sponse and more generating units available for regulation. 5. Charles Concordia. “Effect of Prime Mover Speed Control
Characteristics on Electric Power System Performance:’
IEEE PAS-88. 1969. pp. 752-754.
SUMMARY
6. Thomas Kennedy, “Discussion of NAPSIC Operating Pol-
Over the past two years, Union Electric has been able t o icy,” letter t o NAPSIC. June 3, 1975.
reduce the number of generating units needed for system
regulation while at the same time improving its control per- 7. Thomas Kennedy, “Cost of Power System Regulation”
formance. One reason for these results is t h e improved model- from “Current Operating Problems Associated with Auto-
ing of t h e tie-line frequency bias. Over this two year period, matic Generation Control,” IEEE PAS 98, January-
Union Electric’s control performance, as measured by t h e February, 1979.
NERC Criteria A1 and A2. has improved by approximately
10%. While other improvements certainly contributed t o im- 8. S. M. Hoyt, B. K. Mukherjee. et al., “The Union Electric
proved control performance. the improved tie-line frequency Company Load Dispatch System,” presentation a t IEEE
bias model was an important contribution. Control of Power Systems Conference. Oklahoma City,
March 17-1 9. 1980.
The data collected also supports very closely t h e simu-
lated results found by Ben Oni in his study on B,, control a t the 9. Ben Oni. Non-Linear Tie-Line Bias Control of Interconnect-
University of Missouri-Columbia. See Ref. 9. ed k w e r Svstems. Doctoral Dissertation, University of
Missouri-Columbia (Dr. Lewis Walker, Faculty Advisor),
Monitoring on unit regulation will continue with regard t o 1980, pp. 175- 176.
ACE and generator pulsing. In addition, efforts will be made t o
determine ways of monitoring the effect of using B,, on tie- 10. Dr. Lewis Walker, “Investigation of Non-Linear Tie Line
line swings. Further tuning of the bias model will continue. Bias Control of Interconnected Fbwer Systems:’ IEEE PAS-
100.May 1981, pp. 2350-2356.
In addition t o matching B t o t h e SRC for better control.
each NERC control area should also provide adequate genera- 11. UE Reports t o NERC-OC Performance Subcommittee,
tion response t o control area requirements and maintain its February, 1984-August, 1986.
turbine-generator governors in an unconstrained state so t h a t 12. North American Electric Reliabilitv Council, ODeratina
they can always be ready t o act t o stabilize interconnection “Guide No. 2-Bias Settings,” NERC Operating ‘Manuac
frequency. The spirit and intent of the ‘NERCOperating Com- December 3. 1986.
mittee Criteria and Guides call for each control area t o meet
these requirements so t h a t t h e reliability and control of
t h e interconnected systems will always be maintained at a
high level.
Authorized licensed use limited to: AMRITA VISHWA VIDYAPEETHAM AMRITA SCHOOL OF ENGINEERING. Downloaded on August 17,2023 at 08:22:20 UTC from IEEE Xplore. Restrictions apply.
1248
Authorized licensed use limited to: AMRITA VISHWA VIDYAPEETHAM AMRITA SCHOOL OF ENGINEERING. Downloaded on August 17,2023 at 08:22:20 UTC from IEEE Xplore. Restrictions apply.
1249
AFD = Actual freq. deviation in thousandths of lus Charles F. AbeU was born November 13,1958 in
= 2
PerryviUe, Missouri. He rewived the WEE degree
from University of Missouri, Rolla in 1983. He
Figure 5. Governor Response is a member of Eta Kappa Nu and the IEEE
Power Engineering Society.
Ref. 2 indicates a dead band of turbine-generator gover- He has been in System Operations at Union
Electric Company, St. Louis, Missouri since
nors of f.03 Hz. However, testing on the UE system has graduation in 1983. During that period Mr. Abell
shown t h a t these values might range from f .02 Hz t o f .04 has been involved in the development and
Hz for t h e most part. UE had used f .025 Hz as t h e dead band enhancement of the Load Dispatch Office energy
value. The UE algorithm accounts for the distributed dead management computer system. His primary
band in the overall composite value used in t h e B,, calculation. responsibilities have tm n in the areas of AGC, SCADA, and computer
Testing is still going on t o determine t h e distribution of the system expansion.
governor dead bands.
Authorized licensed use limited to: AMRITA VISHWA VIDYAPEETHAM AMRITA SCHOOL OF ENGINEERING. Downloaded on August 17,2023 at 08:22:20 UTC from IEEE Xplore. Restrictions apply.
1250
Discussion additional assistance granted to a troubled area for the same percentage of
bias above the area frequency response characteristic.
Nathan Cohn (Network Systems Development Associates, Jenkintown, The paper helped resolve ISC disagreements and confirmed that a bias
above the assumed frequency response is much more advantageous than a
PA): Over the years, this individual has had many discussions with Mr.
Kennedy about bias and bias control. Sometimes we have agreed, sometimes bias below it.
we have not. Always the exchanges have been friendly and educational. In the discussion section of [4], 1953, C.P. Almon, Jr., then with TVA,
Responding to an invitation from Mr. Kennedy, these questions and raised two questions. One, interestingly, asked about the possibility of a
comments are submitted. None are intended to be critical of the technique variable nonlinear bias, which was Mr. Kennedy’s approach. The other
described by Kennedy and his coauthors, who are commended for its appli- asked:
cation in a manner they consider successful. Rather, the questions seek to “Can the system, by bias settings, be made to have any reasonably
clarify certain aspects of variable bias technology, and the comments suggest desired characteristics regardless of the dictates of the natural character-
another, differing, point of view for bias setting. istics?”
This, thirty years later, reflects this discusser’s current approach. His
The questions are as follows.
response at the time was in the affirmative and went on to say:
In the light of the many variables that influence area frequency response,
including: varying makeup, magnitude, and frequency coefficient of “The time well may come when imposing definite predictable regulating
connected load; varying load levels, nonlinear incremental droops, characteristics on each operating area in this manner, instead of accepting
particularly at valve change points, and varying sensitivity and dead or relying on its varying natural characteristics, will be the prevalent
bands of on-line generators; and varying levels of system frequency and operating philosophy and practice.”
magnitudes of frequency changes; can the authors comment on the Such a time, after thirty years, has not yet and may never come. Its potential
accuracy of the on-line computations of area frequency response, and advantages, however, have been evolving in this discusser’s mind. It is
whether it is continuously checked and how? discussed in [ 5 ] .
Would the authors clarify the reasoning that placed point 3 of Fig. 1 at What then would be the advantage of such uniformly computed biases?
the location shown and explain the movement of point 2 to 3? It is not What would it achieve? Perhaps this will be clear if one recalls that a major
apparent why frequency would rise to point 3 while the external system function of bias, in addition to avoiding conflict with area frequency
was correcting frequency. response, is to have participating areas provide bias assistance to areas in
trouble or need. From July 21, 1964, to December 2, 1986, this function
3) Would the authors clarify why there is a relatively small bias for area of bias was explicitly stated in NAPSIC-NERC Operating Guide No. 2,
A SRC at frequency deviations close to 60 Hz and larger ones for greater with the following phrase concerning bias control:
frequency deviations? In asking this question, the discusser is conscious
of his own use for analysis of a curve composed of three linear segments “and thereby assist another control area in an emergency due to loss of
somewhat similar to the SRC curve of Fig. 1 and which appeared in [ I ] generation or load.”
of this discussion. He later concluded that frequency variations do not
Though such a phrase was omitted, perhaps inadvertently, from the
always start at 60 Hz. They may start as small deviations anywhere in
December 1, 1986 revision of the guide, assistance to others remains implicit
the band of f 0.03 or f 0.04 Hz customarily encountered daily. Also,
in the new wording.
+
frequency schedule is periodically shifted 0.02 Hz for time correction.
With such assistance needed, who should supply it? How much should
Thus directional reversals, resultant dead bands, and decreased sensi-
each assisting area furnish? Should it be random, or should the assistance
tivity can occur anywhere in the operating band. Correspondingly, low
’burden for each assisting area have some relation to something and what
and high incremental droops can occur anywhere in the operating range.
should that relationship be?
In [2] of this discussion, the late E.E. George noted that ranges of 6:l
This discusser suggests that bias assistance, a vital operating requirement,
were not uncommon in the incremental slopes of generator governing
would be equitably shared if it is provided by control areas in proportion
characteristics.
to their sizes, i.e., in proportion to their MW peaks. The proportion of area
bias to total system bias is the share of the total required bias assistance
The discusser is pleased that his early 1950 bias paper is [ 11 in this paper. that each area is scheduled to provide. Equitable distribution, if desired,
It summarized the characteristics of prior control techniques and noted the would be achieved if all areas had a bias of the same percentage of its peak,
advantages of frequency-biased net interchange control in all areas of the the percentage being selected to be higher than the percentage-of-peak
interconnection with no central frequency regulating area. It pointed out frequency response of any of the areas.
that a frequency bias was needed to coordinate area acontrol with an area’s The very conditions that create a variable frequency response to which
frequency response for remotely caused frequency changes. It demonstrated an area bias is linked as in the subject paper would create a variable level
through graphical analyses that the best coordination was obtained when an of bias assistance by the area in fulfilling system needs. The NERC 1987
area bias was equal to the area frequency response. That conclusion has listing of area peaks and bias settings in the NERC manual shows a peak
often been cited, as in this paper, as justification of matching bias to for Union Electric of 6835 MW and a total Eastern peak of 401 125 MW.
frequency response, which is fair enough. But from this discusser’s point It shows a varying bias range for Union Electric of 50 to 200 MW/O. 1 Hz
of view, that was only the beginning. Other papers and views later followed and a total system bias of 5573 MW/O.I Hz. Based on that data, Union
resulting in “another point of view.” Electric, with 1.7 percent of the system peak, will be scheduled to provide
Considering the uncertainty of an area’s varying frequency response at the low end of its bias range about 0.9 percent of system bias assistance.
characteristic, this discusser began to examine how bias settings that were At the high end it would provide about 3.5 percent of system bias assistance.
under, equal to, or above the area frequency response would affect system Similar percentages of required total system time correction would be
conditions and bias assistance to areas in need when there were unregulated provided by Union Electric during universal time correction periods.
remote load changes. There was also in those years considerable disagree- It is of course recognized that the extent of bias assistance to be scheduled
ment in operating circles on proper bias settings. This discusser was invited by individual areas is, as are all operating practices, a matter for system
to present his views to the Interconnected Systems Committee’s annual operating personnel to determine. This discusser suggests, however, that
meeting at Des Moines in March 1956. A transcript of the presentation there are potential advantages in bias assistance based on a common
appears in [3]. percentage-of-peak for all areas. It would provide an equitable, cooperative,
Later, expanded and formalized, the presentation became an AIEE paper and democratic systems approach.
[4] which includes curves and formulas derived mathematically for calcu- Regarding bias assistance as a “burden” or “tax” that goes with sharing
lating effects on various system and area conditions for different biases and in the benefits of interconnection, the discusser ventures in this Bicentennial
other operating parameters. Year to quote, for consideration, from Article I, Section 1 of the Consti-
That paper confirmed the fact that the best way to coordinate AGC with tution with parenthetical paraphrasing to transfer its applicability to power
area frequency response was to match bias to area frequency response. systems operations as follows:
However, it showed more, defining the effects of bias settings below or
above the area frequency response. It showed that disadvantageous operating “Taxes (bias assistance) shall be apportioned to the several States (control
results are much greater for a bias that is a given percentage below the areas) which may be included in the Union (interconnected system),
frequency response characteristic, as compared to the magnitude of according to their Numbers (MW peak).”
Authorized licensed use limited to: AMRITA VISHWA VIDYAPEETHAM AMRITA SCHOOL OF ENGINEERING. Downloaded on August 17,2023 at 08:22:20 UTC from IEEE Xplore. Restrictions apply
1251
Authorized licensed use limited to: AMRITA VISHWA VIDYAPEETHAM AMRITA SCHOOL OF ENGINEERING. Downloaded on August 17,2023 at 08:22:20 UTC from IEEE Xplore. Restrictions apply.
1252
disturbed area receives an inadvertant energy W. Spencer Bloor (Consultant): The authors are to be complimented on
contribution from every other control area in the presentation of this paper and for proposing an alternate way of dealing
the system. In the terminology of N. Cohn’s with bias. A debt of gratitude is also due them for providing an opportunity
decompositlon technique there is primary to disagree with certain aspects of the nonlinear bias control. Points of
receipt f o r the disturbed area and secondary disagreement are enumerated below along with an incidental comment on
delivery for each other area. The payback a problem in Fig. 1.
will be smooth if the disturbed area alone
invokes a unilateral correction. Ei:ateral 1) The similarity between the control characteristic of nonlinear bias and
01- ~ r . i ? a t e r a lcorrect :c:r Izstitutel ir. nther a discarded control mode of years gone by suggests that the widespread
iireas wi:? initiate an osci?:ation of -
use of nonlinear bias has the potential to degrade the quality
~- of control
inadvertant energy accounts and a sequence of in interconnected system operations. The discarded control mode is
required corrections in various areas of the selective frequency [l]. The idea behind selective frequency was to
system. allow only the SRC to respond to remote changes and reserve the AGC
response for local changes. Selective frequency did not work well in
The adaption of Mr. Cohn‘s technique may practice and inspired the invention of tie-line bias 121.
be impacted by anything which makes its use The proportion of ACE accommodated by governor control of area A
more complex. With variable bias in effect in the authors’ Fig. 1 illustrates another limitation of nonlinear bias and
an integration is required to compute dependence on the initial SCR to do the entire control job. The initial
regulating deficiency in one‘s own area and SCR in Fig. 1 is less than one-half of area A’s ACE. Assuming a 2-
communicated values of variable bias from percent bias and a 0.7-percent load response portion of the total SCR
other areas are needed to compute quantities, response (all percentages are per 0.1 Hz), the governor control portion
such as primary inadvertant, that depend on of the SCR is less than 0.3 percent. This indicates that less than 10
total system bias. To keep things simple by percent of area A’s spinning capacity is responding to governor control.
using constant bias (with the possible The effect of this on units under AGC is described in [3] of this discus-
exception of rare and short term emergency sion. It is characterized therein as operating with a low Q.
situations) is very appealing in the opinion Operating with a low Q increases the regulation of AGC units. In a
of the discusser. relatively large area and especially with only one unit on AGC, the AGC
burden can be excessive and requires operation of this unit at a reduced
Notwithstanding some questions and load. One way to relieve the burden is to reduce the bias setting which
disagreements, the paper is considered a has the effect of decreasing the amount of AGC correction required.
valuable and pleasing contribution to this
subject which is far more profound than it While this reduction is advantageous from the viewpoint of the control
appears on casual exposure. area that is decreasing its bias, it is not the best way when viewed from
the needs of the ’total interconnection. From the interconnection’s
Manuscnpt received August 10, 1987 viewpoint the better way is to raise Q or put more units under AGC in
the control area.
This dependence of the nonlinear bias on Q in the control area is a
limitation which is not shared by the linear bias. The latter makes the
AGC independent of Q and the number, size, and geographical diversity
of generation sources within the control area. This Q dependence of the
Robert K. Green, Jr. (Central and Southwest Services, Inc., Dallas, TX): nonlinear bias creates an inequity in the sharing of the regulating burden
There are very few AGC papers presented that can be immediately applied throughout the interconnected system because a larger geographically
to an existing EMS to improve the AGC function. This paper is one of compact control area is able to reduce Q more readily and safely than
those few. I think that the method described is a very practical and a very are smaller areas or geographically large areas.
creative approach to improving the calculation of area control error (ACE) While it may not be a practical problem, the nonlinear bias characteristic
which is the principal feedback variable in most automatic generation control is also similarly dependent on a control area’s load characteristic. Control
(AGC) systems. areas with highly resistive loads are automatically excused from carrying
In actual practice it is very easy to forget that the bias times the frequency a proportionate share of the regulating burden needed to provide smooth
deviation is a mathematical model that simulates how many MW of the and effective interconnected system operation.
measured net interchange has been caused by governor action within the While unrelated to any limitation in the nonlinear bias technique, there
control area. Any improvement to this model whether analytical or heuristic is a problem in Fig. 1 . The frequency cannot go above 60 Hz (or its
will improve system control. scheduled value if offset for a time correction) as a result of the SCR
If the bias value(s) is too small, after a unit trips, the other control area@) and AGC responses to a load increase in the external interconnection.
will predict too small of a governor MW value and supplemental control
will back down generation, further aggravating the low frequency. If the References
bias value is too large, under normal conditions, small frequency deviations
can cause AGC to chase an ACE that never should have been presented to [I] N. Cohn, “The evolution of real time control applications to power
the controller. A problem with our classical ACE equation is that it depends systems,” presented at the IFAC Symposium on Real Time Digital
on near perfect bias values to perform properly in both the normal and Control Applications, Guadalajara, Mexico, Jan. 1983.
disturbance mode. Filtering invalid ACE values work, but improving the [2] A. J. Williams, Jr., and S. B. Morehouse, “Electric generating
model of governor contribution is a better solution. systems,” U.S. Patent 2 124 724, June 26, 1938.
The authors correctly point out that the governor contribution to a given [3] N. Cohn, “Some aspects of tie line bias control on interconnected
frequency deviation is a function of the number of units on-line within the power systems,’’ AIEE Paper 56-670, AIEE Trans. Power App. Sysr.,
control area. If we do not try to model at least that obvious change in the part 111, Feb. 1957.
bias value we risk taking incorrect control action.
I think the adaptive concepts presented can be extended further in the Manuscript received August 10, 1987.
future. For instance, if frequency is within a given dead band and frequency
is low and time is fast, the bias can be set to zero. You are then doing T. Kennedy,~S. M. Hoyt, and C. F. Abell: The authors wish to thank
constant net interchange control while the frequency error is automatically Messrs. Cohn, Green, Bloor, and VanSlyck for their detailed comments to
correcting the time error. In the same manner, if frequency is fast and time the paper. Mr. Kennedy values his many years of association with Mr.
is slow, the bias can again be set to zero. Cohn very much and also appreciates Mr. Cohn’s several contributions to
Finally, in the conclusion to the paper the variable bias is credited with the industry with regard to electric power system control. The authors offer
production cost savings, but no mention is made of the source of the savings the following response.
or the magnitude of the savings. Would the authors please expand on that As Mr. Cohn points out, the authors are well aware of the fact that there
statement? were many divergent views in the 1950’s as to the proper value of tie-line
Manuscript received July 31, 1987. frequency bias. This was probably brought about by the fact that the bias
Authorized licensed use limited to: AMRITA VISHWA VIDYAPEETHAM AMRITA SCHOOL OF ENGINEERING. Downloaded on August 17,2023 at 08:22:20 UTC from IEEE Xplore. Restrictions apply
1253 .
concept was relatively new to most systems and that analog control very areas used BvN, the assistance to control areas in trouble would be greater
much limited the flexibility of the system operator to properly simulate the and better-distributed for larger frequency excursions than with BFs. This
SRC. The operators were usually faced with choosing the lesser of two is due to the fact that BVNrecognizes and maintains full governor action as
evils-too little or too much bias. As Messrs. Cohn and VanSlyck point mentioned above. BFs,which is tied to the control area yearly peak, actually
out, too much bias is probably better than too little bias. However, with constrains and controls against full governor action during larger frequency
the advent of digital computers in present-day operations, bias can be excursions and can actually force frequency lower for large capacity
matched very closely to SRC and at the same time recognize the minimum deficiencies or higher for large capacity surpluses. Union Electric finds that
limit set by the NERC operating committee. The authors believe that this F1 and F2 are smaller than the *0.06 Hz mentioned by Mr. VanSlyck and
improved bias/SRC match gives the system operator the ability to better in fact have had F1 exceeded and the bias increased several times since
assist his neighbor in time of trouble while still maintaining good regulation BvN has been used. The authors tend to agree with Mr. VanSlyck‘s comment
for his control area. The authors believe BVNhas that advantage over BFs. that BFscould be “describing an existing potential catastrophe.”
It is the authors’ opinion that, even though there are many variables that The authors are confident that a SRC/bias mismatch will always result
make up the SRC, the continuous recognition of the individual turbine in excess regulation. In addition, as discussed in the paper, SRChias
generator dead band and the actual governor slope eliminates approximately mismatch can create undesirable frequency or tie-line excursions (such as
three fourths of the inaccuracy of the SRC simulation made by BFs. At the case mentioned by Mr. VanSlyck where 2 is to the left of 1 in Fig. 1).
Union Electric, BVNis calculated every four seconds and recognizes the In response to Mr. Bloor’s question 4, the frequency can certainly be
dead band and governor slope for each on-line unit and the changing magni- driven over 60 Hz if improper bias settings cause control areas other than
tude of the system load. Because SRC is extremely difficult if not impossible the deficient system to over control, which could be the case with BFs.
to measure in practice, a comparison other than an empirical one is not Very few systems have highly reactive loads, but even so, the load
practical at this time. However, the authors believe that a statistical analysis response portion of SRC is small and, as Mr. Bloor points out, is not a
such as that included in the paper goes a long way to demonstrate the practical problem.
effectiveness of BVN. Even though the inadvertent discussion of Mr. VanSlyck is not within
The authors recognize, as Mr. VanSlyck points out, that the initial move the scope of this paper, the authors do recognize that control areas have
from 0 to 1 (Fig. 1) goes through a transient path and does in fact take broken down the components for years and have used it to analyze their
place in seconds. However, it does settle down in six to ten seconds which inadvertent interchange. With regard to Mr. VanSlycrs concern, digital
is well under normal control response time. The move from 0 to 1 is a pure computer application techniques should allow BVNto be applied to Mr.
system response. The move from 1 to 2 is a controller action. To properly Cohn’s decomposition technique for inadvertent energy and it should add
understand interconnection control one must always keep the two types of more accuracy to the process. Union Electric’s efforts in this direction are
moves differentiated. covered in IEEE paper 31 TP 67-136.
The movements from 1 to 2 and 3 to 0 are due to the SRClBias mismatch. Even though Mr. Bloor’s experience with selective frequency control
The external system causing the frequency deviation will, by the nature of was not good, the authors point out that they have had good experience
the event, take some minutes to correct its deficiency. Control area A, with variable nonlinear tie-line f q u e n c y bias. Rather than degrade the
controlling to its BFS value, will have ample time and regulating capability quality of control as the very early method of selective frequency control
to depart from its SRC response and move from 1 to 2. Control am A will apparently did, variable nonlinear bias has improved control at Union
stabilize at 2. When the external system starts to correct its deficiency it Electric.
will move control am A along its SRC to 3. In response to Messrs. Cohn The 1.7 percent of system peak bias calculated by Mr. Cohn for Union
and VanSlyck’s question, if control area A is responding well, movement Electric is about the middle of the .9-percent to 3.5-percent range he calcu-
2 to 3 and 3 to 0 may take place in the same time frame. Movement 3 to lated for the variable bias.
0 is a component that is counter to movement 1 to 2. The graph in the In response to Mr. Cohn’s comment concerning NERC operating guide
paper was simplified showing movement 2 to 3 and 3 to 0 separately to #2, the first sentence of NERC operating guide #2 (revised December 2,
demonstrate the theory. Had control area A been on BVNthere would have 1986) covers the frequency deviation assistances to other control areas. The
been a very small or no 1 to 2 or 3 to 0 movement. NERC operating committee remains steadfast in its determination to allow
The authors agree with Mr. Cohn that the turbine generator dead band control area automatic generation control to assist other control areas in
will not always be centered for each machine. Some may be on the raise emergency situations.
edge and some may be on the lower edge with the rest somewherebetween. The authors look forward to further improvements in the use of tie-line
The Union Electric algorithm assumes that 20 percent of the generators are frequency bias such as Mr. Green suggests. They also appreciate his positive
normally at either edge of their dead band. view of future possibilities in this area. As could be expected the actual
Concerning Mr. Bloor’s remarks that BVNdepends on SRC to do the savings due to B,, are difficult to evaluate, especially due to the fact that
entire control job, the authors point out that SRC is a system response other improvementsare being made at the same time. However, the authors’
characteristic and must not be confused with controller action. These two best estimate of savings is in the range of 1/2 percent of the total production
actions must be considered separately if interconnection control is to be costs.
properly analyzed. In addition, generating unit response is a third important The authors very much agree with Mr. Cohn that each control area should
factor to be considered. consider their bias obligation as a small price to pay for the substantial
In response to Messrs. Bloor, VanSlyck, and Cohn’s concern regarding benefits they m i v e from interconnection operations. It is the authors’
the relatively small bias setting close to 60 Hz,as pointed out in the paper, opinion that the systems of NERC take that obligation very seriously as
the low response for small frequency deviations is the result of governor verified by the statements in the preamble of the NERC Operating
dead band which is in the order of *0.025 Hz. This dictates a h a l l bias Committee Reliability Criteria for Interconnected Systems Operation.
value for small frequency excursions. Likewise, for larger frequency excur- In response to Mr. VanSlyck’s question as to the universal adoption of
sions, full governor response (3.3%/0.1 Hz at 5-percent governor droop) BVNin the tie-line control of all control areas, the authors believe that BVN
plus load response is allowed. is better than BFsbut would welcome more investigation.
Some of the discussers have expressed concern regarding controller action
for larger frequency deviations. The authors are confident that if all control Manuscript received September 4, 1987.
Authorized licensed use limited to: AMRITA VISHWA VIDYAPEETHAM AMRITA SCHOOL OF ENGINEERING. Downloaded on August 17,2023 at 08:22:20 UTC from IEEE Xplore. Restrictions apply.