Agp-22050-Itp-Ins-Q01-0001 00 Rev 0
Agp-22050-Itp-Ins-Q01-0001 00 Rev 0
Project/JOA
No. 22050 Solid Kiln 4 New Cement Line Expansion Project / 22050
Batangas Heavy Fabrication Yard Bauan-Mabini Road, San Roque, Bauan, Batangas 4201, Philippines
Phone: +63 (43) 740 5800 l www.agpglobal.com
This document is strictly confidential and the exclusive property of AG&P. It cannot be No. of Pages Attachments Rev.
copied, used, modified, adapted, disseminated, published or communicated, in whole
or in part, by any means, for any purpose, without express prior written authorization of 16 8 0
AG&P. Any violation of this clause may give rise to civil or criminal liability - © AG&P.
This document and all information and data herein or herewith is the confidential and proprietary property of AG&P and is not to be used,
reproduced or disclosed in whole or in part by or to anyone without the written confirmation from AG&P.
Page : 1 of 7 .
INSPECTION & TEST PLAN AG&P-22050-ITP-INS-
Doc. No. :
Q01-0001.00
Insulation and Cladding for Rev. No. : 0
Solid Kiln 4 New Cement Line Expansion Project Date : 26-Aug-22
INSPECTION/TEST/
REV. DATE DETAILS PREPARED REVIEWED APPROVED DOCUMENTATION
VERIFICATION CODES
1.1 Review Contract / Project Specification Contract Documents AGP-00000-P-Z-03-0001.00 Contract Review AGP-00000-P-Z-03-0001.00 Contract Review R1 R1
1.2 Review Approved Drawings IFC Drawings AGP-00000-P-Z-03-0001.00 Contract Review Approved Drawings R1 R1
2.1 Project Assurance Execution Plan PC Quality Control AGP-22050-PLN-QLY-Q01-0001.00 Approved PAEP R1-AP IN
AGP-00000-FR-T-13-0001.00
(Material Inspection Report)
AGP-00000-FR-U-84-0002 00
AGP-22050-P-U-84-0004.00 Control of Customer (Notification for Inspection/Testing of Raw
Materials Inspection on Receipt for Damage, ThermaI Insulation for Equipment and If no Material Test Reports/Certificates
Supplied Materials Materials),
3.1 Quantity, Physical Condition of materials, Process Ductwork A1-R1 W1-R1 provided by the customer, refer to
AGP-22050-P-U-84-0001.00 AGP-22050-FRM-IAT-Q01-0001.00
Receipt Documents, etc. EETIM76300/13900 sec. 420 section 12.2 of the Project Assurance
(Materials & Equipment Receipt) (Material Receiving Inspection Checklist)
Execution Plan
AGP-22050-FRM-IAT-Q01-0002.00
(QC Inspection Report)
Material Test Report
AGP-00000-FR-T-13-0001.00
AGP-22050-P-U-84-0004.00 Control of Customer
ThermaI Insulation for Equipment and (Material Inspection Report)
Supplied Materials
3.2 Check identification of the material Process Ductwork AGP-22050-FRM-IAT-Q01-0001.00 A1-R1 W1-R1
AGP-22050-P-U-84-0001.00
EETIM76300/13900 sec. 420 (Notification for Inspection/Testing of Raw
(Materials & Equipment Receipt)
Materials)
Page : 3 of 7. .
INSPECTION & TEST PLAN AG&P-22050-ITP-INS-
Doc. No. :
Q01-0001.00
Insulation and Cladding for Rev. No. : 0
Solid Kiln 4 New Cement Line Expansion Project Date 26-Aug-22
:
1.0 CONTRACT
Check REVIEW
and verify thermal insulation for
ThermaI Insulation for Equipment and Insulation Inspection Checklist
personnel protection using mineral wool board AGP-00000-P-T-13-0006
7.20 Process Ductwork (AGP-00000-FR-T-13-0043.00) A1-C W1
with a high temperature binder, 2lb/ft3 (32 Insulation Inspection
EETIM76300/13900 sec.423 Approved Drawings
kg/m3) and 2 inches (50mm thick)
8.0 FINISHES/CLADDING
Check and verify the finish cover of thermal ThermaI Insulation for Equipment and Insulation Inspection Checklist
AGP-00000-P-T-13-0006
8.1.1 insulation, shall be plane aluminum sheet 22- Process Ductwork (AGP-00000-FR-T-13-0043.00) A1-C W1
Insulation Inspection
Ga. (0.028 inches). EETIM76300/13900 sec. 426 Approved Drawings
9.0 REPAIRS
AGP-00000-P-T-13-0006 AGP-00000-FR-Z-13-0001.00
10.3 Issuance of Punchlist Project Specifications A1-C W1
Insulation Inspection (Punchlist )
AGP-00000-FR-T-13-0013.00 (Certificate of
10.4 Issuance of Certificate of Conformance - - AP-C R1-AP
Conformance)
AGP-0000-P-K-11-0006.00 AGP-00000-FR-K-11-0001.00
11.1 Record / Report Any Nonconformity Project Specification R1-C IN
(Nonconformity and Corrective Action) (Corrective Action Report)
AGP-0000-P-K-11-0006.00 AGP-00000-FR-K-11-0001.00
11.2 Monitor NCR Status Project Specification R1 IN
(Nonconformity and Corrective Action) (Corrective Action Report)
TO : NITRM No. :
DEPARTMENT/SECTION : LOCATION OF INSPECTION :
FROM : PROJECT :
DEPARTMENT/SECTION : J.O.A. NO./CUSTOMER :
REF. DOC. NO. :
We would like to request for the following materials: SUPPLIER :
INSPECTION TESTING (PMI) DATE RECEIVED :
PO NO. :
Item
Item Code Material Description Qty. Unit Material Identification Markings Remarks
No.
Note: Material Identification Markings include but not limited to Heat No./Lot No. or Batch No.
: :
Project Doc. Reference No.
: :
JOA No. Date
: :
P.O. No. Doc. Recv'ng Ref. No.
:
Supplier
Ordered
Delivery Receipt or
Item No. Item Code Description Delivered QTY Packing List Quantity Variance Remarks
UOM QTY QTY
ERROR TYPE:
Purchase Order Discrepancy No Traceability Markings Others (Pls. specify)
Incomplete Documents (MTC, Calibration Cert. etc.) Physical Condition (damaged, defective, etc.)
Qty Different from DR Incomplete/Inaccurate packing list
DATE
Findings:
Recommendation:
Customer Disposition:
Return to Supplier Repair / Rework Use As-is Scrap Others (Please Specify)
ACCEPTABLE REMARKS
SI NO INSPECTION CONTENT YES NO N/A
VERIFICATION OF DOCUMENTS
4 As-built drawings
MATERIAL INSPECTION
6 Quantity of Material
7 Materials/Equipment Preservation
10 Painting Condition
NOTES:
Sheet of
Note: Material Identification Markings include but not limited to Manufacturer, Specifications, Type, Grade, Heat No., Lot No. or Batch No.
INSPECTED BY REVIEWED BY
Customer Representative
QC Inspector QC Supervisor
SIGN
NAME
DATE
Rev. 1, 18 Oct, 2018
AGP-00000-FR-T-13-
0043.00
INSULATION INSPECTION CHECKLIST
Sheet of
DATE : MODULE :
ITEM/EQUIPMENT No. : DRAWING No. :
TAG/ID No. : PROJECT :
Accepted Accepted
Heat Tracing
2.0 INSTALLATION
Accepted Accepted
Application Screw/Fastening
Remarks:
APPROVED BY:
NAME
SIGN
DATE
Rev. 0, 27 Nov. 2018
AGP-00000-FR-Z-13-0001.00
PUNCHLIST
Sheet of
NAME
SIGN
DATE
CERTIFICATE OF CONFORMANCE
QTY. / DESCRIPTION :
CONTRACT No. :
QC MANAGER DATE