PO NO: 3400348787
CLOSE-OUT REPORT
Report No: P698/2023/SKA/COR REV00
Prepared by:
Signature
WAN MOHD
Name LEE KAI YANG HIDAYAT WAN
ABDULLAH
Date 05/07/2023
CLOSE OUT REPORT 5TH July 2023
1 Introduction √
2 Objective √
3 Period Work Performed √
4 Summary Scope of Work √
5 Organization & Manning √
6 Safety Statistic √
7 QA/QC Result NA
8 Inspection Findings and Recommendation NA
9 Project Man-hours/Performance Analysis √
10 Outstanding Scope of Work/Punchlist NA
11 Material Management – Surplus Materials NA
12 Drop Scope NA
13 Emergent Work/Construction Work Request (CWR) NA
14 Lesson Learnt & Best Practices √
15 Conclusion √
16 Attachments √
i. Daily Progress Report (DPR) √
1. INTRODUCTION
This report highlights the work completed for Scaffolding Erection to Assist IP for
i. PL370: 12” X 12.268 KM Oil Line (BAP-B to BKP-A)
The execution was performed to assist ROSEN for online pigging at Baram & Bakau field for PL370. The objective
of this report is to describe the work done that had been carried out throughout the project execution from
beginning until the completion of the project including site findings and lesson learnt during the execution.
Moreover, it is also to authenticate that HCSB had successfully completed the scope of works.
2. OBJECTIVE
The objective of this project is to assist IP launching and receiving in terms of scaffolding table erection for
pipeline PL370. The scaffolding table structure will be erected at PL370 launcher barrel door at BAP-B and
receiver barrel door at BKP-A to assist on online IP activities.
TOTAL: 1 LIFT
CLOSE OUT REPORT 5TH July 2023
For manpower mobilization, a total of three (3) pax are plan to mobilize to Bakau field (BKP-A) on 27th May 2023
via FCB Psalm 39. However, due to gear box issue of FCB Psalm 39, manpower and scaffolding set unable to
mobilize to BKP-A on 27th may 2023. Thus, the way forward was to utilized FCB Hisyam 6 to mobilized scaffolding
set only to BKP-A. Scaffolding set was lifted by operation from FCB Hisyam 6 onto BKP-A on 29th May 2023. On
15th June 2023, a total of three (3) pax mobilized to BKP-A (PL370 Receiving Side) via FCB Hisyam 6 for
scaffolding table erection scope of work. Three (3) pax of the manpower were bedding at MV Keyfield Falcon
from 15th June 2023 until 17th June 2023. Whereas for PL370 Launcher Side – BAP-B, four (4) pax mobilized to
BAP-B from 16th June 2023 for the scaffold table erection on daily basis until 17th June 2023 via FCB Centus 10.
For manpower demobilization, on 29th June 2023, a total of three (3) pax mobilized to BKP-A (PL370 Receiving
Side) via FCB Hisyam 6 for scaffolding table dismantle scope of work. Three (3) pax of the manpower were
bedding at BOCPP-A from 29th June 2023 until 2nd July 2023. Whereas for PL370 Launcher Side – BAP-B, four (4)
pax mobilized to BAP-B from 26th June 2023 for the scaffold table dismantle on daily basis until 28th June 2023
via FCB Centus 10.
Backloading scaffolding set for Bakau (BKP-A) was completed on 4th July 2023 via LCT MK1. Whereas,
backloading scaffolding set for Baram (BAP-B) was completed on 4th July 2023 via LCT MK10. (Refer to
Appendix A).
CLOSE OUT REPORT 5TH July 2023
Details of the summary execution activity can be referred to Appendix A – Daily Progress Report (DPR)
Lifting Activities
Lifting activities for materials placement (scaffolding sets) and toolbox were lifted at BKP-A and BAP-B main deck
by using Jib Crane 1.8MT. The materials were lifted on 29th & 30th May 2023. The scaffolding materials will be
transferred manually to the working locations.
CLOSE OUT REPORT 5TH July 2023
Pipeline Manager
Wan M. Hidayat
Scaffolder Inspector
Velintino David
Rigger
Henry Anak Ngelai
Kelvin Bin Jimy
CLOSE OUT REPORT 5TH July 2023
6. SAFETY STATISTIC
Items Description Cumulative
A HSE Statistics
Total Man Hours Worked 451
Fatality 0
Near Miss 0
Lost Time Injury (LTI) 0
Restricted Work Case (RWC) 0
Medical Treatment Case (MTC) 0
First Aid Case (FAC) 0
Occupational Illness (OI) 0
Fire / Explosion Case 0
Property Damage 0
C Meetings
Pre-mob Meeting 1
Toolbox Meetings Everyday
7. QA/QC RESULT
Not applicable.
No Description Manhours
1 Lifting Equipment at BKP-A & BAP-B 72
2 Worksite preparation at BKP-A & BAP-B 72
Scaffolding table erection / rigging activity to assist IP PL370 at BKP-A &
3 72
BAP-B
6 Dismantle scaffolding table at BKP-A & BAP-B 72
7 Housekeeping 72
8 Backloading 36
Others (including quarantine/stand-by/saliva test/mob/de-mob/FCB U-
9 55
Turn)
Total Manhours 451
CLOSE OUT REPORT 5TH July 2023
Pre-execution
1. Procedure 1. No issue at site 1. No issue at site 1. Site visit is required prior to job
2. Function Test 2. No issue at site 2. No issue at site execution activity.
2. Work scope to be firmed.
3. Function test to be done before
mobilization
Preparation
1. Mobilization of 1. No issue at site 1. No issue at site 1. Delaying mobilization of
equipment 2. No issue at site 2. No issue at site equipment will be affecting the
2. Lifting of 3. No issue at site 3. No issue at site schedule.
equipment to 4. No issue at site 4. No issue at site 2. For execution, lifting of
platform 5. No issue at site 5. No issue at site equipment must be prioritized
3. Mobilization of and movement of LCT need to
manpower be updated to avoid delay in
4. Laydown space activity.
area 3. Information regarding FCB
5. Equipment setup movement for the mobilization
and preparation of crew to be firmed
4. All contractor needs to discuss
and agree to allow the
execution for
priority/emergency job
5. Equipment and material
preparation should be done as
per schedule to ensure
execution not delayed.
Execution
1. Crew movement 1. No issue at site 1. No issue 1. Personnel transportation for
2. Project execution 2. No issue at site 2. No issue at site crew must be in good condition
3. during mobilization.
2. Work leader/PSS to ensure
work is completed as per work
pack before demobilization.
15. CONCLUSION
Haluan Cekap Sdn Bhd is pleased to confirm the completion of Scaffolding Erection to Assist IP for PL370.
Haluan Cekap Sdn. Bhd is honored to be given the privilege to provide and serve PETRONAS Carigali Sdn Bhd
in this activity.
Completion of SKO Pipeline Baram & Bakau field to assist IP inspection was performed within the given
approved schedule to complete the activities.
Throughout the entire duration of the project, Haluan Cekap has never compromise the health and safety of
every personnel involved during the execution. We have undertaken some efforts to exercise HSE which
includes: -
The exercise has brought zero LTI and zero incident/accident. In conclusion, this project has been completed
with satisfactory to both PETRONAS CARIGALI SDN.BHD and HALUAN CEKAP SDN.BHD.
16. APPENDICES
APPENDIX A:
DAILY PROGRESS REPORT
(DPR)