PETRONAS CARIGALI SDN BHD

PROVISION OF SERVICES FOR SCAFFOLDING


ERECTION ACTIVITY TO ASSIST IP
FOR
PL370: 12” X 12.268KM OIL LINE FROM BAP-B TO BKP-A

PO NO: 3400348787

CLOSE-OUT REPORT
Report No: P698/2023/SKA/COR REV00
Prepared by:

HALUAN CEKAP SDN BHD


Prepared by Reviewed by Reviewed by Approved by

Pipeline Inspection Pipeline Inspection


Pipeline Engineer Project Manager
Position Engineer Team Leader
(HCSB) (HCSB)
(QTO8) (QTO8)

Signature

WAN MOHD
Name LEE KAI YANG HIDAYAT WAN
ABDULLAH
Date 05/07/2023
CLOSE OUT REPORT 5TH July 2023

PROVISION OF SERVICES FOR SCAFFOLDING ERECTION ACTIVITY P698/23/SKA/COR


TO ASSIST IP
HALUAN CEKAP SDN BHD Rev. 00
PL370: 12” X 12.268KM OIL LINE (BAP-B TO BKP-A)

TABLE OF CONTENTS Tick - √ /NA

1 Introduction √
2 Objective √
3 Period Work Performed √
4 Summary Scope of Work √
5 Organization & Manning √
6 Safety Statistic √
7 QA/QC Result NA
8 Inspection Findings and Recommendation NA
9 Project Man-hours/Performance Analysis √
10 Outstanding Scope of Work/Punchlist NA
11 Material Management – Surplus Materials NA
12 Drop Scope NA
13 Emergent Work/Construction Work Request (CWR) NA
14 Lesson Learnt & Best Practices √
15 Conclusion √
16 Attachments √
i. Daily Progress Report (DPR) √

Note: Additional items can be added based on activities’ requirements.


CLOSE OUT REPORT 5TH July 2023

PROVISION OF SERVICES FOR SCAFFOLDING ERECTION ACTIVITY P698/23/SKA/COR


TO ASSIST IP
HALUAN CEKAP SDN BHD Rev. 00
PL370: 12” X 12.268KM OIL LINE (BAP-B TO BKP-A)

1. INTRODUCTION
This report highlights the work completed for Scaffolding Erection to Assist IP for
i. PL370: 12” X 12.268 KM Oil Line (BAP-B to BKP-A)
The execution was performed to assist ROSEN for online pigging at Baram & Bakau field for PL370. The objective
of this report is to describe the work done that had been carried out throughout the project execution from
beginning until the completion of the project including site findings and lesson learnt during the execution.
Moreover, it is also to authenticate that HCSB had successfully completed the scope of works.

2. OBJECTIVE
The objective of this project is to assist IP launching and receiving in terms of scaffolding table erection for
pipeline PL370. The scaffolding table structure will be erected at PL370 launcher barrel door at BAP-B and
receiver barrel door at BKP-A to assist on online IP activities.

3. PERIOD WORK PERFORMED


The date of equipment mobilization and demobilization are as per Table 3.1 below. Further details can be
referred to Appendix A: Daily Progress Report (DPR).

Table 3.1: Equipment Mobilization and Demobilization for PL370


NO DATE DESCRIPTION FROM TO

EQUIPMENT MOBILIZATION TO BAKAU


(BKP-A) – VIA FCB HISYAM 6
BAKAU
FROM
1 29/05/2023 FIELD (BKP-
 SCAFFOLDING SET LOOSE – 1 SET SERIMAS
A)
TOTAL: 1 LIFT

EQUIPMENT MOBILIZATION TO BARAM


(BAP-B) – VIA CENTUS 10
BARAM
FROM
2 30/05/2023  HCSB-OTT- 018 (OPEN TOP TRAY FIELD (BAP-
SERIMAS
WITH SCAFFOLDING SET) B)

TOTAL: 1 LIFT
CLOSE OUT REPORT 5TH July 2023

PROVISION OF SERVICES FOR SCAFFOLDING ERECTION ACTIVITY P698/23/SKA/COR


TO ASSIST IP
HALUAN CEKAP SDN BHD Rev. 00
PL370: 12” X 12.268KM OIL LINE (BAP-B TO BKP-A)

EQUIPMENT DEMOBILIZATION FROM


BARAM (BAP-B) TO BPA – VIA LCT MK10
BARAM
 HCSB-OTT- 018 (OPEN TOP TRAY
3 4/07/2023 FIELD BPA
WITH SCAFFOLDING SET) (BAP-B)
TOTAL: 1 LIFT

EQUIPMENT DEMOBILIZATION FROM BAKAU


(BKP-A) TO BPA – VIA LCT MK1
BAKAU
4 4/07/2023 FIELD BPA
 SCAFFOLDING SET LOOSE – 1 SET
(BKP-A)
TOTAL: 1 LIFT

For manpower mobilization, a total of three (3) pax are plan to mobilize to Bakau field (BKP-A) on 27th May 2023
via FCB Psalm 39. However, due to gear box issue of FCB Psalm 39, manpower and scaffolding set unable to
mobilize to BKP-A on 27th may 2023. Thus, the way forward was to utilized FCB Hisyam 6 to mobilized scaffolding
set only to BKP-A. Scaffolding set was lifted by operation from FCB Hisyam 6 onto BKP-A on 29th May 2023. On
15th June 2023, a total of three (3) pax mobilized to BKP-A (PL370 Receiving Side) via FCB Hisyam 6 for
scaffolding table erection scope of work. Three (3) pax of the manpower were bedding at MV Keyfield Falcon
from 15th June 2023 until 17th June 2023. Whereas for PL370 Launcher Side – BAP-B, four (4) pax mobilized to
BAP-B from 16th June 2023 for the scaffold table erection on daily basis until 17th June 2023 via FCB Centus 10.

For manpower demobilization, on 29th June 2023, a total of three (3) pax mobilized to BKP-A (PL370 Receiving
Side) via FCB Hisyam 6 for scaffolding table dismantle scope of work. Three (3) pax of the manpower were
bedding at BOCPP-A from 29th June 2023 until 2nd July 2023. Whereas for PL370 Launcher Side – BAP-B, four (4)
pax mobilized to BAP-B from 26th June 2023 for the scaffold table dismantle on daily basis until 28th June 2023
via FCB Centus 10.

Backloading scaffolding set for Bakau (BKP-A) was completed on 4th July 2023 via LCT MK1. Whereas,
backloading scaffolding set for Baram (BAP-B) was completed on 4th July 2023 via LCT MK10. (Refer to
Appendix A).
CLOSE OUT REPORT 5TH July 2023

PROVISION OF SERVICES FOR SCAFFOLDING ERECTION ACTIVITY P698/23/SKA/COR


TO ASSIST IP
HALUAN CEKAP SDN BHD Rev. 00
PL370: 12” X 12.268KM OIL LINE (BAP-B TO BKP-A)

4. SUMMARY SCOPE OF WORK (SOW)


Summary of job scope is as below:
Table 4.1: Summary of SOW
FINISH
No. ACTIVITY DATE REMARK
DATE
PRE-EXECUTION
Equipment mobilization from Serimas to BKP-A &
1 27/05/2023 30/05/2023 Completed
BAP-B.
2 Lifting activity at BKP-A & BAP-B. 29/05/2023 30/05/2023 Completed
Worksite preparation at BKP-A & BAP-B and
3 15/06/2023 15/06/2023 Completed
scaffolding erection.
EXECUTION
SCAFFOLDING ERECTION TO ASSIST IP PL370
1 PL370: 12” X 12.268 KM Oil Line (BAP-B to BKP-A)
Scaffolding table erection for PL370 at BKP-A & BAP-
1 16/06/2023 17/06/2023 Completed
B.
Dismantle scaffolding table for PL370 at BKP-A & BAP-
2 26/06/2023 30/06/2023 Completed
B.
POST-EXECUTION

1 Housekeeping 30/06/2023 30/06/2023 Completed

2 Backloading activity 04/07/2023 04/07/2023 Completed

Details of the summary execution activity can be referred to Appendix A – Daily Progress Report (DPR)

Lifting Activities
Lifting activities for materials placement (scaffolding sets) and toolbox were lifted at BKP-A and BAP-B main deck
by using Jib Crane 1.8MT. The materials were lifted on 29th & 30th May 2023. The scaffolding materials will be
transferred manually to the working locations.
CLOSE OUT REPORT 5TH July 2023

PROVISION OF SERVICES FOR SCAFFOLDING ERECTION ACTIVITY P698/23/SKA/COR


TO ASSIST IP
HALUAN CEKAP SDN BHD Rev. 00
PL370: 12” X 12.268KM OIL LINE (BAP-B TO BKP-A)

5. ORGANIZATION & MANNING

Pipeline Manager

Project Manager Wong Kang Yuon

Wan M. Hidayat

Pipeline Inspection Team


Lead
M Adnin B M A Aziz
Project Engineer
Ahmad Shahrul

Field Engineer Pipeline Engineer


Lee Kai Yang Felicia Supang Bujang

Scaffolder Inspector
Velintino David

Rigger
Henry Anak Ngelai
Kelvin Bin Jimy
CLOSE OUT REPORT 5TH July 2023

PROVISION OF SERVICES FOR SCAFFOLDING ERECTION ACTIVITY P698/23/SKA/COR


TO ASSIST IP
HALUAN CEKAP SDN BHD Rev. 00
PL370: 12” X 12.268KM OIL LINE (BAP-B TO BKP-A)

6. SAFETY STATISTIC
Items Description Cumulative
A HSE Statistics
Total Man Hours Worked 451
Fatality 0
Near Miss 0
Lost Time Injury (LTI) 0
Restricted Work Case (RWC) 0
Medical Treatment Case (MTC) 0
First Aid Case (FAC) 0
Occupational Illness (OI) 0
Fire / Explosion Case 0
Property Damage 0

B Unsafe Act / Unsafe Conditions


Unsafe Act 0
Unsafe Condition 0
Safe Act 10
Total: 10

C Meetings
Pre-mob Meeting 1
Toolbox Meetings Everyday

D HSE Enhancement Activities


CC Card Compliance – PTW Awareness & e-PTW 1
Escape Route & Mustering Station Briefing at site 1
PPE spot-check by PCSB Site Safety Executive 0
E Audit / Inspection
Equipment Inspection 0
Function Test on Equipment 0
Safety Walkabout at site 1
CLOSE OUT REPORT 5TH July 2023

PROVISION OF SERVICES FOR SCAFFOLDING ERECTION ACTIVITY P698/23/SKA/COR


TO ASSIST IP
HALUAN CEKAP SDN BHD Rev. 00
PL370: 12” X 12.268KM OIL LINE (BAP-B TO BKP-A)

7. QA/QC RESULT
Not applicable.

8. INSPECTION FINDINGS AND RECOMMENDATION


Not applicable.

9. PROJECT MAN-HOURS/PERFORMANCE ANALYSIS

No Description Manhours
1 Lifting Equipment at BKP-A & BAP-B 72
2 Worksite preparation at BKP-A & BAP-B 72
Scaffolding table erection / rigging activity to assist IP PL370 at BKP-A &
3 72
BAP-B
6 Dismantle scaffolding table at BKP-A & BAP-B 72
7 Housekeeping 72
8 Backloading 36
Others (including quarantine/stand-by/saliva test/mob/de-mob/FCB U-
9 55
Turn)
Total Manhours 451
CLOSE OUT REPORT 5TH July 2023

PROVISION OF SERVICES FOR SCAFFOLDING ERECTION ACTIVITY P698/23/SKA/COR


TO ASSIST IP
HALUAN CEKAP SDN BHD Rev. 00
PL370: 12” X 12.268KM OIL LINE (BAP-B TO BKP-A)

10. OUTSTANDING SCOPE OF WORK / PUNCHLIST


Not applicable.

11. MATERIAL MANAGEMENT – SURPLUS MATERIALS


No Descriptions Quantity Remark(s)
1. Scaffolding Tube 3 Meter 20 PCS
2. Scaffolding Tube 2 Meter 10 PCS
3. Scaffolding Planks 3 Meter 8 PCS
4. Double Clamp 40 PCS
5. Swivel Clamp 10 PCS
6. Single Clamp 25 PCS
7. Chain Block 2 Tonne 1 UNIT
8. Open Top Tray N/A

12. DROP SCOPE


Not applicable.

13. EMERGENT WORK / CONSTRUCTION WORK REQUEST (CWR)


Not applicable.
CLOSE OUT REPORT 5TH July 2023

PROVISION OF SERVICES FOR SCAFFOLDING ERECTION ACTIVITY P698/23/SKA/COR


TO ASSIST IP
HALUAN CEKAP SDN BHD Rev. 00
PL370: 12” X 12.268KM OIL LINE (BAP-B TO BKP-A)

14. LESSON LEARNT & BEST PRACTICES


This section includes the recommendations for future. Throughout the equipment mobilization, execution and
demobilization, some lesson learnt are captured and shared in this report.
Subject Issues Consequences Way Forward / Improvement
1. Contract/Purchase 1. No issue at site 1. No issue at site 1. QSM2 to confirm the validity of
order PO issued to HCSB to proceed
with execution – after long
period of pandemic

Pre-execution
1. Procedure 1. No issue at site 1. No issue at site 1. Site visit is required prior to job
2. Function Test 2. No issue at site 2. No issue at site execution activity.
2. Work scope to be firmed.
3. Function test to be done before
mobilization

Preparation
1. Mobilization of 1. No issue at site 1. No issue at site 1. Delaying mobilization of
equipment 2. No issue at site 2. No issue at site equipment will be affecting the
2. Lifting of 3. No issue at site 3. No issue at site schedule.
equipment to 4. No issue at site 4. No issue at site 2. For execution, lifting of
platform 5. No issue at site 5. No issue at site equipment must be prioritized
3. Mobilization of and movement of LCT need to
manpower be updated to avoid delay in
4. Laydown space activity.
area 3. Information regarding FCB
5. Equipment setup movement for the mobilization
and preparation of crew to be firmed
4. All contractor needs to discuss
and agree to allow the
execution for
priority/emergency job
5. Equipment and material
preparation should be done as
per schedule to ensure
execution not delayed.

Execution
1. Crew movement 1. No issue at site 1. No issue 1. Personnel transportation for
2. Project execution 2. No issue at site 2. No issue at site crew must be in good condition
3. during mobilization.
2. Work leader/PSS to ensure
work is completed as per work
pack before demobilization.

HSE No issue No issue 1. Alert to weather forecast


2. No boat transfer should be
allowed during bad weather
CLOSE OUT REPORT 5TH July 2023

PROVISION OF SERVICES FOR SCAFFOLDING ERECTION ACTIVITY P698/23/SKA/COR


TO ASSIST IP
HALUAN CEKAP SDN BHD Rev. 00
PL370: 12” X 12.268KM OIL LINE (BAP-B TO BKP-A)

15. CONCLUSION

Haluan Cekap Sdn Bhd is pleased to confirm the completion of Scaffolding Erection to Assist IP for PL370.
Haluan Cekap Sdn. Bhd is honored to be given the privilege to provide and serve PETRONAS Carigali Sdn Bhd
in this activity.

Completion of SKO Pipeline Baram & Bakau field to assist IP inspection was performed within the given
approved schedule to complete the activities.

Throughout the entire duration of the project, Haluan Cekap has never compromise the health and safety of
every personnel involved during the execution. We have undertaken some efforts to exercise HSE which
includes: -

a) Toolbox meeting every morning


b) Record and compile Unsafe Act Unsafe Condition (UAUC) found at site.

The exercise has brought zero LTI and zero incident/accident. In conclusion, this project has been completed
with satisfactory to both PETRONAS CARIGALI SDN.BHD and HALUAN CEKAP SDN.BHD.

16. APPENDICES

APPENDIX A: DAILY PROGRESS REPORT (DPR)


CLOSE OUT REPORT 5TH July 2023

PROVISION OF SERVICES FOR SCAFFOLDING ERECTION ACTIVITY P698/23/SKA/COR


TO ASSIST IP
HALUAN CEKAP SDN BHD Rev. 00
PL370: 12” X 12.268KM OIL LINE (BAP-B TO BKP-A)

APPENDIX A:
DAILY PROGRESS REPORT
(DPR)