Professional Documents
Culture Documents
Empirical Values
Empirical Values
999450402 en-GB
Empirical values
Time Fixtures,
for stop-ends
fitting-
zones
Contingency Allowances
allowance
ime
Basic time
m t
ys te
S
9720-011
2 999450402 - 04/2011
The Formwork Experts
Doka Knowledge Transfer Empirical values
Contents
4 Doka forming circle
5 Forming and assembly times
6 Grupp's calculated guide values for work time
9 Reinforcement
11 Concrete placement
12 Capacities
13 Annex
999450402 - 04/2011 3
The Formwork Experts
Doka Knowledge Transfer Empirical values
Time Fixtures,
for stop-ends
fitting-
zones
Allowances
Contingency
allowance
ime
Basic time
mt
y ste
S
9720-011
4 999450402 - 04/2011
The Formwork Experts
Doka Knowledge Transfer Empirical values
☞ Important note:
● Assembly time is the time for preassembling
individual system components to form a sys-
tem element, for example: Combining the
individual components of Top 50 beam form-
work on the reference flat.
● The times stated for the individual formwork
systems are guide times. Factors such as
training and experience of the workers, the
number of people available to undertake the
work, formwork height and shoring height,
weather conditions and on-site specifics all
extend the bandwidth.
● If you would like information on the individual
systems, do not hesitate to consult the con-
tact partners in the Project Management
department.
999450402 - 04/2011 5
The Formwork Experts
Doka Knowledge Transfer Empirical values
6 999450402 - 04/2011
The Formwork Experts
Doka Knowledge Transfer Empirical values
Guide values for work time for set- Guide work times for handset framed formwork
with 2 men, first cycle: Panel height 2.65 to 2.70, 2
ting up and stripping out formwork formwork ties over entire height
for walls Panel
Guide work times
[h/pc.] [h/m2]
Work with framed formwork subdivides Panel width 0.25 m 0,36 0,53
into: Panel width 0.50 m 0,40
● Forming up Panel width 0.75 m 0,48 0,24
- Clean the flat Longitudinal closure with closure
0,74
- Mark out walls plate
Longitudinal closure with wooden
- Set up panels filler
0,21
- Join panels Inside corner 90° 0,45
- Apply release agent Inside corner, articulated, without
0,60
- Install formwork ties wooden filler
- Set up rakers Filler for articulated corner 0,21
- Secure concreting scaffold Formwork lock 0,03
- Plumb formwork
Guide work times for handset framed formwork
● Stripping out
with 2 men, first cycle: Panel height 1.50 m, 2 form-
- Back off and remove ties work ties over entire height
- Break joins between panels Guide work times
- Reposition panels, large-area Panel
[h/pc.]
- Clean panels Panel width 0.25 m 0,27
- Stripping out after single-cycle use Panel width 0.50 m 0,29
- Remove scaffolding Panel width 0.75 m 0,30
- Back off formwork ties Longitudinal closure with closure plate 0,55
- Back off rakers Longitudinal closure with wooden filler 0,20
- Break joins between panels Inside corner 90° 0,34
- Remove each panel in turn and clean Inside corner, articulated, without
0,37
wooden filler
Filler with articulated corner 0,20
Guide work times for framed formwork, heavy-duty
Formwork lock 0,03
type, crane-lifted, first cycle: Panel height 2.65 to
2.70 m, 2 formwork ties over entire height
Guide work times for other jobs
Guide work times
Panel Guide work times
[h/pc.] [h/m2] [h/pc.]
Panel width 0.50 m 0,44 0,33 Door box-out in wood, approx. 2.0 m2 1,60
Panel width 0.75 m 0,53 0,26 Set door frame in steel, approx. 2.0 m2 1,75
Panel width 1.00 m 0,63 0,23 Window box-out in wood, approx. 1.5
Panel width 1.325 to 1.35 m 0,73 0,20 1,15
m2
Panel width 2.40 to 2.65m 1,19 0,18 Set prefabricated window, bedded in
0,25
Panel width 5.30 m 2,07 0,15 hard foam
Multipurpose panels (outside cor- End shuttering in wood, with
0,60 0,46
ner) site resources, height 2.65 m
Closure plate (longitudinal closure) 0,76 Longitudinal closure in wood, for walls,
0,21
Inside corner 90° 0,45 height 2.65 m
Inside corner, articulated 0,47 Install reinforcing rails, single and
0,20
double, l = 0.75 m
Filler for articulated corner 0,21
Tensioner, consisting of sleeve,
Formwork lock 0,03 DYWIDAG tensioning rod, 1 to 1.50 m, 0,19
2 wing nuts
Guide work times for framed formwork, heavy-duty Drive in plug 0,002
type, crane-lifted, multiple cycle: Panel height 2.65
to 2.70
Combination width Guide work times
[m] [h/pc.]
1,50 0,80
2,00 0,98
2,50 1,16
3,00 1,33
3,50 1,51
4,00 1,69
4,50 1,87
5,00 2,07
999450402 - 04/2011 7
The Formwork Experts
Doka Knowledge Transfer Empirical values
Guide work times for circular form- Working scaffolds and protective
work systems scaffolds (lightweight)
The times listed here apply to forming up and stripping Basic times:
out, plus application of release agent, for panels up to
● Install suspension loops in about 0.05 h/pc.
a maximum height of 3.00 m.
● Craneage averaging 0.075 hour (4.5 minutes).
Guide work times for use of various circular form- Repositioning the working platforms takes 2 people,
work systems the crane and the crane operator.
Guide work times
[h/pc.] [h/m2]
Worked example for calculating work time, postu-
Framed formwork as tangential polygon
lating 20 platforms and 60 suspension loops
Number Work time Total time
Framed panels, width approx. 0.21 to
[pcs.] [h] [h]
0.75 to 1.35 m 0.27
Suspension loops 60 60 · 0,05 3,00
approx. 0.18 to
Wooden closure Crane cycles (crane and
0.20 20 20 · 0,075 1,50
operator)
Formwork tie approx. 0.20
Work time 2 workers 20 · 2 · 0,75 3,00
Comparison, forming time
approx. 0.48 Total time 7,50
all-inclusive
Large-area beam formwork
Panel width approx. 2.50 approx. 0.20 to Working scaffolds and protective
m, including formwork ties 0.25
Preassembly and subse- scaffolds (heavyweight)
quent disassembly of the approx. 0.80
panels Basic times:
Comparison, forming time ● Install and remove suspension shoe, stud or slot-in
approx. 1.05
all-inclusive (for one cycle) shoe in about 0.17 h/pc.
5 cycles (assembly appor- ● Install and remove site covers in about 0.15 h/pc.
approx. 0.40
tioned)
Flexible circular formwork systems
● Engage and disengage single bracket in about
0.10 h/pc.
Panel formwork approx. 0.20 to
including formwork ties 0.25 ● Craneage averaging 0.075 hour (4.5 minutes).
approx. 0.18 to Repositioning the working platforms takes 2 people,
Wooden closure
0.20 the crane and the crane operator.
Adjust to curvature approx. 0.15
Comparison, forming time Worked example of calculating work time, postulat-
approx. 0.45
all-inclusive (for one cycle) ing 18 folding platforms (3.00 and 4.50 m), 41 sus-
5 cycles approx. 0.33 pension shoes and 5 site covers.
Tie-less circular formwork Unit time Total time
Number Designation
Panel formwork, width approx. 0.15 to [h/pc.] [h]
approx. 2.70 m 0.18 41 Suspension shoes 0.17 6,97
Preassembly and subse- 18 Crane cycles 3 · 0,075 4,05
quent disassembly of the approx. 0.95 5 Site covers 0,15 0,75
panels
Total time, first cycle and subsequent cycles 11,77
Comparison, forming time
approx. 1.10
all-inclusive (for one cycle)
5 cycles (assembly appor-
approx. 0.37
tioned)
8 999450402 - 04/2011
The Formwork Experts
Doka Knowledge Transfer Empirical values
Reinforcement
Allowances for reinforcement Installation
Build-sequence planning is prepared prior to structural It is now common practice to outsource reinforcement
planning on most projects. Consequently, a rough esti- work to subcontractors. The time outlay has to be esti-
mate has to be included at this phase so that an allow- mated for build scheduling and so that progress by the
ance can be made for reinforcement work.. subcontractor can be monitored. The unit of measure
for reinforcement placement is hours per metric ton.
Rule of thumb The average diameter of the rebar is the critical factor
Rate determining how fast the reinforcement can be
Structural component
[kg/m3]
installed. Average diameter is calculated from average
Columns 100 - 150
weight per running metre.
Walls 50 - 100
Slabs 50 - 100 Rule of thumb:
High-rise cores approx. 150 Diameter Rate
Bridge towers approx. 300 [mm] [h/to]
An empirical threshold for structural engineering (wall 6-8 30 - 50
formwork) is 100 – 180 kg/m³ for reinforcement. 10 - 12 20 - 30
14 - 16 15 - 20
18 - 20 10 - 15
24 - 40 8 - 12
The figures listed above apply when single rebars are
handled. For prefabricated rebar cages it is safe to
assume that the figures can be doubled.
Approximation:
One man can install one metric ton of rebar in a
shift (8 – 10 hours)
999450402 - 04/2011 9
The Formwork Experts
Doka Knowledge Transfer Empirical values
Reinforcement installed with crane Guide values for calculating useful capacity of
tower cranes of various sizes
Crane or cycle times depend on the following site-spe- Lower- Slewing Crane
cific and crane-related factors: Lifting Runner
ing speed travelling
Size speed speed
speed [rota- speed
● Lifting height [m/min] [m/min]
[m/min] tion/min] [m/min]
● Lowering depth Small 30 80 1.0 40 40
● Slewing angle Medium 70 100 0.8 30 30
● Slewing, lifting and lowering speeds Large 150 150 0.6 16 20
● Load-attachment times/times for filling the concrete
Operating factor: Matrix as simplified key to gaug-
bucket
ing the factor
● Operating factor
Machine (preparation,
● ... age, condition Very good Good Medium Poor
These points have to be taken duly into account in cal- Very good 1.0 0.9 0.8 0.7
culating exact cycle times. Good 0.9 0.81 0.72 0.63
Medium 0.8 0.72 0.64 0.56
Useful capacity in metric tons per hour [t/h] of an Poor 0.7 0.63 0.56 0.49
average tower slewing crane
Lifting height [m] Useful capacity [t/h]
10 24.16
20 21.90
30 20.00
40 18.32
50 16.93
60 15.74
70 14.70
80 13.80
90 13.00
100 12.28
Postulation:
Slewing angle: 180°
Lowering depth 5 m for each lift
Load lifted: 10 stock reinforcing mats AQ 70; 6 x 2.4 m; 6.04 kg/m²
Lifting speed: 75 m/min
Lowering speed: 100 m/min
Slewing speed: 0.8 U/min
10 999450402 - 04/2011
The Formwork Experts
Doka Knowledge Transfer Empirical values
Concrete placement
Placement rate Concrete mixers
Placement rates in m³/hour Capacities of truck mixers:
Info. Empirical ● 6 m3
Transported by Rule of thumb
contractor value
● 15 m3
Crane and bucket 10 8 - 15 10
Concrete pump 30 20 - 25 20
Conveyor belt 100 - - Truck mixer (6 m3)
94504-801
94504-802
999450402 - 04/2011 11
The Formwork Experts
Doka Knowledge Transfer Empirical values
Capacities
General Transport with container
Provision has to be made for unloading on site: Destination zones:
● Crane (from above) ● Middle East
● Forklift (side, from rear ● Far East
● Overseas
Transport by truck 20 ft container 40 ft container
Destination zone: Europe Length ≤ 5.90 m ≤ 12.00 m
Width ≤ 2.20 m ≤ 2.20 m
Articulated truck Abnormal load Height ≤ 2.20 m ≤ 2.00 m
Length ≤ 13.60 m > 13.60 m Payload ≤ 17 to 1) ≤ 26 to 1)
Width ≤ 2.45 m > 2.45 m 1) Varies from country to country, laws change frequently
Height ≤ 2.50 m > 2.50 m
Payload ≤ 24 to 24 - 39 to 1) Standard container
Complexity and addi-
tional costs:
● Approvals
Comment Standard ● Accompanying vehi-
cles
● Special traffic control
● Etc.
1) Varies from country to country, laws change frequently
94504-804
94504-803
94504-805
12 999450402 - 04/2011
The Formwork Experts
Doka Knowledge Transfer Empirical values
Annex
References
Literature:
● Doka internal
● Dopi tile, TOP50 formwork for Doka automatic climb-
ers (link in the "Empirical values" tile)
● Habison, R.: "Baubetriebslehre - Ausmaßermittlung,
Kostenschätzung, Baugerät, Organisation, Projekt-
management" (Construction economics – quantity
surveying, cost estimates, construction equipment,
organisation, project management), Manz Verlag,
1997
● "Schalungsatlas, Schalungssysteme und Einsatz in
der Praxis", (Formwork atlas, formwork systems and
use in practice) DI (FH) Peter Grupp, Verlag Bau +
Technik GmbH, 2009
999450402 - 04/2011 13
The Formwork Experts