3.4.

1 SELECT PROVISIONS OF THE the corresponding entities for construct, alter, repair, move,
NATIONAL BUILDING CODE OF the rerouting of the parts convert or demolish any
THE PHILIPPINES RA 6541 building or structure, or cause
Section 806. Size and Dimensions of the same to be done, shall
Section 1.01.03 – Scope of the Rooms as per RA6541. obtain a building permit from
National Building Code the Building Official for
a) Minimum sizes of rooms and
(a) The provisions of this their least horizontal whichever of such work is
Code shall apply to the dimensions shall be as follows: proposed to be undertaken for
design, location, siting,  Rooms for Human the building or structure,
construction, alteration, Habitations. 6.00 square before any such work is
repair, conversion, use, meters with at least started.
occupancy, maintenance, dimensions of 2.00 3.4.3 REQUIRED ARCHITECTURAL
moving, and demolition  Kitchens. 3.00 square PLANS FOR BUILDING PERMIT:
of, and addition to, public meters with at least
and private buildings and dimension of 1.50 meters;  Vicinity Map/Location Plan
structures.  Bath and toilet. 1.20  Site Development Plan
square meters with at  Perspective
General Requirements:
least dimension of 0.90  Floor Plans (not less than
 No part of any building or meters. 1:100)
structure or any of its  Elevations, at least four (4),
Section 807. Air Space Requirements same scale as floor plans
appendages shall project in Determining the Size of Rooms.
beyond the property line of  Sections, at least two (2)
the building site, except as a) Minimum space shall be  Reflected ceiling plan
provided in this Code. provided as follows:  Details, in the form of plans,
 The projection of any structure  School Rooms. 3.00 cubic elevations/sections
or appendage over a public meters with 1.00 square meter  Schedule of Doors and
property shall be the distance of floor area per person; Windows
measured horizontally from  Workshops, Factories, and  Schedule of Finishes
the property line to the Offices. 12.00 cubic meters of  Details of other major
outermost point of the space per person; Architectural Elements
projection.  Habitable rooms. 14.00 cubic
3.4.4 REQUIRED STRUCTURAL PLANS
meters of space per person.
Projection into Alleys or Streets. AND DETAILS FOR BUILDING PERMIT:
3.4.2 ACCESS AND EGRESS:
 No part of any structure or its  Foundation Plan
appendage shall project into  Every storey or portion  Roof Framing Plan
any alley or street, national thereof, having an occupant  Floor Framing Plans
road or public highway except load of 500 to 999 shall have  Foundation and Column
as provided in this Code. at least three exits. Details
 Footings located at least 2.40  Distance to Exits. No point in a  Floor Slab Details
meters below grade along building without a sprinkle  Roof Framing Details
national roads or public system shall be more than  Details of Beams and Girders
highway may project not more 45.00 meters from an exterior  Schedule of Beams, Girders,
than 300 millimeters beyond exit door, a horizontal exit, exit and Columns
the property line. passageway, or an enclosed  Other Structural Details
 Foundations may be permitted stairway, measured along the
to encroach into public line of travel. In a building 3.4.5 OTHER REQUIRED PLANS AND
sidewalk areas to a width not equipped with a complete DETAILS FOR BUILDING PERMIT:
exceeding 500 millimeters; automatic fire extinguishing  Electrical Plan with Schedule
provided, that the top of the system the distance from exits of Loads
said foundations is not less may be increased to 60.00  Plumbing Plans - Drainage &
than 600 millimeters below meters Water Supply (Hot or Cold)
the established grade; and
SECTION 1.02.03 – Building permits  Waste Disposal and Drainage
provided further, that said
Plans
projections does not obstruct
 Any person, firm, or  Mechanical Plans (If Any)
any existing utility such as
corporation, including any
power, communication, gas,
department, office, bureau,
water, or sewer lines, unless
agency of instrumentality of
the owner concerned shall pay 3.5 PEDESTRIAN PROTECTION DURING
the government intending to
CONSTRUCTION:
3.5.1 PROTECTION OF PEDESTRIANS shall be provided. The entire joints, valves, or fittings. Tests
DURING CONSTRUCTION OR structure shall be designed to shall be conducted by the
DEMOLITION carry the loads imposed upon owner of the building
it: Provided, that the live load contractor in the presence of a
Section 1101. General Requirement. shall be not less than 600 representative of the Building
 No person shall use or occupy kilograms per square meter.
3.7 NATIONAL BUILDING CODE
a street, alley or public 3.6 NATIONAL BUILDING CODE PROVISIONS FOR FOUNDATIONS:
sidewalk for the performance REQUIREMENTS ON FIRE SAFETY OF
of work covered by a building BUILDINGS:  MINIMUM THICKNESS OF
permit except in accordance FOOTINGS: 250 MM
with the provisions of this 3.6.1 Fire-Extinguishing Systems.  MINIMUM DEPTH OF
Chapter. a)Fire-Extinguishing Systems EXCAVATION FOR FOOTINGS:
 No person shall perform any When required, standard 0.60 M. FROM THE TOP
work on any building or automatic fire-extinguishing NATURAL GROUND LEVEL
structure adjacent to a public systems shall be installed in
way in general use for the following places, and in 3.8 WASHROOMS AND TOILETS BP
pedestrian travel, unless the the manner provided in this 344 requirement as per RA 6541:
pedestrians are protected as Code.  minimum of 1.70 x 1.80 m.
specified in this Chapter.  In every storey, basement or with grab bars
cellar with an area of 200  turning space of 2.25 sq.m.
Section 1106. Pedestrian Protection. square meters or more which with minimum of 1.50 m. for
 Protection Required. is used for habitation, wheelchairs shall be provided
Pedestrian traffic shall be recreation, dining, study, or outside closet stall.
protected by a railing on the work, and which has an
 minimum number of
street side when the walkway occupant load of more than
accessible water closets on
extends into the roadway, by a 20.
each floor level = 1 for every
railing when adjacent to  In all dressing rooms, 20 (total per floor) and 2 for
excavations. rehearsal rooms, workshops or more than 20
 Railings. Adequate railings factories, and other rooms
 maximum height of water
when required shall be built with an occupant load of more
closet = 0.45 m., flush control
substantially strong and than 10 or assembly halls
= 1.20 m.
should be at least 1.00 meter under Group H and I
 maximum height of lavatories
in height. occupancies with occupant
= 0.80 m. with knee recess
 Fences. Fences shall be built of load of more than 500, and if
0.60 to 0.70 m. vertical
an approved material, not less the next doors of said rooms
clearance and 0.50 m. depth.
than 2.40 meters in height are more than 30.00
above grade, and be placed on meters from the nearest safe
the side of the walkway fire dispersal area of the
nearest to the building site. building or opening to an exit
Fences shall enclose entirely court or street.
the building site. Openings in  In all rooms used for storage
such fences shall be provided or handling of photographic x-
with doors which shall be keep ray nitrocellulose films and
closed at all times. other inflammable articles.
 Canopies. The protective b) Dry Standpipes Every building
canopy shall have a clear four or more storeys in height
height of 2.40 meters above shall be equipped with one or
the railway, and shall be more dry standpipes.
structurally safe. Every canopy 3.7 Construction and Tests:
shall have a solid fence built
along its entire length on the  Dry standpipes shall be of
construction side. If materials wrought iron or galvanized
are stored or work is done on steel and together with fittings
top of the canopy, the edge and connections shall be of
along the street shall be sufficient strength to
protected by a tight curb withstand 20 kilograms per
board not less than 300 square centimeter of water
millimeters high and an railing pressure when ready for
not less than 1.00 meter high service, without leaking at the