METHOD OF STATEMENT
Title Description
Project Water sealing the toilet area to avoid leakage
M.O.S. Reference no. TPG-MOS1-SGP-2023
Arranged by: Engr. Abdullah Al-Qahtani
1. SCOPE
TPG is proposing this step-by-step procedure to water seal the area without removing the
existing tiles. The scope will cover the following:
1. Water sealing the tile areas.
2. Seal the connection between the water closets and the drainage pipes.
2|P ag e
2. Seal the connection between the water closets and the drainage pipes.
• Remove grimes and dirt on the pipes and drainage/sewage junctions.
• Ensure the area is totally dry (at least 24 hours).
• Apply the following materials proposed to seal the junction between the pipe
and the drainage/sewage lines.
o J-B Water Weld Or equivalent (Waterproof epoxy putty)
o The application will be based on technical data.
• For the junctions in between the water closets and the tiles, silicone will be
applied accordingly.
All material technical data will be provided to the client for approval prior to procurement
and delivery.
3|P ag e