You are on page 1of 10

Installation, Operation and Maintenance Manual

Double Block and Bleed Gate Valve


Table of Contents
INSTALLATION .................................................................................................................................. 1
Orientation .......................................................................................................................................... 1
Design ................................................................................................................................................ 1
Flow Direction ................................................................................................................................... 1
Clearance for Repair .......................................................................................................................... 1
Flange Fastener .................................................................................................................................. 1
Handling of Valves ............................................................................................................................ 2
Pressure Testing ................................................................................................................................. 3
Mounting of Gearbox/Actuator ......................................................................................................... 3
OPERATION ........................................................................................................................................ 3
Pressure Testing .................................................................................................................................. 3
Mounting of Gearbox/ Actuator .......................................................................................................... 4
MAINTENANCE .................................................................................................................................. 5
Troubleshooting .................................................................................................................................. 5
Seat Replacement ............................................................................................................................... 6
About Posiwell Double Block and Bleed Valve ................................................................................ 7
Exploded View of Posiwell Double Block and Bleed Valve ............................................................. 8
INSTALLATION
Table 1
Orientation Valve Number Recommend
Maximum
Size/Rating of Thread : Torque for
PosiWell® DBB Gate Valves may be Threaded UNC UNC
installed in any position; vertical position is Holes per Threads
Flange (Nm)
preferable. Either side of the valve can be
installed as the upstream end. 2”/150 4 ⅝" 97.4
3”/150 4 ⅝" 97.4
Design 4”/150 4 ⅝" 97.4

PosiWell® DBB Gate Valves design is 6”/150 4 ¾" 178


symmetrical. Independent disc ensures shut 8”/150 4 ¾" 178
off is achieved equally on both sides of
upstream and downstream. Full bore design 10”/150 4 ⅞" 279
minimizes pressure drop and allows 12”/150 4 ⅞" 279
passage of all types of scrapers (pigs).
14”/150 4 1" 418
16”/150 4 1" 418
Flow Direction 18”/150 8 1 ⅛" 593
PosiWell® DBB Gate Valves are equipped 20”/150 8 1 ⅛" 593
with Thermal Relief Accessories which is
required to be installed according to the 24”/150 8 1 ¼" 837
selected flow direction. 26”/150 8 1 ¼" 837
28”/150 8 1 ¼" 837
Clearance for Repair 30”/150 8 1 ¼" 837
PosiWell® DBB Gate Valves can be 36”/150 12 1 ½" 1456
overhauled right on the line without
excessive shutdown time. Therefore,
adequate space above the valve should be
allowed for removing parts and replaced
during troubleshooting.

Flange Fastener
PosiWell® DBB Gate Valves flange holes
are drilled and tapped when there is no
possibility of fitting a hexagonal nut behind
the flange.

1
Handling of valves
Proper lifting method must be adopted
accordingly to avoid damaging the valve.
Fibre Sling of right capacity is used to lift
via the DBB Valve’s Yoke as shown in
PITURE 1. Lifting Eye Bolts will be
provided on the Valve’s Bonnet to lift
bigger size valve.
The valve should be lifted in such a way
that the body supports the load.

CAUTION: NEVER use hand wheel or


other protruding parts of the gearbox or
actuator while lifting the valve. Also,
remove Clear Stem Cover Tube before
lifting.

Operator Disassemble:
1. To dissemble the valve, make sure that
stem is centre aligned before lifting.
2. Lift the yoke up slowly during
operation; stop if necessary chiefly to
avoid disc galling with parts especially
guide bars, handle with care placing the
bonnet after disassemble.
3. Once maintenance or repair is done, the
yoke is again lifted up and reassemble
accordingly.
Operator Reassemble:
1. Again, place the bonnet down slowly;
stop if necessary to avoid disc
knocking into other parts especially
guide bars. The discs will centrally-
aligned with the body with the aid of
guide bars.
2. Finally, tighten the Bonnet evenly with
recommended torque as shown in
TABLE 1.

2
OPERATION

PosiWell® DBB Gate Valves are designed Mounting of Gearbox/Actuator


with patented independent spring loaded
discs, seating design that compensate Following guidelines should be strictly
automatically when fluctuations of pressure followed to mount a gearbox or actuator on
and temperature occur; thus providing a valve minimizing any damages that could
positive proof of line segregation. occur to the valve.
With this in mind, in opening the valve, the NOTE: The guidelines provided are for
stem is raised, thus fully retracting the typical gearbox and actuator designs
double discs as it rises up to the fully open
position as shown in FIGURE 1. Specific instructions for each design should
be obtained from the gearbox or actuator
Correspondingly, in closing the valve, the manufacturer.
discs are driven down in fully retracted
position between the guide bars, with no 1. Make sure the actuator match the valve
seal-to-body contact until the discs are position (fully open or closed); adjust
positioned over the ports. to match the valve position before
In turn, the discs gate are fully expand to install.
form a tight mechanical closure against the 2. The actuator can be installed in
upstream and downstream seats as shown in multiple positions depending on the
FIGURE 3. Venting the body cavity will gear or actuator mounting kit. Make
provide total, tight shut off. sure the desires hand wheel and
actuator control panel position and
PosiWell® DBB Gate Valves are soft install accordingly based on
seated design and does not required high customer’s request or space provided
closing torque. in site.
3. Once the gearbox or actuator is
mounted, secure it with the appropriate
Pressure Testing bolts.
PosiWell® DBB Gate Valves can be
hydrostatically pressure-tested after
installation, to full API 6D limits.

3
FIGURE 1: Discs FIGURE 2: Discs FIGURE 3: Discs
are Retracted are still Retracted are Expanded in
in Fully Open in Close Position Fully Closed
Position Position

4
MAINTENANCE
To prolong the life of the valve and trouble-free operation, it is recommended to visually
inspect the valve and relief system half-yearly to prevent any abnormalities while operating the
valve. Repair and replace can be done immediately once problems are spotted.

Troubleshooting

Problem Probable Cause Method


The valve is not closed Operate the valve to fully closed position.
completely Block-and-Bleed the valve to insure that
the leakage has stopped.
There is a build-up in the Operate the valve to partially open
The seats are seat area due to line enabling the disc to retract and allow
leaking contaminates or debris. pressurized flow to flush off any trapped
contaminates. Repeat this for 2 to 3 times.
Seat is damaged Replace seat ring. Contact TRISOME for
assistance.

Stem screw or nut is loose Tighten the stem screw or nut tightly
enough to stop the leakage. Do not exceed
torque value for stem screw as shown in
The stem is Table 1. Operate the valve to make sure
leaking the stem is causing the leak.
The stem seal is damaged In most cases, leaks should stop after
above methods. If not, replace stem seal.
See Page 6. Contact Trisome for more
assistance.
Perform stem maintenance:
1. Inspect housing for damage and
wear.
The valve is Valve’s stem is not in good
2. Lubricate stem using approved
difficult to condition.
grease; apply grease on the Thrust
operate
Bearings and the valve’s stem.
(Recommended to perform
maintenance semi-annually).

5
PosiWell® DBB Gate Valves are designed Seat Replacement
for low maintenance and in-line repair that  1 set of Spare Seat Rings (2 pieces)
requires only minimal parts. Seats and other  1 off Bonnet Gasket
internal parts can be removed and replaced  1 off 4mm Allen Key
if necessary without excessive shutdown  Spanner to suit Bonnet Fastener
time.  Spark – Proof Hammer
With valve fully closed, seat leakage can be Operator Disassemble/Assemble:
verify via the Bonnet Vent/Bleed Valve.
Firstly, open bleed valve slowly to allow 1. Firstly, de-pressurized and drain off
cavity pressure to be relief. There should debris in the valve’s body cavity.
not be any leakage or continuous dripping 2. Later on, turn the valve to fully open
after the excess is drip off over some position and unfasten the bolting of
minutes. bonnet.
3. Lift the Bonnet up squarely (see
Continuous dripping indicate a seat leakage procedures on page 2) slowly and
if hand wheel is already tighten gradually move aside to allow room to access
until fully closed position. the lower body for seat replacement.
If leakage is confirmed, check 4. Allen key is used to remove the Seat
troubleshooting steps from Page 5. Holding Ring followed by the Soft
Seat Ring.
5. For now, replace the new set of Seat
Ring and tighten Seat Holding
Ring squarely. Likewise, Bonnet
Gasket is replaced as well.
6. Assemble the Bonnet back into the
body with caution. The Bonnet is
lowered slowly making sure it is
centrally aligned. In any event,
Bonnet Fasteners are hand
tightened. (Do Not fully tighten just
yet)
7. All in all, close the valve manually
to allow the disc to fully close
position. Fully Open and Close the
valve for a few times to allow
central-alignment of the Bonnet and
the Body.
8. Finally, fully tighten the Bonnet
with appropriate torque with
NOTE: When Posiwell is in Fully Closed partially open valve.
Position, the Thermal Relief Valve releases
any thermal expansion of the body liquid
back into the line, Relief is set at 25 PSIG.

6
About Posiwell ® Double Block and Bleed Valve

Locking Device
Indicator
A valve indicator is
inserted to enable user
to easily capture valve’s
position.

When the valve is not in


Vibration is a Fully Close Position, an
common issues for orange indicator is visible.
piping layout in
most installation.
Posiwell ® have
When the valve is in Fully
incorporated a Close Position, the orange
Hand-Wheel indicator is not visible.
locking devise to
secure the valve
especially at the
Fully Open position.
Resilient Seat (Fire Safe)
Posiwell ® is designed with
Gland Packing patented independent spring
loaded discs, patented seating
A packing gland is design that compensate
used around automatically when fluctuations
a valve stem to of pressure and temperature
prevent occur, thus providing positive
pressurized fluid proof of line segregation.
from escaping
during linear
motion of stem.

7
Exploded View of Posiwell ® Double Block and Bleed Valve

You might also like