HASSAN CAMBODIA PROJECT

Test Pile No.TP#2 BORED PILE DIA.1200 MM.


Test Load 2535 tons.
FIG. 2 TIME - LOAD CURVE
2750
2535 Ton
2500 Cycle 1
Cycle 2
2250
Cycle 3
2000
1690 Ton
1750
LOAD, (ton)

1500

1250

1000 845 Ton

750

500

250

0
0 30 60 90 120
TIME (hours)
0 30 60 90 120
0
-1.01 mm.
-0.52mm.
-2
-3.16 mm.
-4

-6
SETTLEMENT, (mm.)

-6.15 mm.
-8

-10

-12

-14
-13.91mm.
-16
Cycle 1
-18 Cycle 2
Cycle 3
-20
-20.29 mm.
-22
FIG. 3 TIME - SETTLEMENT CURVE