You are on page 1of 35

BUILDING TECHNOLOGY 4

WEEK 8

Ar. Don G. De Vera, uap


Covered under previous lecture:
• General Requirements
• Civil Works
•Excavation
•Backfilling and Compaction
• Concrete Proportion
• Estimate on Concrete Slab
• Estimate on Reinforced Concrete
• Estimate on Post and Footing
• Estimate on Rectangular Beam and Girder
• Estimate on Masonry
• Estimate on Cement Mortar
• Estimate on Plastering
• Estimate on Reinforced Concrete Hollow Blocks
• Estimate on Tie Wire for Concrete Hollow Blocks Reinforcement
• Estimate on Independent Footing
• Estimate on Lateral Ties
ESTIMATE ARCHITECTURAL
(TILE WORKS)
Given:
10x20cm glazed wall tiles
20x20cm unglazed floor tiles
cement for mortar
white cement for joint filler

1. Solve for wall area


A= 1.50x (5.00+3.00) = 12sq.m

Area of tiles .10x.20 = .02sq.m

divide wall area


12/.02 = 600 pieces 10x20 (4”x8” glazed tiles)

2. Same with floor tiles (A= 15sq.m) = 375 pieces

3. Solving for Cement Mortar


Total area of wall and floor = 12+15 = 27sq.m

Use table for cement mortar


Cement Mortar: 27x .086 = 2.3 or 3 bags
White cement filler: 27x.50 = 13.5 or 14 kg.
Given:
7.00x9.00
30x30 vinyl tiles

1. Solve for floor area


A= 7.00x 9.00 = 63sq.m

using 30x30 vinyl tiles

63sq.m x 11.11 = 700 pieces

Solve for the adhesive

63x .042 = 2.65 or 3 gallons


ESTIMATE ARCHITECTURAL
(Laminated Flooring/ Engineered
wood flooring)
Area for laminated application

Material Cost = 400/sq.m


Labor cost = 35% of material cost

Material Cost = 1200/sq.m Material Cost = 2500/sq.m Material Cost = 400/sq.m


ESTIMATE ARCHITECTURAL
(Wall Finishes/ Painting)
SKIM COAT
• Get the area of wall
• 20 kilos/bag = 7sq.m (rodela)
•Water application
•Rough/ fine
• No need for neutralizer (lason)

• 65 per sq.m/ labor cost


• emoltion – Davies penetrating (clear)

1st step: Remove oil and grease by detergent cleaning.


2nd step: Apply diluted BOYSEN® Masonry Neutralizer and let stand overnight
3rd step: Rough sand surface to remove efflorescence salts
Semi-gloss or flat latex
• area of wall
• Apply Masonry Neutralizer (lason) –
20sq.m/ gal
• water = 1 litter = 15litters of water
• Sanding of wall
• if application of skim coat no need of
neutralizer
• apply semi gloss or flat latex
• Plain – 25sq.m/ gallon
• Rough – 20 sq.m/ gallon

• 220 per/sq.m labor cost


• paint brush, tape, covering (provide cost)
Semi-gloss or flat latex
• area of wall
• Apply Acrytex Primer – 17sq.m/ gal
• Sanding of wall
• Reducer
• apply semi gloss or flat latex
• Plain – 25sq.m/ gallon
• Rough – 20 sq.m/ gallon

• 220 per/sq.m labor cost


• paint brush, tape, covering (provide cost)
Baseboard/ Cornice (varnish
or ducco Finish)
• Varnish
• linear meter of baseboard or cornice
• 200/ meter – labor cost

•Ducco Finish
• lacquer primer
• lacquer patty (2coats)
• Sanding
• Primer
• Sanding with water
• Top coat - Automotive lacquer 1000/
gal

• 220 per/sq.m labor cost


• Compressor, tape, covering (provide cost)
ESTIMATE ARCHITECTURAL
(Ceiling )
•Area/ 2.88 (Gypsum Board =
___quantity of boards

• Price 12mm Gypsum Board = 300


• Price 4.5mm Fiber Cement Board = 480

• Ceiling Framing – Direct Counting


• Double furring – spacing at 60x60
• 0.40x5meters standard length
• Php 71.00
• Carrying Channel – spacing at 1.00
meters
• carry gypsum board
• double furring/ the whole system
• 0.80x 5 meters standard length

• W-clip = Php 3.00


• Full threaded rod 10mmx 3.00 m =
Php150
•Gypsum screw (15 or 20cm) = 1box
1000pcs. = php300
• wall angle 0.50 (1”x1”3m) = Php 29.00

•Labor Cost = Php 300/sq.m


• Area
• + area of Cove

• Boral Powder – to cover up joints


• sanding
• Flat latex
•Labor Cost = Php 220/sq.m

STEEL
• Epoxy Primer
• Polytap (Masilya)
• Sanding
• Epoxy enamel (2coats)
• Labor = ex: 2k/ materials: 1K
ESTIMATE ARCHITECTURAL
(Doors and Windows )
Pocket Door = Php 45,000
ESTIMATE PLUMBING
3.00 meters commercial length
Check price for fittings
4.00 meters commercial length (Php250.00)
PVC pipe standard length: 3.00
meters

Pvc6". - 1643.88
Pvc4" - 837.60
Pvc3" -. 568.40
Pvc2". -. 293.29

Check price for fittings


ESTIMATE ELECTRICAL
TYPES OF CONDUIT

1. PVC (POLYVINYL CHLORIDE)

2. RSC (RIGID STEEL CONDUIT)

3. EMT (ELECTRICAL METALLIC TUBING)

4. IMC (INTERMEDIATE METAL CONDUIT)

5. FMC (Flexible Metal Conduit)

6. ENT (Electric Non Metal Conduit)


Standard size of conduit for installation of wire cable
SAMPLE PHOTO

PVC
RSC
EMT
IMC
FMC
ENT