You are on page 1of 15

Ensure enforcement of safety procedures in accordance with the approved HSE Plan.

Will be closely monitoring the site engineer’s strict implementation of the MS and Risk
Assessment, the use of proper tools and equipment to maintain safety, certifications of
equipment and their adherence to safety regulations, reporting of any unsafe work or
stopping work that does not comply with ES & H procedures.

HSE Officer
Monitor and control all HSE matters related to project team members and contractors in
ensuring that the Project is in compliance with the project requirement i.e. specification,
safety code, and other policies/guidelines related to the project. Participate in HSE Risk
Assessment and hold the relevant meeting, and workshops internally and with related 3rd
parties. Monitor and update the HSE risks register and ensure all mitigation plans are
strictly adhered to throughout the project execution.

Foreman
Mason
Carpenter
Laborers

II. Concrete Repair

All concrete repairs shall be done in accordance with the approved Method Statement
for Repair of Concrete 
Manual chipping of concrete honeycomb prior to repair
1.1 General
Particular Specifications for Concrete

1. Any defect noticed in concrete shall be rectified by methods approved by the


consultant and client.
2. This method statement shall be adopted when concrete defects are identified at the
site after post-concrete work inspection specifically after stripping of the formed
surface.

3. All materials to be used for repair works shall be submitted for approval thru
Material Transmittal.
4. All proprietary materials shall be used strictly in accordance with the
materials manufacturer’s instruction and/or recommendations.
5. Curing for Concrete Patchwork:
Polyethylene or plastic sheets shall be used to cover concrete patchwork. Unless
otherwise specified in the technical data sheets, curing shall be carried out for 2-3
days. If curing compound/membrane is used, they shall be compatible with the
repair products.
6. Store unmixed materials in a cool (preferably temperature-controlled)
environment, avoiding exposure to direct sunlight.
7. Keep equipment cool, arranging shade protection if necessary. It is especially
important to keep cool those surfaces of the equipment, which will come into
direct contact with the material itself.
8. Try to avoid application during the hottest times of the day, and arrange temporary
shading as necessary.

9. Make sufficient material, plant, and labor available to ensure that the application is
a continuous process.

 1.2 Identification of Defects

1. Surface Imperfections a. Blowholes b. Form tie rod/bolt holes, cone holds, and
voids

2. Honeycombs a. Honeycomb not exposing rebars; b. Deep honeycomb exposing


rebars
2.1 Honeycombs or Spalling (Reinforcement not exposed and within the
cover zone)
The impact from a heavy object, form stripping, poor vibration, and use of very
stiff concrete is some of the main causes of this kind of defect.
Surface Preparation
a. Attention to the full and proper preparation of the substrate is essential for
complete repair adhesion.
b. Mark out the affected area, then cut back the edge of the repair to a minimum
depth of 10 mm. Make several vertical and horizontal cutting for easy breaking of
concrete. Break out the repair area to remove all contaminated or damaged
concrete to a minimum depth of 10 mm, up to the pre-cut edge of the repair.
c. Fully expose any corroded reinforcement in the repair area and continue until
un-corroded steel is reached. It may be necessary to break out the concrete beyond
the original repair area in order to achieve this.
d. Oil and grease deposits are best removed by steam cleaning, detergent
scrubbing, or the use of a proprietary degreaser.
e. Fully clean the concrete and steel surfaces to remove laitance, the by-products
of corrosion, and other contaminants. This is most effectively achieved by
proprietary blast media, with particular attention required to both the rear face of
the bars and the edge of the repair. The steel bars should be cleaned to a uniform
bright condition and the edge of the repair should be ‘roughened’ to provide a
good mechanical key at the substrate interface.
f. Chloride-induced corrosion will further require high-pressure washing with
clean water after blasting to ensure complete removal of the corrosive elements.
Reinforcement Priming
a. Exposed steel reinforcement should be securely held in place to avoid
movement during the application, as this will affect the compaction, build, and
bond of the mortar.
b. Apply one full, unbroken coat of approved primer and allow drying before
continuing. If unsure about the continuity of the coating, apply a second coat and
allow drying.
Substrate Priming
a. For standard repair conditions, thoroughly soak with clean water and remove
excess. Apply approved substrate primer by scrubbing into the surface and allow
becoming tacky.
b. For priming in other conditions, apply the approved primer as per its current
instructions. 
Mixing and Application
a. It is essential that the approved material is thoroughly mixed and that the
temperature of the mixed material should be below the maximum allowable
temperature as per the approved datasheet.
b. Mixing and application shall strictly follow the approved product data.
c. If sagging occurs on vertical or overhead faces, the compound must be
completely removed.
d. The substrate must be reprised and compounded and then reapplied in layers of
reduced thickness.
e. Multiple layers can also be used to achieve the desired thickness and profile but
care must be taken to ensure consistency of inter-coat bond strength.
f. Where multiple layers are to be applied, the surface of intermediate layers
should be ‘scratch-keyed’ and cured with wet hessian. Further applications of the
fresh compound may be applied once the intermediate layer has reached its initial
set.
g. It can be finished by striking off with a straight edge and closing with a steel or
plastic float. Note that water can be drawn to the surface if ‘overworking’ with the
float occurs, and an unsightly finish may result.
h. Damp sponges or plastic floats may be used to achieve the desired surface
texture, but care should again be taken not to overwork the surface.
i. Curing of repaired areas should be carried out as soon as possible after the
surface has been closed.
j. Approved curing compound should be spray applied in accordance with its
current data sheet instructions.
k. In adverse conditions (e.g. windy conditions or ambient temperatures greater
than 30°C), supplementary curing in the form of polyethylene sheeting taped down
at the edges should be used.
2.2 Honeycombing or Spalling (Reinforcement exposed and beyond cover
zone) Impact, rebar space too close, loss of grout, poor vibration, and low slump
are some of the main causes of this kind of defect.
Surface Preparation 
a. Attention to the full and proper preparation of the substrate is essential for
complete repair adhesion.
b. Mark out the affected area, then cut back the edge of the repair to a minimum
depth of 10 mm.
c. Break out the repair area to remove all contaminated or damaged concrete to a
minimum depth of 10 mm, up to the pre-cut edge of the repair.
d. Fully expose any corroded reinforcement in the repair area and continue until
un-corroded steel is reached. It may be necessary to break out the concrete beyond
the original repair area in order to achieve this.
e. Oil and grease deposits are best removed by steam cleaning, detergent
scrubbing, or the use of a proprietary degreaser.
f. Fully clean the concrete and steel surfaces to remove laitance, the by-products of
corrosion, and other contaminants. This is most effectively achieved by
proprietary blast media with particular attention required to both the rear face of
the bars and the edge of the repair. The steel bars should be cleaned to a uniform
bright condition and the edge of the repair should be ‘roughened’ to provide a
good mechanical key at the substrate interface.
g. Chloride-induced corrosion will further require high-pressure washing with
clean water after blasting to ensure complete removal of the corrosive elements.
Reinforcement Priming
a. Exposed steel reinforcement should be securely held in place to avoid
movement during the application, as this will affect the compaction and bond of
the material;
b. Apply one full, unbroken coat of approved priming and allow drying before
continuing. If unsure about the continuity of the coating, apply a second coat and
allow drying.
Substrate Priming – water (standard repairs)
a. Priming with water should take place after the erection of the formwork.
b. Several hours prior to placing the approved substrate primer, the prepared
concrete substrates should be saturated, by filling the formwork.
c. With clean water. Immediately prior to the application of approved substrate
primer, any excess water should be removed via the drainage outlet, leaving the
substrate “saturated surface dry”.
d. Different substrate priming shall be selected and approved depending upon
defects like chloride-contaminated concrete etc. Application of the same shall be
done in strict accordance with the manufacturer’s instructions.
Formwork
a. Formwork should be constructed such that the unrestrained surface area of the
repair is minimized.
b. The formwork should be rigid and tight to the substrate to prevent grout loss.
Use of silicone sealant, or similar, is also advised around the edge of the
formwork.
c. The internal faces of the formwork should be sealed, using an approved release
agent, to ensure that water is not absorbed from the repair material by the
formwork.
d. The formwork should include suitable drainage outlets for pre-soaking and,
when filling the repair ‘bottom up’ (e.g. soffit repairs), should further include
provision for air-venting to release trapped air as pouring proceeds.
e. There must be suitable access points to pour or pump the mixed material in
place.
Mixing, Placing, and Curing
a. It is essential that mixing is done following the approved product data-sheet.
b. Limits of the repair geometry should be in accordance with that laid down in the
‘Design criteria’ section of the approved product data-sheet.
c. Placement should be a continuous process, to avoid the formation of a ‘cold
joint.
d. If placed by the pump, the pipeline should be ‘grouted’ with a rich cement
slurry or mortar, discharging such grout as waste.
e. Pumping of the mixed material should follow immediately after grouting has
been carried out.
f. Formwork should be left in place until the cured grouting area has reached a
self-supporting, compressive strength, or as otherwise advised by the Engineer.
g. Immediately after the formwork has been struck, all exposed faces of the repair
should be thoroughly soaked with clean water to remove residual traces of the
shutter release agent.
h. At ambient temperatures above 30°C supplementary curing in the form of
polyethylene sheeting, taped down at the edges, must be used.
3. Cracks
a. The dry/damp crack is identified as per structure elements as below:
b. Cracks equal to or larger than 0.20mm on External Walls and Side part of Base
Slabs c. On all other elements i. Non-structural Cracks equal or greater than (>)
0.20mm, but () 0.2mm
d. Wet Cracks: Wet cracks are the type of defects caused by faulty construction
work, especially in waterproofing work. 
3.1 Non-Structural Concrete Cracks
As the surface of concrete dries, water evaporates from the spaces between
particles. As this water dissipates, the particles move closer together, resulting in
the shrinkage of the concrete. Because the surface of a concrete slab is exposed to
air but the underlying concrete is not, concrete near the surface dries and shrinks at
a rate different from that of the underlying concrete. The underlying concrete acts
as a restraint to shrinkage, resulting in the cracking of the surface layer.
1.

Resin crack injection activity on the slab concrete Surface Preparation


a. Generally, surface preparation includes the removal of all loose surface
deposited material by a wire brush. The prepared areas must be free of dirt, oil,
and other contaminants & be thoroughly cleaned by dry air, oil-free compressed
air.
b. Remove from the substrate all traces of dust, oil, paint, laitance, and other
deleterious materials that might affect subsequent bonding.
c. Mark the defective area, V-cut to a minimum depth (as required by repair
material manufacturers) & break out the repair area to remove all contaminated or
damaged concrete.
d. Immediately prior to the application of repair material, the prepared substrate
should be cleaned with oil-free compressed air.
Priming
Water Priming: Soak the substrate with clean water.
Excess water shall be removed and leave the substrate in a saturated surface dry
condition. More soaking time is required for poor-quality concrete.
For large structural repair, soak the substrate for several hours after the installation
of the formwork.
Mixing/Application/Finishing/Curing
a. Pre-packed repair materials shall be mixed as per the manufacturer’s
recommendation.
b. Apply repair material and allow to partly set before finally trowelling to a
smooth finish. In any case, follow the manufacturer’s manual.
c. Curing is not generally required but in extreme drying conditions, must be
placed within 30 minutes after mixing and placement are done in a continuous
process to avoid cold joints.
d. Removal and repair of exposed surfaces and curing shall be carried out as
per the manufacturer’s recommendation.
e. Thickness applied shall be as per manufacturer product data-sheet finish using
steel or plastic float.
f. Damp sponges can also be used to achieve the required surface texture.
g. Proper curing by means of wet hessian cloth covered by polythene sheet or use
approved applicable curing materials as per manufacturer’s recommendation.
h. Inspection Request shall be submitted after completion of works.
3.2 Structural Concrete Cracks
The impact from heavy objects, early stripping of formworks, or shoring and
disturbance while at the initial setting of concrete are some of the major causes of
this type of crack. All the Structural cracks (cracks more than 0.2mm width) which
are beyond the reinforcement zone or through cracks larger than 0.2mm width, the
injection will be carried out by approved material and after successful completion
of the injection, all the packers will be removed and the surface will be finished by
approved material. 
Crack injection shall be done as follows:
a. Remove surface laitance and contaminants from a bond 50 mm wide centered
on the crack, using power wire brushing or high-pressure air jetting. Identify the
nature of the crack and investigate the extent and magnitude of the crack by
making a V-groove cut 25 mm deep along the crack line. Remove surface dust &
laitance by high-pressure air jetting.
b. Surface cracks extending to bar reinforcement and excess of 0.2 mm in width
and 25 mm in depth shall be injected by a low-viscosity epoxy resin.
c. If packers are being used, drill holes along the center of the crack to accept the
packers. The centers should be 1-1.5 times the depth of the crack, but not more
than 200 mm.
d. Surface Preparation:
     1. Clean the surface and remove all traces of dust, oil, paint, curing compounds,
grease, corrosion deposits, algae, or any unsound material.
    2. The surface should be preferably prepared by using high-pressure water
jetting or light abrasive blasting, followed by thorough washing to remove dust
and remaining particles.
    3. Oil and grease deposits are best removed by steam cleaning, detergent
scrubbing or the use of a proprietary degreaser.
e. Mixing:
    1. The hardener and the base resin should be thoroughly mixed manually until
the liquid becomes clear.
    2. Crack injection material should be used with standard injection equipment
having closed containers at an injection pressure of 0.4N/mm² (4 bar).
    3. Mix only sufficient material that can be used within the pot life of the
material. (Refer to Technical Data Sheet).
f. Application:
    1. Crack injection material should be injected using standard injection
equipment having closed containers.
    2. Injection packers should be inserted into the pre-drilled holes at intervals
along the length of the crack. The distance between each packer shall depend on
the length and width of the crack.
    3. If practical, seal the surface of the cracks between the packers with approved
sealer material, 30 to 40 mm wide and 2 to 3 mm thick. Both sides of the cracks,
which lead through a wall or slab, shall be sealed this way. If the water flow is
severe the sealer application can be omitted.
    4. In case of a wall or slab which is cracked all the way through, packers shall
be located on both sides with those at the back placed at midway points between
those at the front.
    5. One end of the injection hose shall be attached to the lowest packer on
vertical cracks or to either end of horizontal cracks.
    6. Each crack shall be treated in a single continuous operation and sufficient
material shall, therefore, be made prior to the commencement of the work.
    7. Remove the packers or nipples and make good any holes or voids with sealer
and allow curing. The sealer can then be ground off or softened with a blowlamp
and peeled off. Make sure that it does not burn.
    8. Upon completion of the injection works, the injection system shall be allowed
to cure for 24 hours and shall be left undisturbed for this time.
Crack Repair by Gravity Feed:
a. Clearly, mark the cracks to be repaired.
b. Rake the crack to widen it to a minimum of 5mm wide and 10 mm deep.
c. Clean the crack with compressed air/air blower to remove loose deposits and
fine dust.
d. Use a stopper on both sides of the crack using a sealant or cement sand mortar
or sealant to create a reservoir.
e. After preparing the surface, mix Crack injection material as per the instructions
given in the product datasheet. If the cracks run all the way through the underside
of the slab/beam, seal the underside of the crack with sealer. Allow sealer to
cure for a minimum of 12 hours.
f. Pour the mixed material (within the pot life of the resin) over the top of the
crack and allow it to penetrate. Keep filling the cracks until they will no longer
accept resin. For flood coat applications, distribute the resin evenly over the
surface initially and then puddle the resin over the cracks. On smooth surfaces, use
wire brushes or rollers to promote penetration.
g. Inspect the filling. Look for signs of penetration such as air bubbles escaping
from the cracks as the resin displaces the air. ALLOW TIME FOR
PENETRATION. Twenty to 30 minutes should be a minimum. Also, be aware
that several minutes may pass before the resin has fully penetrated tight cracks and
more resin may still be required.
h. Once all cracks have been filled to refusal, remove the excess surface resin with
a flat rubber squeegee.
i. After the grout has fully cured, remove the sealant/sand mortar stopper and
grind smoothly.

2.  Form Tie Rod/Bolt Holes/Cone Holes and Voids


a. Probable Cause/s: Sleeves, Insufficient curing
b. Make sure that the substrate surface must be free from oil, grease, or any
loosely adherent material; a. If the concrete surface is defective or has laitance, it
must be cut back to a sound base; b. Bolt holes or fixing pockets must be blown
clean of any dirt or debris
c. Bearing Plate/Base Plate a. The underside of the base plate should be clean and
free from oil, grease, rust, scale, or other loosely adherent material; b. It may be
necessary to provide air pressure relief holes to allow venting of any isolated high
spots; c. If leveling shims are to be removed once the approved grout has
hardened, then they should be pretreated with a thin layer of grease.
d. Formwork – General
      1. Before fixing any formwork, ensure that the area to be grouted is clean.
      2. The formwork itself must be constructed to be leakproof, to prevent any
possible grout loss. This can be achieved by using a foam rubber strip or mastic
sealant beneath the formwork, and at any joints in the formwork. It shall, however,
also be provided with drain holes and plugs.
     3. The formwork should also be constructed in such a way as to keep the
final, unrestrained surface area of the grout to a minimum, to avoid problems with
cracking at a later stage.
    4. It should be fixed in such a way as to allow easy stripping, without causing
damage or distress to the grout – particularly if this is to be done whilst the grout
is still green.
    5. All dirt and debris are to be removed from the grout area before the last piece
of formwork is fixed, to facilitate pre-soaking.
e. Formwork – Geometry a. Pouring side: Set up so that grout will be poured the
shortest distance across the base plate. Erected a maximum of 150 mm from the
base plate edge. Erected a minimum of 150 mm higher than the underside of the
base plate. b. Open Side: Set up directly opposite the pouring side. Erected a
maximum of 50 mm from the plate edge. Erected a minimum of 25 mm from the
underside of the plate. c. Flanking Sides: Set flush with the plate edge. Close
attention to, the grout tightness” of the formwork.
f. Pre-Soaking a. All concrete surfaces within the formwork area should be
saturated with clean, fresh water for several hours prior to grouting. b.
Immediately before grouting takes place, any free water should be removed.
Particular care should be taken to blow out all bolt holes and pockets.
g. Mixing a. Mixing shall be done as per the approved repair material technical
data sheet.
h. Placing
     1. It is essential that the machine mixing capacity, material supply, and labor
availability are adequate to enable the grouting operation to be carried out
continuously. This may require the use of a holding tank, with provision for gentle
agitation to maintain fluidity;
    2. Immediately prior to placement, the mixed grout should be briefly agitated to
release any surface tension.
    3. Placing shall be done depending upon the thickness of the filling referring to
approved product data.
    4. Any bolt pockets must be grouted prior to grouting between the substrate and
the base plate.
    5. Continuous grout flow during the grouting operation is essential. Sufficient
grout must be available prior to the start, and the time taken to pour a batch must
be regulated to the time taken to prepare the next one.
    6. The mixed grout should be poured only from one side of the void to eliminate
the entrapment of air or surplus pre-soaking water.
    7. The grout head must be maintained at all times so that a continuous grout
front is achieved.
    8. When the grout reaches the open side of the formwork and rises above the
underside of the base plate, pouring should continue slowly down the length of the
base plate until completed.
i. Finishing a. Wherever possible unrestrained “shoulders” are to be avoided.
These have a tendency to crack and/or deboned, due to their unrestrained nature; b.
The gap between the perimeter formwork should not exceed 150 mm on the
pouring side and 50 mm on the opposite side. It is advisable where practical to
have no gap at the flank sides.
j. Curing On completion of the grouting operation, all exposed areas of grout
should be thoroughly cured. Using approved curing compound, continuous
application of water and/or wet hessian.
k. In summary along with the standard practice, methods described by the
approved manufacturer shall be followed strictly.
3. Filling of Core Holes
a. Prepare the core hole by removing dust, loose particles, grease, oil, and traces of
foreign materials which may affect the adhesion of the mortar on the concrete.
b. Wash the area with water by copiously spraying just a few hours before the
application of the mortar. At the time of application, the area should be free from
water but still damp.
c. Mixing of the repair material shall be done as per the manufacturer’s technical
datasheet.
d. Place the approved micro-concrete or approved repair material inside the hole
by gravity pouring and use a trowel for better finishing.
e. Upon filling the hole, the surface should be kept moistened by curing it with
cool water for 3 days. Protect the surface from wind or excessive heat or properly
secured plastic sheeting during the curing period.
f. If required, formwork shall be provided based on site need as specified in
“Formwork – General” and “Formwork – Geometry”. Note: These steps are for
guidelines only. The manufacturer’s specifications/instructions supersede the
above steps.
4. Pinholes and Blowholes
Probable Cause/s: Insufficient Vibration, High W/C Ratio
a. Attention to the full and proper preparation of the substrate is essential for
complete repair adhesion.
b. The substrate should further be ‘roughened’ to remove excess laitance, to
expose pinholes & blowholes, and to provide a mechanical key for subsequent
application of approved material. This is most effectively achieved by the use of
proprietary blast media, such that the fine aggregate is exposed but not polished.
Where preparation techniques result in voids of greater than 10 mm depth,
alternate methods,s and materials shall be used as an approved material data sheet.
c. Immediately prior to the application of approved material, the prepared substrate
should be blown clean with oil-free compressed air.
d.Substrate priming shall be done following the procedure mentioned in an
approved material-technical datasheet. Small quantities (up to 5 kg) can be mixed
manually but large quantities of special tools referring to the manufacturer’s
procedure shall be obtained and used.
e. The application of repair material shall be done strictly in accordance with the
manufacturer’s datasheet.
f. Curing shall be followed according to the manufacturer’s specifications.

5. Removal and Repair of Construction Temporary Embedments


All temporary construction embedments such as temporary mechanical or
electrical sleeves, block-outs, etc. shall be removed and repaired using suitable
approved repair materials and as per the manufacturer’s recommendation.
a. After removal of any temporary embedments, remove any loose areas, laitance,
and any foreign materials that will affect the bonding of repaired materials.
b. If the embedded item reached the location of reinforcement, ensure to remove
any rust formation not only on the exposed surface but also on the rear side of the
reinforcement bars.
c. Apply corrosion treatment prior to starting the repair.
d. Proceed with the application of approved suitable materials as required.
e. Curing shall be done as per the approved curing process or as recommended by
the manufacturer.

III. Risk Assessment Please refer to the attached document in Appendix B.

IV. Permit and Licensing Requirements Necessary permits shall be obtained.

V. Drawings, Diagrams, Maps, and Survey Data sketches shall be attached to the


submitted INR.

VI. Pre-Start Safety Briefing Arrangements Refer to Risk Assessment in Appendix B.

1. Protective and Safety Equipment All workers Involved shall be equipped with
adequate PPE as stated below: a. Safety Helmet with Company Logo b. Safety
Boots c. High Visibility Vest d. Safety Goggles e. Face Mask f. Hand Gloves g.
Coveralls

2. Information to Personnel a. Safety Induction b. Job training c. Superintendents


Notices/Memos d. Toolbox talks e. STARRT Card
3. Special Safety Requirements
a. All necessary personal/protective equipment (PPE) be provided.
b. Banksman, wearing distinctive vests, shall be assigned to help operators
maneuver their equipment.
c. The equipment operators shall possess the required licenses and certificates.
d. Generated dust shall be controlled by periodic water spraying.
e. The project safety officer is responsible along with the project zone site
engineer for ensuring that all operations are carried out with due regard to the
safety of all project personnel & property.
f. All working activity shall comply with Client Safety Procedure.
g. First Aid Material.
h. General management of protection/operation hazards is to be observed.
i. In case of working at night, please refer to Method Statement for Night Works
4. Emergency Procedures The Flow Chart below shows the Emergency Contact No.
during work:

5. Emergency Contact Numbers


Supervision and Monitoring Arrangements
Construction Manager
He is in charge of all construction activities. Schedule the project in logical steps
and budget the time required to meet deadlines. Inspect and review projects to
monitor compliance with building and safety codes and other regulations.
Site Engineer
The Site Engineer shall evaluate the number of materials consumed by each trade
to be compared against the planned quantity.
Site Foreman
A construction foreman is responsible for supervising the workers and also doing
actual construction work. The foreman monitors employees to ensure that the
work is done efficiently and within quality standards.
QA/QC Engineer
The QA/QC Engineer shall monitor whether the installation works are conforming
to the required quality otherwise he shall notify the Site Engineer should he find
nonconformance to the ongoing activities. The Site Engineer shall immediately
rectify the work to avoid receipt of NCR from the QA/QC Engineer.
HSE Engineer
The Safety Engineer shall be full-time at the site and shall frequently visit all the
ongoing works at the site. All safety violations and on-conformance of the HSE
Plan shall be registered and immediate action shall be done in coordination with
the Site Engineer.
HSE Officer
Monitor and control all HSE matters related to project team members and
contractors in ensuring that the Project is in compliance with the project
requirement i.e. specification, safety code, and other policies/guidelines related to
the project. Participate in HSE Risk Assessment and hold a relevant meeting, and
workshop internally and with related 3rd parties. Monitor and update the HSE
risks register and ensure all mitigation plans are strictly adhered to throughout the
project execution. Note: Site Engineers / HSE Staff shall have access on-site to
each MS/RA. Consultants will monitor activities on-site based on the MS/RA. XI.
Environment and Quality Issues
6. Precautionary Measure All precautionary measures shall be briefed to all workers
prior to commencing activity
7. Disposal Requirements All waste shall be disposed of as per the Construction
Environmental Management Plan and as per Government approved disposal areas.

VII. Inspection, Test, and Sampling


Request for Inspection and Testing will be submitted prior to and after execution of
works.

VIII.Quality Assurance Requirements Table


Refer to the Project Quality Plan
a. Project Specifications

IX. Attachments
References (attach here)
Documentation (attach here)
Project Specifications (attach here)
Appendices:
Appendix A-Material Technical Data Sheet (attach here)
Appendix B-Risk Assessment
Appendix C-Inspection and Test Plan

You might also like