UB/GOMC/2014/414
14/10/2014
To :
From :
CC :
Subject :
1. Total Mechanical Expenses (KSA):
Mechanical expense for the month of Sep-14 was recorded at 11.21 SAR/mᶟ, i.e. 0.45 SAR/mᶟ more than month of Aug-14. Also
decrease in production to 76,930 m3 in comparison to Aug-2014, the total expenses has recorded SAR 862,503 in the month
of Sep-14.
Average Operating Cost for Workshop was recorded at 9.08 SAR/mᶟ which is 0.14 SAR/mᶟ more than the allocated
budget (Source Account report).
Average operating Cost of Batching Plant was recorded 2.13 SAR/Mᶟ for month of Sep-14 which is 1.42 SAR/Mᶟ less than
the allocated budget (Source Account report)
Average Mechanical Operating Cost for Jeddah, Makkah, Sulay and CRCC were recorded at 15.20 SAR/Mᶟ, 11.94 SAR/Mᶟ,
11.25 SAR/Mᶟ and 8.33 SAR/Mᶟ respectively in the month of Sep-2014.
Average Operating Cost recorded by the transit mixer in KSA for the month of Sep-14 were 5.33 SAR/mᶟ. However, the
Average Operating Cost of Transit mixer recorded for Jeddah, Makah, Sulay and CRCC are 5.26 SAR/mᶟ, 6.79 SAR/mᶟ, 4.79
SAR/mᶟ and
5.98 SAR/mᶟ respectively.
Expenses recorded by the Mobile Pumps in Jeddah, Makah, Sulay and CRCC were 4.01 SAR/Mᶟ, 1.04 SAR/Mᶟ, 3.30 SAR/Mᶟ and
0.51 SAR/Mᶟ, in Sep-14 respectively.
Expenses incurred by Batching Plant has increased to 2.13 SAR/Mᶟ in Sep-14 as compared to 2.05 SAR/Mᶟ in Aug-14 also
decrease in production compare to Aug-14.
Average Operating Cost of Batching Plant for different locations: Jeddah, Makah, Sulay and CRCC are 4.29 SAR/Mᶟ, 2.42 SAR/Mᶟ,
1.88 SAR/Mᶟ & 1.32 SAR/Mᶟ respectively.
Ref. No. UB/GOMC/2014/414
14/10/2014
1 TRANSIT MIXER 9330 UZA CRCC141097 720 CRCC 29,004 Engine overhauling done / injector repaired
Gear box overhauling / clutch calibration carried
2 42 meter 1018 SKA SLY143676 472 Sulay 23,045
out & sensor was replaced.
Engine overhauling done / oil pump assembly &
3 TRANSIT MIXER 1159 NZA SLY143605 492 Sulay 22,812
clutch plate has been replaced
Top Engine overhauling done / concrete
4 TRANSIT MIXER 9114 ENA CRCC141054 301 CRCC 15,462
breaking done.
5 TRANSIT MIXER 6909 GKA MAK141033 350 Makkah 12,749 Site Breakdown / fan hub belt broken
Engine Overhauling done / checked electric
6 TRANSIT MIXER 2976 RAB SLY143604 264 Sulay 11,731
wiring & repaired.
Second time engine top overhauling / liner
7 TRANSIT MIXER 4558 XAB CRCC141089 281 CRCC 9,522
changed
Gera box replaced / Clutch booster & pressure
8 TRANSIT MIXER 2126 AZA SLY143598 472 Sulay 7,981
plate replaced.
9 TRANSIT MIXER 3750 DNA MAK141060 424 Makkah 7,414 Injector worn out / injector changed.
10 TRANSIT MIXER 5816 EZA MAK141013 324 Makkah 4,366 Gear box overhauling done.
(Source: job card)
Highest Expense recorded against transit mixer – 9330 UZA (TM-295) CRCC with expense of 29,004 SAR & down time 720 hr.
in Sep- 14 due engine overhauling required & injector repaired from outside. (CRCC141097)
Pump- 1018 SKA (P-51) Sulay was recorded with down time 472 Hr correspondence to expense SAR 23,045 in the month
of Sep- 14 due to gear box bell housing broken & gear box overhauling required also clutch calibration carried out &
sensor was replaced. (SLY143676)
Transit Mixer (TM-292) 1159 NZA Sulay was recorded with down time 492 Hr & expense of SAR 22,812 in the month of Sep-
14 due to engine overhauling , during its repair oil pump assembly & clutch plate has been replaced which was cost SAR
1,051 (I056812) & SAR 1,100 respectively other expense for machining work & other spare parts etc. (Job card no: SLY143605).
Expense recorded against Transit Mixer TM-280 (9114 ENA) CRCC with expense of 15,462 SAR & down time 301 hr. in Sep- 14
due to engine over heat after engine dismantling & inspection it was found that top overhauling required. Also concrete breaking
was done during the repair
Transit Mixer (TM-423) 6909 GKA Makkah was recorded with down time 350 Hr & expense of SAR 12,749 in the month of
Sep-14 due to site breakdown & it was observed that fan hub belt was broken in the site also brake pad & crank shaft
front seal was changed (MAK141033)
Expenses on TM in Sep-14 has decreased to 5.33 SAR/Mᶟ compared to 5.33 SAR/mᶟ in Aug-14 & it has been observed
that availability of transit mixer was 89% in the month of Sep-2014.
ef. No. UB/GOMC/2014/414
14/10/2014
3.2 TM Mechanical Expenses breakup-Drum Capacity
Transit Mixer Expenses (Sep-14)
Aug-14 Sep-14
Mechanical Expenses (SAR) Produc
Drum
Nos. Outsid tion SAR/ SAR/T Availability SAR/ SAR/ Availabilit
Cap Spares Lubes Tyre's Total
e (m3) 3 M (%) TM y (%)
m m3
9 M3 30 35,165 5,862 15,602 7,187 63,815 9,184 7.30 3,721 89% 6.95 2,127 84%
10 M3 30 90,804 6,851 10,629 18,803 127,087 11,931 10.85 6,034 85% 10.65 4,236 87%
12 M3 68 133,960 25,056 51,455 8,400 218,871 55,815 3.93 4,396 90% 3.92 3,219 93%
Total 128 259,928 37,769 77,685 34,390 409,772 76,930 5.47 4,622 89% 5.33 3,201 89%
SAR/TM 2,031 295 607 269 3,201
SAR/m3 3.38 0.49 1.01 0.45 5.33
(Source: Job card)
The majority of expenses were incurred on spare parts i.e. 63% of the total expenses followed by the Tyre expenses 19%,
Lube expenses 9% & outside repair expense 8% of the total expenses in the month of Sep-14.
Expenses on10 Mᶟ Transit Mixer for the month of Sep-14 has decreased to 10.65 SAR/m3, compared to 10.85 SAR/mᶟ in Aug-
14 & expense was 31% of total expense.
Expenses for 9 M3 TMs has slightly decreased to 6.95 SAR/Mᶟ in Sep -14 compared to 7.30 SAR/Mᶟ in Aug -14 & 16% of
total expense.
Expenses on 12M3 Transit mixer was recorded 3.92 SAR/Mᶟ in Sep-14 compared to 3.93 SAR/Mᶟ in Aug-14 & 53% of total
expense.
Expenses on Per Transit Mixer was recorded 3,201 SAR/TM in the month of Sep-14 compared to 4,622 SAR/TM in Aug-
14 because of total expense on transit mixer was decrease in compare to aug-14.
1 TRANSIT MIXER 9330 UZA CRCC141097 720 CRCC 29,004 Engine overhauling done / injector repaired
Engine overhauling done / oil pump assembly
2 TRANSIT MIXER 1159 NZA SLY143605 492 Sulay 22,812
& clutch plate has been replaced
Top Engine overhauling done / concrete
3 TRANSIT MIXER 9114 ENA CRCC141054 301 CRCC 15,462
breaking done.
4 TRANSIT MIXER 6909 GKA MAK141033 350 Makkah 12,749 Site Breakdown / fan hub belt broken
Engine Overhauling done / checked electric
5 TRANSIT MIXER 2976 RAB SLY143604 264 Sulay 11,731
wiring & repaired.
Second time engine top overhauling / liner
6 TRANSIT MIXER 4558 XAB CRCC141089 281 CRCC 9,522
changed
Gera box replaced / Clutch booster &
7 TRANSIT MIXER 2126 AZA SLY143598 472 Sulay 7,981
pressure plate replaced.
8 TRANSIT MIXER 3750 DNA MAK141060 424 Makkah 7,414 Injector worn out / injector changed.
Highest Expense recorded against transit mixer – 9330 UZA (TM-295) CRCC with expense of 29,004 SAR & down time 720 hr.
in Sep- 14 due engine overhauling required & injector repaired from outside. (CRCC141097)
Transit Mixer (TM-292) 1159 NZA Sulay was recorded with down time 492 Hr & expense of SAR 22,812 in the month of Sep-
14 due to engine overhauling , during its repair oil pump assembly & clutch plate has been replaced which was cost SAR
1,051 (I056812) & SAR 1,100 respectively other expense for machining work & other spare parts etc. (Job card no: SLY143605).
Expense recorded against Transit Mixer TM-280 (9114 ENA) CRCC with expense of 15,462 SAR & down time 301 hr. in Sep- 14
due to engine over heat after engine dismantling & inspection it was found that top overhauling required. Also concrete breaking
was done during the repair.
Ref. No. UB/GOMC/2014/414
14/10/2014
Transit Mixer (TM-423) 6909 GKA Makkah was recorded with down time 350 Hr & expense of SAR 12,749 in the month of
Sep-14 due to site breakdown & it was observed that fan hub belt was broken in the site also brake pad & crank shaft
front seal was changed (MAK141033)
Highest down time was recorded against Transit Mixer-295 & highest expense recorded against transit mixer – 295 in the month
of Sep-14 due to engine overhauling.
4. Mobile Pump
1. Mobile Pump Expenses Trend Line:
Expenses per M3 on Pump in Sep-14 has increased to 3.14 SAR/Mᶟ compared to 2.47 SAR/mᶟ in Aug-14 & it has been
observed that availability of Pumps was recorded 92% in the month of Sep-14.
The Majority of the expenses were incurred on Spare Parts i.e. 76% of the Total Mobile Pump Expense followed by Lubricants
10% tyre 9% & outside repair 5% in Sep- 14.
The majority of the expenses were incurred for 42 Meter Pump (19 nos.) which is 70% of total expense, 14% of the expense
on the 52 meter pump (2 nos.) and 16% of expense on pumps 54 & above meter (5 nos.).
Expense on mobile pump has increased to 3.14 SAR/m3 in Sep-14 compared to 2.47 SAR/mᶟ in Aug-14 because of major
repair carried out in the month.
Expense per mobile pump was recorded 7,402 SAR/MP in the month of Sep-14 compare to 8,378 SAR/MP in aug-14.
Ref. No. UB/GOMC/2014/414
14/10/2014
4.3 Top – Mechanical expenses recorded in Sep-14 – Mobile Pump
Total Expense
Sr. No Asset Type Reg. No Job Card location Observation/Comments
Downtime (Hr) Recorded (SAR)
Gear box overhauling / clutch calibration
1 42 meter 1018 SKA SLY143676 472 Sulay 23,045
carried out & sensor was replaced.
Trunk / S Valve repair & agitating shaft
2 42 meter 2345 TNA SLY143900 12 Sulay 8,590
was changed
Concrete congestion in concrete delivery
3 42 meter 6705 GKA SLY143584 21 Sulay 7,566
pipes & elbow.
Preventive Maintenance – A / rubber
4 56 meter 4341 XAB SLY143689 9 Sulay 5,542
piston & twin pipe was changed
Hydraulic hose replaced / window lifter
5 52 meter 1103 BNA JD141942 5 Jeddah 5,235
repaired.
Reverse stroke was not working / it was
6 42 meter 4509 DNA JD141935 64 Jeddah 4,740
repaired from outside agency.
Pump- 1018 SKA (P-51) Sulay was recorded with down time 472 Hr correspondence to expense SAR 23,045 in the month
of Sep- 14 due to gear box bell housing broken & gear box overhauling required also clutch calibration carried out &
sensor was replaced. (SLY143676)
P-78 (2345 TNA) Sulay Was second expensive Pump which were recorded expense of 8,590 SAR in Sep-14 due to Trunk / S
Valve repair & agitating shaft was changed. (Job card No: SLY143900)
Third most expense against P-60 (6705 GKA) which was amounting 7,566 SAR & down time of 21 Hr. in the month of Sep-14
due to Concrete congestionin concrete delivery pipes & elbow. Pipe & rubber seal was changed. (Job card No: SLY143584)
Fourth most expense against P-113 (4341 XAB) which was cost 5,542 SAR in Sep-14 due to preventive maintenance – A & during
maintenance rubber piston & twin pipe (2 nos) was changed. ( Job card No: SLY143689)
Highest down time & expense was recorded against Pump - 51 in the month of Sep-14 due to gear box overhauling.
5. Static Pumps
1. Static Pump Expenses Trend Line:
Expenses on Static pump decreased to 1.42 SAR/mᶟ in month of Sep-14 compared to 1.90 SAR/mᶟ in month of Aug-14 because
of SP- 35 was under workshop for major repair.
Ref. No. UB/GOMC/2014/414
14/10/2014
5.2 Breakups of Static pump Expenses:
SP/MSP Expenses (Sep-14)
Aug-14 Sep-14
Mechanical Expenses (SAR)
Type Nos. Production (m3)
Spares Lubricants Tyre’s Outside Total SAR/m3 SAR/SP SAR/m3 SAR/SP
SP 13 5,731 1,618 0 0 7,348 5,188 1.90 1,119 1.42 565
Total 13 5,731 1,618 0 0 7,348 5,188 1.90 1,119 1.42 565
SAR/SP 441 124 0 0 565
SAR/m3 1.10 0.31 0.00 0.00 1.42
The Majority of expenses were incurred on spare parts i.e. 78% of the total expense followed by 22% expense incurred on
lubricants in the month of Sep-14.
In Sep-14, SAR per m3 cost has decreased to 1.42 SAR/M3 compare to 1.90 SAR/M3 in month of Sep-14 also production of static
pump are decrease to 5,188 M3.
Highest expense was recorded against Stationary Pump (SP-035) Sulay which is SAR 3,195 & SAR 1,502 with downtime 193
& 11 Hour in the month of Sep-14 due to cylinder stroke was not working & its finger assembly was replaced (SLY143738).
Second job card open for preventive maintenance – B (SLY143616).
Second most Expense recorded against static Pump SP-27 (Makkah) with expense of 1,020 SAR in Sep- 14 due battery
not working & battery has been replaced also hydraulic oil leakage arrested. (Job card : MAK141075)
6. Shovel:
1. Shovel Expenses Trend line:
Shovel Expenses trendline-2010 to 2014
Month Total UB SH Production Expenses (SAR) Cost (SAR/Mᶟ) Cost SAR/SH Availability (%)
Jan-14 10 120,887 33,960 0.28 3,396 88%
Feb-14 10 110,252 38,197 0.35 3,820 91%
Mar-14 10 106,592 14,384 0.16 1,738 91%
Apr-14 10 105,489 50,961 0.48 5,096 92%
May-14 10 116,949 53,304 0.46 5,330 89%
Jun-14 10 69,205 26,323 0.38 2,632 94%
Jul-14 10 98,123 31,258 0.32 3,126 93%
Aug-14 10 108,063 30,163 0.28 3,016 86%
Sep-14 10 76,930 14,335 0.23 1,734 94%
The expense on Shovels in Sep - 14 was SAR 14,335 whereas the expenses recorded that for the month of Aug- 14
were SAR 30,163. The Operating cost for month of Sep- 14 was recorded 0.23 SAR/m3. Expenses per shovel has
decreased to 1,734 SAR/SH in month of Sep-14, compared to 3,016 SAR/SH in month of Aug-14.
Ref. No. UB/GOMC/2014/414
14/10/2014
6.2 Breakup of Shovel Expenses:
The majority expenses were incurred on spare parts i.e. 41% of total expense, followed by tyre expense i.e. 26% of
total expense & lubricants 31% of total expense.
Expenses per m3 for shovel was recorded 0.23 SAR/m3 in month of Sep-14 compared to 0.28 SAR/m3 in Aug-14.
Highest expense recorded against Shovel- SH-07 (8142 JJA) Sulay with expense of 4,969 SAR & down time 28 hr in Sep- 14 due to
LHS rear tyre worn out & Lifting fuel pump leak which was rectified(job card : SLY143579) .
Second Highest expense recorded against Shovel- SH-44 (6193 GDA) Jeddah with expense of 3,000 SAR & down time 10 hr in Sep- 14
due to its preventive maintenance type C & during PM alternator was change. (Job Card no : JD141862)
Shovel SH-09 (8290 JJA) Sulay recorded with expense of SAR 2,370 & 53 hour down time in the month of Sep- 14. Job card
(SLY143841) open for Preventive maintenance – A during Preventive maintenance engine oil filter & oil was changed etc.
Shovel SH-12 Jeddah was recorded with expense of 1,697 SAR & down time of 127 hour in Sep – 14 due to preventive maintenance
– C. during PM also painting work was carried out. (Job card no: JD141897).
Ref. No. UB/GOMC/2014/414
14/10/2014
The Count of Accidents recorded in Sep-14 were 2 and the Expense Corresponding to them were 1,043 SAR. The
count of Incidents recorded for the month of Sep-14 were 2.
Decreased in the Count of incidents (2) are seen for the month Sep-14 as compared to the ones recorded in the
month of Aug-14 (3).
The accident count for month of Sep-14 (2) as compared to the ones recorded in the month of Aug-14(4).
Vehicle Type & Repair Type Jul-14 Aug-14 Sep-14 Grand Total
MOBILE SERVICE 3TON PICK UP / Trailer
Accident Work 75 75
Incident work 0
Pick up / Car
Accident Work 350 295 826 1,471
Incident work 0
TRANSIT MIXER
Accident Work 12,854 8,842 214 21,913
Incident work 1,057 1,352 1,214 3,626
Shovel
Accident Work
Incident work
Mobile Pump
Accident Work 0
Incident work 0
Grand Total 14,336 10,489 2,260 27,085
Repair cost of accident was recorded SAR 214 for transit mixer compare to the SAR 8,842 in Aug-14 & total Accident
cost has been recorded SAR 1,043 in the month of Sep- 14.
1 nos. of Transit Mixer met with accident in month of Sep- 14 & 2 Nos of transit mixer met with incident.
Ref. No. UB/GOMC/2014/414
14/10/2014
The count of Actual preventive maintenance was recorded 122 in the month of Sep-14 against the target
preventive maintenance was 124.
Total manpower count of KSA are recorded 67, the manpower of Sulay, CRCC, Makkah, & Jeddah was recorded
29, 11, 12 & 15 respectively.
Total Site breakdown were recorded 21 in the month of Sep-14 majority of site breakdown occur in the Sulay branch
i.e. is 10 & CRCC was recorded 5.
It has been seen that repeated repair for due to the less pickup while full loading capacity. Fuel pump was repaired
from outside & replaced. (job card No : CRCC141162)
9. Batching Plant
The Majority of the expenses were incurred on batching plant spares parts i.e. 54% of the total Expense followed by ice / chiller
plant spares parts 10%, Generator parts 12%, lubricants 14%, & outside repair 3% respectively in the month of Sep- 14.
The majority of the expense was recorded against the Sulay plant i.e. 48% of the total expense. Jeddah &
Makkah were recorded 26 % & 13% of total expense respectively.
Sulay plant was recorded expense with SAR 78,916 (48% of the total expense) Majority of expense on plant
which was around SAR 51,950 among which SAR 44,200 was spent on Mixer wear plate installation job card
No: BPSLY142097
ef. No. UB/GOMC/2014/414
14/10/2014
Jeddah Plant was recorded expense with SAR 41,963 in the month of Sep-14. Cost was decrease compare to Aug-
14. Mixer concrete discharge door of plant was changed which was amounting SAR 14,437 (Job card:
BPHMD140990) & SAR 4,680 spent on wire mesh. (BPHMD140982)
CRCC Plant were recorded expense with SAR 21,597 in the month of Sep-14. Center Mixer arm of plant was
changed which was amounting SAR 2,900 (Job card: BPCRCC140147) & SAR 1,400 spent on calibration of
scales. (BPCRCC140208)
Makkah Plant were recorded expense with SAR 21,516 in the month of Sep-14. Majority of expense on chiller /
ice plant spare parts which was cost SAR 8,343 i.e. 38% of the total cost of Makkah batching plant.
Cost/M3 of Sulay, CRCC, Jeddah, & Makkah Was recorded with 1.88, 1.32, 4.29 & 2.42 SAR/M3 respectively in
the month of Sep-14 & average operating cost of the batching plant was slightly increased compare to the Aug-
14.
Current stock recorded against Jeddah, Makkah & Riyadh (Sulay & CRCC) are SAR 3,128,458 SAR 1,430,975 &
SAR 3,012,850 respectively.
Stock inventory level of Riyadh the location has been increases in the month of Sep-14 compare to in the month of Aug-
14.
Ref. No. UB/GOMC/2014/414
14/10/2014
ver all Store inventory for month of Sep-14 are increased to SAR 7,601,109 compare to SAR 7,553,936 because
of store stock items increased in Riyadh & Makkah location.
Regards
Prepared by: Reviewed by:
Rohit Tiwari Mr. Saquib A Khan
Workshop Engineer Technical Manager -GOMC
Ref. No. UB/GOMC/389/2014 20.11.2014
INTERNAL CORRESPONDENCE
To :
From :
CC :
Subject :
Dear Sir,
We have done Analysis of Diesel Consumption & Expenses for the Months of Oct, 2014 & Sep, 2014. Please find below our
Observations & findings, for your kind information and updates as deemed necessary.
UAE
Oct-14 Sep-14
93
MIC
Oct-14 Sep-14
94
Observations:-
1. The Overall diesel consumption for UAE was increase from 679,931 liters in Sep, 2017 to 707,303 liters in Oct, 2014
i.e., there was an increase of fuel consumption by 27,372 liters in Oct, 2014.
2. TM’s (UB & Hired) Transit Mixer Diesel Consumption had been increased from 2576.32 Ltr/TM in Sep, 2014 to
3170.09 Ltr/TM in Oct, 2014 commensurate with Production increased.
3. The Overall Diesel consumption at Gold Line Plant in Oct, 2014 was the Highest @ 302,971 Liter, commensurate
with the Highest QTY. produced for the said Month.
4. The total Quantity of fuel consumed by Generators had been decreased from 356,279 liters in Sep, 2017 to
326,596 liters, in Oct 2014 Incommensurate with the QTY. Produced.
5. LTR/M3 in Oct-2014 at GOLDEN LINE Plant for the Transit Mixers is increased to the Month precede.
Commensurate with the Production.
6. The mobile concrete pump Diesel consumption had increased from (UB &Hired) 52,201 liters in Sep, 2014 to
63,646 liters, in Oct, 2014 proportionate with MP Production for the month Precede.
NPP-NL 7,087.5 164,326 336,121 23.19 47.42 6,244.0 153,294 311,301 24.55 49.86 6,129.0 148,454 301,362 24.22 49.17
MIC 28,938.5 209,236 427,983 7.23 14.79 27,729.5 221,040 448,875 7.97 16.19 26,742.0 217,307 441,133 8.13 16.50
Al Riffa 34,311.0 302,971 619,713 8.83 18.06 28,356.5 242,607 492,672 8.56 17.37 27,626.5 271,211 550,558 9.82 19.93
Al Rayan 3,038.5 30,770 62,939 10.13 20.71 6,441.5 62,990 127,917 9.78 19.86 6,554.0 74,121 150,466 11.31 22.96
TOTAL 73,375.50 707,303 1,446,756 9.64 19.72 68,771.50 679,931 1,380,765 9.89 20.08 67,051.50 711,093 1,443,519 10.61 21.53
UAE
Fuel Fuel Avg. Qty. / Avg.
Month m3 Total Trips Total Km Cost Cost/Km Km/ Litre Km/ Gal Cost/m3 Litre/m3
(in (in Trips KM/
Litre) Gallon) Trips
Aug-17 64,353 7,280 466,794 227,465 50,036 461,753.95 8.84 64.1 0.99 2.05 9.33 7.18 3.53
Sep-17 65,975 7,376 479,038 231,869 51,005 470,866.35 8.94 64.9 0.98 2.07 9.39 7.14 3.51
Oct-17 71,152 7,979 531,360 272,628 59,971 553,637.40 8.92 66.6 1.04 1.95 8.86 7.78 3.83
95
Transit Mixer Diesel Consumption Analysis – MIC
MIC
Fuel Fuel Avg. Qty. Avg.
Month m3 Total Total Km Cost Cost/Km Km/ Litre Km/ Gal Cost/m3 Litre/m3
(in (in / Trips KM/
Trips
Litre) Gallon) Trips
Aug-17 24,721 2,746 221,514 84,412 18,568 171,356 9.00 80.67 0.77 2.62 11.93 6.93 3.41
Sep-17 26,165 2,907 230,644 88,534 19,475 179,790 9.00 79.34 0.78 2.61 11.84 6.87 3.38
Oct-17 27,358 3,031 243,324 99,448 21,876 201,953 9.03 80.28 0.83 2.45 11.12 7.38 3.64
Un-utilized Fuel issuance/Abnormal Diesel Consumption in TM’s/Concrete Mobile Pump: Oct, 2017:
Door Qty
Sl No Reg No. Qty(M3) Lit/m3 Remarks
No. (Lit.)
MAJOR BREAKDOWN AVAILABLE DAYS
1 206904 TM-325 450 38 11.84
ONLY 8.
2 259984 TM-336 1411 141 10.01 UNDERGOING REFURBISHMENT WORK
UNDERGOING MAJOR BREAKDOWN
3 259353 TM-350 570 61 9.34
AVAILABLE DAYS 3.
4 257082 TM-362 1642 247 6.65 UNDERGOING PASSING WORK
DRUM WELDING WORK AVAILABLE DAYS
5 64025 TM-380 1860 278.5 6.68
13.
6 292277 TM-449 1963 240.5 8.16 DUE TO LOW PULLING
7 272027 TM-484 941 80 11.76 WAITING FOR ESTIMARA , PASSING
DONE
1. The Diesel consumption in the month of Oct, 2017 had increased by 27,372 liters, proportionate with the increased in
production QTY. by 4,604 m3 to the preceding Month.
2. Gold Line Plant had produced 34,311 m 3
of concrete in Oct, 2017 which is 46.76% of the total Qatar concrete
production in Oct, 2017. Hence, the fuel consumption at Gold Line Plant had also been the highest, i.e., 302,971 liters
which is 42.83% of the total fuel consumed in Qatar.
Prepared by Reviewed by
Rohit Kumar Tiwari Mr. Nayan Jyoti Bora
Workshop Engineer Deputy Manager-Technical