You are on page 1of 9

PART PB

General
PB-1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 117

Materials
PB-5 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118
PB-6 Brazing Filler Metals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118
PB-7 Fluxes and Atmospheres . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118

Design
PB-8 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118
PB-9 Strength of Brazed Joints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119
PB-10 Brazed Joint Efficiency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119
PB-14 Application of Brazing Filler Metal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119
PB-15 Permissible Types of Joints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119
PB-16 Joint Clearance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119
PB-17 Joint Brazing Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119
PB-18 Openings. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119
PB-19 Brazed Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121

Fabrication
PB-26 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121
PB-28 Qualification of Brazing Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121
PB-29 Qualification of Brazers and Brazing Operators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121
PB-30 Cleaning of Surfaces to Be Brazed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121
PB-31 Clearance Between Surfaces to Be Brazed. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121
PB-32 Postbrazing Operations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 122
PB-33 Repair of Defective Brazing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 122

Inspection and Tests


PB-46 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 122
PB-47 Check of Brazing Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 122
PB-48 Brazer and Brazing Operator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 122
PB-49 Visual Examination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 122

Exemptions
PB-50 Exemptions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123

115
Marking and Reports
PB-51 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123

Figure
PB-15 Some Acceptable Types of Brazed Joints. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120

Tables
PB-1 Maximum Design Temperatures (°F) for Brazing Filler Metal . . . . . . . . . . . . . . . . . . . 118
PB-16 Recommended Joint Clearance at Brazing Temperature. . . . . . . . . . . . . . . . . . . . . . . . . . 120

116
PART PB
REQUIREMENTS FOR BOILERS
FABRICATED BY BRAZING

GENERAL PB-1.3 Service Restrictions. Brazed components


may be used for service up to the temperatures as
PB-1 GENERAL
shown in Table PB-1 provided acceptable qualification
PB-1.1 Scope. The rules in Part PB are applicable tests are performed.
to pressure parts of boilers, including piping constructed
under the provisions of this Section, that are fabricated PB-1.4 Responsibility. Each Manufacturer1 (Certifi-
by brazing. These rules shall be used in conjunction cate of Authorization Holder) is responsible for the
with the general requirements in Part PG and the brazing done by his organization and shall establish
specific requirements in the applicable Parts of this the procedures and conduct the tests required by Section
Section that pertain to the type of boiler under consider- IX, and when necessary those required by this Section
ation. The rules in Part PB are not applicable to non- to qualify the brazing procedures used in the construc-
pressure bearing attachments to pressure parts which tion of brazed assemblies and the performance tests of
have essentially no load-carrying function (such as brazers2 who apply these procedures. Such brazing will
extended heat transfer surface, insulation support ordinarily be done by employees of the Manufacturer
pins, etc.). who accepts the responsibility for Code construction
of the boiler or part being brazed. Alternatively, the
Manufacturer may perform Code brazing using the
PB-1.1.1 Definition of Brazing. A group of weld-
services of individual brazers who are not in his employ
ing processes that produces coalescence of materials
provided all the following conditions are met.
by heating them to the brazing temperature in the
presence of a filler metal having liquidus above 450°C
PB-1.4.1 All Code construction shall be the respon-
(840°F) and below the solidus of the base metal. The
sibility of the Manufacturer.
filler metal is distributed between the closely fitted
faying surfaces of the joint by capillary action. PB-1.4.2 All brazing shall be performed in accord-
ance with Manufacturer’s brazing procedure specifica-
PB-1.1.2 Brazing processes which are permitted tions which have been qualified by the Manufacturer
for use under this Part are classified by method of in accordance with the requirements of Section IX and
heating as follows: when necessary, based on design temperature, with the
(a) torch brazing; additional requirements of this Section.
(b) furnace brazing;
(c) induction brazing; PB-1.4.3 All brazers shall be qualified by the
(d) resistance brazing; Manufacturer in accordance with the requirements of
(e) dip brazing — salt and flux bath. Section IX.

PB-1.4.4 The Manufacturer’s quality control sys-


PB-1.2 Elevated Temperature. Maximum design
tem shall include the following as a minimum.
temperature is dependent on the brazing filler metal
and on the base metals being joined. The maximum
design temperatures for some brazing filler metals are 1 Manufacturer includes contractor, Assembler, and installer.
shown in Table PB-1. 2 Brazer includes brazing operator.

117
PB-1.4.4.1 1998 SECTION I PB-8

TABLE PB-11
MAXIMUM DESIGN TEMPERATURES (°F) FOR BRAZING FILLER METAL

Temperature Below
Filler Metal Which Section IX Tests Temperature Range Requiring
Classification Only Are Required Section IX and Additional Tests

BCuP 300 300–350


BAg 400 400–500
BCuZn 400 400–500
BCu 400 400–650
BAlSi 300 300–350
BNi 1200 1200–1500
BAu 800 800–900
BMg 250 250–275
NOTE:
(1) Temperatures based on AWS recommendations.

PB-1.4.4.1 A requirement for complete and ex- PB-6 BRAZING FILLER METALS
clusive administrative and technical supervision of all
The selection of the brazing filler metal for a specific
brazers by the Manufacturer.
application shall depend upon its suitability for the
PB-1.4.4.2 Evidence of the Manufacturer’s au- base metals being joined and the intended service.
thority to assign and remove brazers at his discretion Satisfactory qualification of the brazing procedure under
without involvement of any other organization. Section IX and when necessary based on design temper-
ature, with the additional requirements of this Section,
PB-1.4.4.3 A requirement for assignment of is considered proof of the suitability of the filler metal.
brazer identification symbols. Brazing with brazing filler metals other than those
listed in Section II, Part C, SFA-5.8 shall be separately
PB-1.4.4.4 Evidence that this program has been
qualified for both procedure and performance qualifica-
accepted by the Manufacturer’s Authorized Inspection
tion in accordance with Section IX and when necessary
Agency.
with the additional requirements of this Section.
PB-1.4.5 The Manufacturer shall be responsible
for Code compliance of the brazement including Code
symbol stamping and providing Data Report Forms PB-7 FLUXES AND ATMOSPHERES
properly executed and countersigned by the Authorized Suitable fluxes or atmospheres or combinations of
Inspector. fluxes and atmospheres shall be used to prevent oxida-
tion of the brazing filler metal and the surfaces to be
MATERIALS joined. Satisfactory qualification of the brazing proce-
dure under Section IX and when necessary, based on
PB-5 GENERAL
design temperature, with the additional requirements of
PB-5.1 Materials used in brazed construction of this Section, is considered proof of the suitability of
pressure parts shall conform to one of the specifications the flux and/or atmosphere.
given in Section II and shall be limited to those
specifically permitted in Parts PG, PWT, and PFT for
DESIGN
which allowable stress values are given in Tables 1A
and 1B of Section II, Part D for Section I Construction, PB-8 GENERAL
and for which brazing group P-numbers are assigned
The rules in the following paragraphs apply to boilers
in Section IX.
and parts thereof that are fabricated by brazing and shall
PB-5.2 Combinations of Dissimilar Metals. Combi- be used in conjunction with the general requirements for
nations of dissimilar metals may be joined by brazing design in Part PG, as well as with the specific require-
provided they meet the qualification requirements of ments for design in the applicable Parts of this Section
Section IX and this Section. that pertain to the type of boiler under consideration.

118
PB-9 PART PB — REQUIREMENTS FOR BOILERS PB-18.1

PB-9 STRENGTH OF BRAZED JOINTS powder, rings, strip, cladding, spraying, or other means.
After brazing, the brazing filler metal should be visible
It is the responsibility of the Manufacturer to deter-
on both sides of the joint.
mine from suitable tests or from experience that the
specific brazing filler metal selected can produce a joint
which will have adequate strength at design temperature.
PB-15 PERMISSIBLE TYPES OF JOINTS
The strength of the brazed joint shall not be less than
the strength of the base metal, or the weaker of the Some permissible types of brazed joints are shown
two base metals in the case of dissimilar metal joints. in Fig. PB-15. Lap joints shall have a sufficient overlap
to provide a higher strength in the brazed joint than
PB-9.1 Qualification of Brazed Joints for Design
in the base metal.
Temperatures Up to the Maximum Shown in Column
The nominal thickness of base material used with
1 of Table PB-1. Satisfactory qualification of the
lap joints tested using the test fixture shown in Section
brazing procedure in accordance with part QB of Section
IX, QB-462.1(e) shall not exceed 1⁄2 in. There is no
IX is considered evidence of the adequacy of the base mate-
thickness limitation when specimens are tested without
rials, the brazing filler metal, the flux and/or atmosphere,
the test fixture shown in QB-462.1(e).
and other variables of the procedure.
PB-9.2 Qualification of Brazed Joints for Design
Temperatures in the Range Shown in Column 2 of PB-16 JOINT CLEARANCE
Table PB-1. For design temperatures in the range
The joint clearance shall be kept sufficiently small
shown in Column 2 of Table PB-1, tests in addition
so that the filler metal will be distributed by capillary
to those in PB-9.1 are required. These tests shall be
action. Since the strength of a brazed joint tends to
considered a part of the qualification procedure. For
decrease as the joint clearance is increased, the clearance
such design temperatures, two tension tests on produc-
for the assembly of joints in pressure vessels or parts
tion type joints are required, one at the design tempera-
thereof shall be within the tolerances set up by the
ture and one at 1.05T (where T is the design temperature
joint design and used for the corresponding qualification
in degrees Fahrenheit). Neither of these production-
specimens made in accordance with Section IX.
type joints shall fail in the braze metal.
NOTE: For guidance, see Table PB-16 which gives recommended
joint clearances at brazing temperature for varying types of brazing
filler metal. Brazing alloys will exhibit maximum strength if clearances
PB-10 BRAZED JOINT EFFICIENCY are maintained within these limits.

The joint efficiency factor to be used in design of


boilers with brazed joints shall be 1 for all joints.
PB-17 JOINT BRAZING PROCEDURE
A joint brazing procedure shall be developed for
PB-14 APPLICATION OF BRAZING each different type of joint of a brazed assembly. A
FILLER METAL recommended form for recording the brazing procedure
is shown in QB-482 of Section IX. If more than one
The design of the joint shall provide for the applica-
joint occurs in a brazed assembly, the brazing sequence
tion of the brazing filler metal. Where practicable, the
shall be specified on the drawing or in instructions
brazing filler metal shall be applied in such a manner
accompanying the drawing. If welding and brazing are
that it will flow into the joint or be distributed across
to be done on the same assembly, the welding shall
the joint and produce visible evidence that it has
precede the brazing unless it is determined that the
penetrated the joint.
heat of welding will not adversely affect the braze
PB-14.1 Manual Application. The manual applica- previously made.
tion of the brazing filler metal by face-feeding to a
joint should be from one side only. Visual observation
of the other side of the joint will then show if the PB-18 OPENINGS
required penetration of the joint by the filler metal has
PB-18.1 Openings for nozzles and other connections
been obtained.
shall be far enough away from any main brazed joint
PB-14.2 Preplaced Brazing Filler Metal. The braz- so that the joint and the opening reinforcement plates
ing filler metal may be preplaced in the form of slugs, do not interfere with one another.

119
Fig. PB-15 1998 SECTION I Table PB-16

FIG. PB-15 SOME ACCEPTABLE TYPES OF BRAZED JOINTS

TABLE PB-16
RECOMMENDED JOINT CLEARANCE AT
BRAZING TEMPERATURE

Brazing Filler Metal Clearance, in. [Note (1)]

BAlSi 0.006–0.010 for laps less than or equal to 1⁄4 in.


0.010–0.025 for laps greater than 1⁄4 in.
BCuP 0.001–0.005
BAg 0.002–0.005
BCuZn 0.002–0.005
BCu 0.000–0.002 [Note (2)]
BNi 0.001–0.005
NOTES:
(1) In the case of round or tubular members clearance on the radius is intended.
(2) For maximum strength use the smallest possible clearance.

120
PB-18.2 PART PB — REQUIREMENTS FOR BOILERS PB-31

PB-18.2 Openings for pipe connections in boilers shall not qualify that procedure for any other Manufac-
having brazed joints may be made by inserting pipe turer, except as provided in QB-201 of Section IX.
couplings, or similar devices not exceeding NPS 3
(DN 80) in the shell or heads and securing them by
welding provided the welding is performed by welders PB-29 QUALIFICATION OF BRAZERS
who have been qualified under the provisions of Section AND BRAZING OPERATORS
IX for the welding position and type of joint used.
PB-29.1 The brazers and brazing operators used in
Such attachments shall conform to the rules for welded
brazing pressure parts shall be qualified in accordance
connections PW-15 and PW-16.
with Section IX.
The qualification test for brazing operators of machine
or furnace brazing equipment shall be performed on a
PB-19 BRAZED CONNECTIONS separate test plate prior to the start of brazing or on
PB-19.1 Connections such as saddle type fittings the first work piece.
and fittings inserted into openings formed by outward PB-29.2 Each brazer or brazing operator shall be
flanging of the vessel wall, in sizes not exceeding NPS assigned an identifying number, letter, or symbol by
3 (DN 80), may be attached to boilers by lap joints the Manufacturer which shall be used to identify the
of brazed construction. Sufficient brazing shall be pro- work of that brazer or brazing operator.
vided on either side of the line through the center of
the opening parallel to the longitudinal axis of the shell PB-29.3 The Manufacturer shall maintain a record
to develop the strength of the reinforcement through of the brazers and brazing operators showing the date
shear in the brazing. and result of tests and the identification mark assigned
to each. These records shall be certified by the Manufac-
PB-19.2 For nozzle fittings having a bolting flange turer and be accessible to the Inspector.
and an integral flange for brazing, the thickness of the
flange attached to the boiler shall not be less than the PB-29.4 Brazing of all test coupons shall be con-
thickness of the neck of the fitting. ducted by the Manufacturer. Testing of all test coupons
shall be the responsibility of the Manufacturer. A
performance qualification test conducted by one Manu-
facturer shall not qualify a brazer or brazing operator
FABRICATION to do work for any other Manufacturer.
PB-26 GENERAL
The rules in the following paragraphs apply specifi- PB-30 CLEANING OF SURFACES TO BE
cally to the fabrication of boilers and parts thereof that BRAZED
are fabricated by brazing and shall be used in conjunc-
tion with the general requirements for fabrication in Part The surfaces to be brazed shall be clean and free
PG, as well as the specific requirements for fabrication in from grease, paint, oxides, scale, and foreign matter
the applicable Parts of this Section that pertain to the of any kind. Any chemical or mechanical cleaning
type of boiler under consideration. method may be used that will provide a surface suitable
for brazing.

PB-28 QUALIFICATION OF BRAZING


PB-31 CLEARANCE BETWEEN
PROCEDURE
SURFACES TO BE BRAZED
PB-28.1 Each brazing procedure shall be recorded
The clearances between surfaces to be brazed shall
in detail by the Manufacturer. Each brazing procedure
be maintained within the tolerances provided for by
shall be qualified in accordance with Section IX and
the joint design and used in the qualifying procedure.
when necessary determined by design temperature with
If greater tolerances are to be used in production, the
the additional requirements of this Section.
joint must be requalified for those greater tolerances.
PB-28.2 Brazing of all test coupons shall be con- The control of tolerances required may be obtained by
ducted by the Manufacturer. Testing of all test coupons using spot welding, crimping, or other means which
shall be the responsibility of the Manufacturer. Qualifi- will not interfere with the quality of the braze. If such
cation of a brazing procedure by one Manufacturer means are employed in production, they must also be

121
PB-31 1998 SECTION I PB-49.6

employed in qualification of procedure, brazer, and ments of this Section. He shall satisfy himself that
operator. each joint has been fabricated in accordance with the
procedure. Where there is evidence of consistent poor
quality, the Inspector shall have the right at any time
PB-32 POSTBRAZING OPERATIONS to call for and witness tests of the brazing procedure.
Brazed joints shall be thoroughly cleaned of flux
residue by any suitable means after brazing and prior
to inspection.3 Other postbrazing operations such as
thermal treatments shall be performed in accordance PB-48 BRAZER AND BRAZING
with the qualified procedure. OPERATOR
PB-48.1 The Manufacturer shall certify that the braz-
ing on a boiler or part thereof has been done by
PB-33 REPAIR OF DEFECTIVE BRAZING brazers or brazing operators who are qualified under
Brazed joints which have been found to be defective the requirements of Section IX. The Inspector shall
may be rebrazed, where feasible, after thorough clean- assure himself that only qualified brazers or brazing
ing, by employing the same brazing procedure used operators have been used.
for the original braze. If a different brazing procedure
PB-48.2 The Manufacturer shall make available to
is employed, i.e., torch repair of furnace brazed parts,
the Inspector a certified copy of the record of the
a repair brazing procedure shall be established and
qualification tests of each brazer and brazing operator.
qualified.
The Inspector shall have the right at any time to call
When a repair brazing procedure is established it
for and witness tests of the ability of a brazer or
shall meet Section IX and other conditions set forth
brazing operator.
in this Section.

INSPECTION AND TESTS


PB-49 VISUAL EXAMINATION
PB-46 GENERAL
PB-49.1 When possible, the Inspector shall visually
PB-46.1 The rules in the following paragraphs apply inspect both sides of each brazed joint after flux residue
specifically to the inspection and testing of power boiler removal. It is recognized that for certain joints (blind
parts that are fabricated by brazing and shall be used joints) this is not possible.
in conjunction with the general requirements for inspec-
tion and tests in Part PG as well as the specific PB-49.2 When visually possible there shall be evi-
requirements for inspection and tests in the applicable dence that the brazing filler metal has penetrated the
Parts of this Section that pertain to the type of boiler joint. In a butt braze there shall be no concavity. The
under consideration. braze may be repaired or rebrazed.

PB-46.2 Inspection During Fabrication. The Manu- PB-49.3 The presence of a crack in the brazing
facturer shall submit the boiler or other pressure part filler metal shall be cause for rejection. Dye penetrant
for inspection at such stages of the work as may be inspection may be used if desired. The braze may be
designated by the Inspector. repaired or rebrazed (see PB-33).

PB-49.4 The presence of a crack in the base metal


PB-47 CHECK OF BRAZING adjacent to a braze shall be cause for rejection even
PROCEDURE if the crack is filled with brazing alloy. Repair is not
permitted.
PB-47.1 The Inspector shall assure himself that the
brazing procedure for each type of joint being produced PB-49.5 Pinholes or open defects in the braze shall
is qualified in accordance with the requirements of be cause for rejection. The joint may be rebrazed.
Section IX and when necessary the additional require-
PB-49.6 Rough fillets, particularly those with a con-
3 Flux residues can be extremely corrosive as well as interfering vex appearance, are cause for rejection. Such joints
with visual inspection. may be repaired or rebrazed.

122
PB-50 PART PB — REQUIREMENTS FOR BOILERS PB-51

PB-50 EXEMPTIONS
Certain brazed joints regardless of their service tem-
peratures may be exempt from the additional mechanical
testing of this Section providing that the design applica-
tion does not assume any benefit from the brazed joint
strength. It shall however meet the requirements of
those qualification tests required by Section IX of the
Code (see PB-1.1, Scope).

MARKING AND REPORTS


PB-51 GENERAL
The provisions for marking and reports given in PG-
104 through PG-113 shall apply to brazed boilers and
parts thereof.

123

You might also like