You are on page 1of 2

Right Of Way Department

Permit Number ROWPS-11082023-5057 Permit Details

Permit Type Trade License 949089


Access

Company Name
Permit Subtype AL MAMZAR
Access Design Study ENGINEERING CONSUL

Location Information
Payment NA
Date Plot Number 5912903

Receipt NA Community JABAL ALI FIRST


Number Name

For Queries / Street NA


Tel 04 - 284 4444 / 800 90 90 Fax 04 - 206 5555

Project Information

Project Name g+1 villa at furjan

Project No. 5912903

TIS No. NA

Land Use Class No. Of Units Unit


722 Compound Villa 1 No. of Units

Terms and conditions: :


All Safety precautions in terms of traffic signs, dimensions
n
and cones shall be provided during the implementation as n
per the approved drawing and as per the work zone traffic
.
management manual standards.
All safety measures to be provided as per the relevant
n
standards and regulations of RTA Work Zone Traffic n

Management manual standards.


Access for the proposed development is approved on
n
. n
conceptual basis.

ROWPS-11082023-5057 Page : 1 / 2
Right Of Way Department

Contractor should obtain needful NOC from all relevant


n
Authorities (Dewa, Etisalat? etc.) and relevant Departments n
of RTA (R.O.W. services, Traffic, Intelligent Traffic
Systems, Roads, Maintenance etc.).
n
RTA has the right to transfer any parking in RTA R.O.W to n
paid parking whenever required in future plans. .
n
RTA reserves the right to cancel /modify/hold NOC n
whenever required. .
n
Developer NOC must be obtained before commencement n
of work
Approval is based on the provided landuse details. In case
n
of revision in landuse due to any circumstances, a new n
application must be submitted to obtain the approval from .
RTA/ROW Department
Any conflict with existing road projects further to our
n
approval and before constructing the access/interlock, must n
be notified to RTA to maintain consistency with the .
proposed road design
The contractor shall get Construction NOC from RTA
Construction NOC
n
before starting the external paving works, to protect all the n
utility services in the ROW and to avoid any violations and
.
fine.
The contractor shall get sidewalk modification permit from
n
RTA before starting the external paving works, for the n
safety of the roads and the road users, and to avoid any
.
violations and fines.
Contractor must coordinate with Roads & Facilities
Maintenance Department before commencement of work to
n
report any existing damage to ROW assets at the proposed n

work zone. Contractor holds complete responsibility for any .


type of damage at the time of refund of security deposit.
This permission must be available on the site (scope of
n
work) and must be shown whenever asked by RTA n

inspectors
n
TIS not required, compound Villa 1 No. of Units
The conceptual design for the access is approved as per
the attached drawing. The project does not need Traffic
Impact Study based on the provided landuse details;
However, you have to submit final detailed design drawing
n
prior to submission of Construction NOC. Contractor must
obtain RTA permit (External pavement Modification) before
starting any construction activities for interlock at site for
external paving works from https://rowpermits.rta.ae. RTA
reserves the right to cancel /modify/hold NOC whenever
required.

ROWPS-11082023-5057 Page : 2 / 2