You are on page 1of 3

Date: 24-Jan-23 Ref.

: MD-VPCN-04541-2023

To: All Tenderers

RFX# 2122200123
PARKING AREA WITH ROAD BASE FOR 450 PARKINGS AT ‘C’ STATION- SATWA
Pre Tender Clarification # 1

Please find below clarification in Question - Answer form, in response to queries raised by tenderers.

Sl. Query Answer


No
1. Please confirm, there is no services to be Successful tenderer shall obtain NOCs and follow the
relocated or Protected inside project limit. NOC conditions. Trial excavation shall be carried out to
ensure the safety of services, if any.

2. Please confirm that the removal or Protection of Not required.


Existing Street lights & Security portacabin is not
required under this contract.

3. As per provided tender Specification Documents Kerbstone of size 900x250x100 all around the
, Page no: SPEC-1 , Clause 1 , Scope of Works , proposed area may be considered. Successful tenderer
Item: g- Fixing of Edge Kerbstone , Please provide shall submit the material and fixing details for approval.
the details for required Kerbstone Like Location
and Specification.

4. Please confirm, while making the formation level Shifting of sand is not required. However, construction
if any excess sand arising that will be dump in debris/waste, if any, shall be dumped at the designated
adjacent side inside the same plot and will not be Dubai Municipality dump yard.
shifted to Other Dumping yard.
Sl. Query Answer
No
5. Please confirm, If sand required to make Usage of sand from adjacent area depends on plot level
formation level for proposed parking, Sand surveying, quantity of sand required and DEWA approval
material can be taken from Adjacent site inside
the same plot.

6. Please provide the details of Proposed Attached.


Directional and Safety Sign Board Location and
Specification in order to Quantify the Required
number of Sign Board and Quote Accordingly.

7. Kindly confirm there is no existing Refer Sl. No 01


underground services in project location. If any,
kindly provide GIS/existing services drawings
to identify existing water/electrical services.

8. Please clarify if the contract is lumpsum or re- Lumpsum


measurable?

9. Please confirm, Obtaining All types of NOC is Yes.


under contractor scope?

10. Is Existing Lights poles/ other services to be Refer Sl. No 02


relocated/removed. Kindly confirm

11. Kindly confirm that the existing natural plants To be considered.


either to be removed or not. If yes, can it be
considered in the BOQ pricing?
Sl. Query Answer
No.
12. Kindly provide the specifications & quantity of Refer the attached drawing and Tender document
directional & safety signages and MC 70 primer. specifications for MC70 primer.

13 Referring to specification 1.g (page 86) indicates, Refer Sl. No 03


fixing of edge kerbstones with concrete support
which is not mentioned in BOQ. Kindly confirm

14 Please Clarify, the edge kerbstones is required for All around the proposed parking area.
parking end curves or as vehicle stopper?

15. Referring to specification 2 (page 86) indicates, Removal of top 20 cm sand layer shall be considered.
Existing sand (20cm) has to be removed from OGL
which is not mentioned in BOQ. Kindly confirm.

This clarification shall form a part of the Tender Document and is to be submitted along with the Tender Offer,
duly signed by the Tenderer.