CITY AND COUNTY OF DENVER

DEPARTMENT OF PUBLIC WORKS

CONTRACT NO.: 201736456


PROJECT NAME: 2017 Annual Sanitary Lining Program

ADDENDUM NO. _1_ TO CONTRACT DOCUMENTS

Bidders are hereby instructed that the drawings, specifications, and other contract documents are modified, corrected, supplemented
and/or superseded for the above-mentioned project as hereinafter described in the following attachments:

BID FORM
• Replace existing BF-6.1 with attached page: Add #1 BF-6.1
• Please note Bid Item 34-17.4a increased from 80,075 LF to 82,490 LF

BID DOCUMENT
• Replace existing SQ-1 with attached page: Add #1 SQ-1
• Please note Bid Item 34-17.4a increased from 80,075 LF to 82,490 LF

DRAWINGS
• Replace existing Drawings ( 12 pages) with attached Drawings Add # 1 (12 pages)

QUESTIONS AND ANSWERS

1. Can we get a full size set of drawings prior to bid deadline?


Response: The bidders can print the files to a large format printer at double the scale or fit to sheet size,
to a 22x 34 sheet size by sending it to a printing service if they do not have in house printer. The City
will not provide paper copies prior to bid.

2. Can City and County of Denver provide copies of video reports on these lines?
Response: The video files will be provided to the winning bidder after the contract is awarded.

3. How soon after bid award will City and County of Denver know the "Critical" sewer locations, and will
CCD be willing to consider a change order to cover additional traffic control costs if the TC requirements
are beyond what the Contractor can self-perform?
R esponse: Critical sewer locations will be known when they are found. Critical locations may be found
during routine inspections, from public complaints, or other sources. CCD will not consider a change
order to cover additional traffic control costs.

4. Per Technical Spec Section 10.7.5.1.1 , in regards to ASTM E797 - please clarify for the onsite thickness
testing, who is responsible for taking the ultrasonic thickness test and who is responsible for providing the
testing equipment? We have only seen this reference in regards to high temperature metallic pipe.
Response: The contractor will be responsible for providing this equipment.

5. Spec Section 01 -5213 2.0lrequires an office trailer adjacent to thejobsite. Since the CIPP project is a
mobile jobsite, that is not really feasible. Please let us know if this requirement can be waived.
Response: There is not a bid item for an office trailer therefore a trailer is not required for this project.

6. Spec states that "all permits will be paid by the contractor". Does this include ROW permits? In the past,
all ROW permits are no-fee for Denver projects. Please clarify.
Response: This is a City project and ROW permits will be required, but ROW fees will be waived. The
contractor should mention when obtaining the permit that this is a City ofDenver project.
7. Can you please provide the flow data for the Bypass requirements?
Response: The City doesn't provide flow data. The contractor is encouraged to visit tlte site and pull
manhole lids prior to bidding to estimate flows.

8. Are the associated manholes going to be relined after the CIPP installation?
Response: No manholes will be /foe or rehabilitated with this project.

This ADDENDUM shall be attached to, become a part of, and be returned with the Bid Proposal.

~~Th~ City Engineer

9 -b·I°?"'
Date

The undersigned bidder acknowledges receipt of this Addendum. The Proposal submitted herewith is in accordance
with the stipulations set forth herein.

Contractor

ADDENDUM NO. _ 1_
Date