Right Of Way Department

Permit Number ROWPS-17062023-5069 Permit Details

Permit Type Trade License 567304


Major Roads Diversion

Company Name (..)( )


Permit Subtype CHINA STATE
All Purposes, except buildings CONSTRUCTION ENGIN

Date From 15-Jul-2023

Payment 14-Jul-2023 11:14 AM


Date To 26-Aug-2023
Date

Receipt 00001570628564 Time From 12:00 AM


Number
Time To 12:00 AM
For Queries /
Tel 04 - 284 4444 / 800 90 90 Fax 04 - 206 5555 Location Information

Plot Number 0

Community AL YALAYIS 5
Name

Street Emirates Road

Terms and conditions: :


All Safety precautions in terms of traffic signs, dimensions
n
and cones shall be provided during the implementation as n
per the approved drawing and as per the work zone traffic
.
management manual standards.
All safety measures to be provided as per the relevant
n
standards and regulations of RTA Work Zone Traffic n

Management manual standards.


n
Safety of the workers is solely the responsibility of the n
contractor / consultant.
Contractor should obtain needful NOC from all relevant
n
Authorities (Dewa, Etisalat? etc.) and relevant Departments n
of RTA (R.O.W. services, Traffic, Intelligent Traffic
Systems, Roads, Maintenance etc.).
Police and Civil Defense Centers in area of jurisdiction
n
. n
should be informed before assuming the work.
n
RTA has the right to cancel the permit issued whenever n
violation occurs. .

ROWPS-17062023-5069 Page : 1 / 3
Right Of Way Department

Any damages to RTA properties caused by your work


n
activities shall be charged and penalties will be imposed n

according to the local order No. 54/2021. 2021/54


n
This permit does not absolve the permit holder from the n
responsibility of any damages caused to third parties.
n
Access to building/villas as well as pedestrian facilities n
should be maintained during work constructions.
The work zone and surroundings shall be kept in a neat
n
and clean shape, and shall be returned to previous n
.
condition right after finishing the work.

n
This Permit is not valid unless all above conditions are fully n
complied with.
.
Please apply for permit renewal 3 to 5 days before expiry
n
5 3 . n
date
n
In case of deposit refund, please apply a request through n
the website
Contractor must coordinate with Roads & Facilities
Maintenance Department before commencement of work to
n
report any existing damage to ROW assets at the proposed n

work zone. Contractor holds complete responsibility for any .


type of damage at the time of refund of security deposit.
Provide safe, smooth continuous walkway as per RTA
n
. n
standards.
Contractor must inform inspection section in ROW
n
department and traffic control centers in ITS department (at n
24
least before 24 hours of applying the diversion)
Activities that cause noise are not allowed during the night
n
time in the residential areas including the major roads next 09:00 n
to the residential area, Weekdays (from 9:00pm to 7:00 10:00 10:00 07:00
am), Saturdays and Sundays (from 10:00pm to 10:00 am) .
For any long term diversion, coordinate with the ROW
n
Services Section for pre-opening inspection before n

implementing the diversion.


n
Contractor must inform PTA atleast 5 DAYS before 5 n
applying the diversion .
Traffic Diversion implementation at site should be done
n
only by qualified and approved RTA contractor for these n
type of works or similar (asphalt work, signage, road
marking, etc.)
n
The Traffic Diversion must be executed in the site by only n
Qualified and approved contractor from RTA . .
Pre-opening inspection is required by RTA concerned
n
sections if the traffic diversion will change the geometry or n
.
surface of the road.
n
The contractor shall not add RTA Logo on any of the sign n
boards except for Projects that belong to RTA .

ROWPS-17062023-5069 Page : 2 / 3
Right Of Way Department

This permission must be available on the site (scope of


n
work) and must be shown whenever asked by RTA n

inspectors
- Provide concrete barriers & shadow vehicle with a crash
cushion and flashing arrow to protect the working area. -
Provide a shadow vehicle with a crash cushion for each
n
lane drop as per RTA standards. - end treatment for the
concrete barriers should be as per RTA standards. - All
work details to be according to the WZTM manual for
Dubai. All work details to be according to the Roadside
Design Guide manual for Dubai
“No Objection” subject to the following comments: 1. The
contractor should adhere to the approved detailed signs
shop drawing. 2. Fabrication and erection of signs shall be
carried out only by RTA approved contractor. 3.
Consultant/contractor will be fully responsible for the strict
implementation of RTA Traffic Signs Manual (DTCDM)
n
Standards. with florescent yellow green background. 4.
Consultant/contractor should take into consideration that
signs are not hiding each other, with a suitable location. 5.
Consultant/contractor will be fully responsible for Providing
safe & standard footbath for the pedestrian (1.8 Minimum).
6. Remove all the temporary signs after finishing the
diversion.
n
Approved subject to not affecting/ closing any bus
operational movements as shown in the drawings
n
No objection to work over the weekend from Saturday
00:00 AM till Monday 5AM.
n
Stage 1 (From July 15, 2023 to August 5, 2023)
n
Stage 2 (From August 5, 2023 to August 26, 2023)

ROWPS-17062023-5069 Page : 3 / 3