ENGINEERING DEPARTMENT
BOQ NUMBER :
SHEET NAME : PROJECT TERMS AND CONDITIONS
PROJECT NO :
PROJECT : CAR PARK
1.01
Necessary site cleaning – Removal of all existing masonry/ concrete structures, floor finishes, uprooting and
non-use offcuts, all debris shall separate and show to TFPL Engineering store before dispose. All the debris s
different disposal locations according to the EHS and Engineering Store advices.
1.02
Secure the site for mechanical and required civil work so as not to interfere with the general working of the
1.03 Pipe inlets and/ or outlets laying pipe install equipment’s to be installed by the contractor in consultation with
Engineering [HOE] of TFPL.
1.04 Excavation for required column footings /foundation up to required depth and levels given by TFPL Engineer
per reference drawing mentioned in the Site discussions, contract or the annexures.
1.05
Any damage to existing structures shall repair as per guidance of TFPL Engineering satisfactory level with al
1.06 Fabrication of Pipeline network and to the highest standard quality by supplying corrosion free material of g
certified/ agreed by HOE of TFPL.
1.07
All materials movement up to work site from various material stored locations at TFPL – Thulhiriya Site are u
scope of work. Contractor shall store/ Keep for project works at site in proper way as per guidance issued by
according to TFPL production requirements, all materials shall request through TFPL Engineering Store.
1.08 Contractor shall Store Contractor's materials in secured manner, ad Contractors work site shall be arranged
with required safety and tools, equipment's.
1.09 Site shall maintain dedicated executive level experience (Over 5 years similar capacity) qualified engineer ag
TFPL (If any other required to get pre-approved from HOE-TFPL) for site supervision.
1.1
The Contractor shall keep at the site on a full-time basis a Competent, Qualified Site Officer/ supervisor shal
managing Safety, Engineering requirements in site and shall coordinate site condition variations with TFPL E
team. If site Officer/ supervisor not educated standards and requirements in terms of safety and compliance
provided Officer/ supervisor not pay his first priority to EHS (environment, health and safety) TFPL can reque
Officer/ supervisor to site and contractor shall provide resident experienced officer within two days from the
Daily maintain dedicated Site Officer/ supervisor is contractor’s responsibility, necessary assistants acceptab
who shall supervise and monitor the progress of the work.
1.11 Site Officer/ supervisor shall face to Safety, compliance and general Practices and skill understanding intervi
advance payment.
1.12 Site Officer/ supervisor shall call daily safety and daily target plan to contractor’s team briefing by daily 7:15
1.13
Contractors resident Site Officer/ supervisor shall understand company requirement and required to particip
with HOE of TFPL, and contractors company owner or his authorized officer shall visit the works at least one
attending company organized related meetings are compulsory.
1.13.01
If contractor failed to deploy Site Officer/ supervisor, after 3 written reminders from any official media TFPL
deploy his representative with the conditions of deducting opportunity lost, TFPL HOD representatives per d
days Site Officer/ supervisor will be Rs. 15,000 Per day and additional hours it will be 2,500 per hour. and ch
from contractor's nearest payment. And HOE shall inform officially to contractor related information. If furt
employed Site Officer/ supervisor then the chargers will be 08 hour service Rs. 25,000 per day and above 08
charge will be Rs. 3,500 per hour will be applicable.
1.14
Company shall inform connection plans and contractor shall agreed to commence the work as per given com
Site Officer/ supervisor shall gather standard work approvals at least 12hours before the next day works, fro
Engineering office daily at 4:00PM (Weekdays). Weekends Site approval shall obtain every Friday at same tim
shall request officially through email.
1.15 All the important legal related matters shall communicate through inwriting hard copies in letterhead or em
WhatsApp, SMS will consider as supporting media to flow quick information sharer tool.
1.16
Construction to be tested for zero leaks prior to use them with using 1.5times Line actual pressure with Wat
Air pressure, provided by company and rectify any attend leaks/ defects within short time.
1.17 Certification of the ‘as built drawings’, construction design calculations and ‘design drawings’ by a recognize
Engineer to be submitted to the HOE of TFPL
1.18 Fair faced finish of all concrete structures
1.19 Layout of Structures and levels to be as per Plans and Drawings issued by the HOE of TFPL
1.2 Levels of Structures to be in synchronization with the existing Structures system to ensure gravitational liqu
the instructions given by HOE, the Plans and Drawings issued by the HOE of TFPL
1.21 All the handling materials shall provide by contractor as per requirements and guidelines issued to contracto
1.22
Contractor shall maintain site daily diary and daily required to get acceptance confirmation from HOE of the
1.23
Work shall be carrying out without stopping TRISCHEL normal production activities and contractor shall carr
providing priority to company operations. Contractor shall counter such cases in advance, prior to quotation
company acceptance can be charge for delays if any.
1.24 Contractor shall share debris removal plan, including disposal process, if any landfilling required to be involve
confirmation and relevant government authorities permits shall obtain by contractor.
i). Land owners' ownership confirmation documents (Last 2Months Electricity+Water+Telephone Bill copies
confirmation)
ii). Owners no Objection Letter with clearing his responsibility from entering to his site.
Contractor shall obtain Trischele EHS clearance before advance payment and share acceptance confirmation
Department.
iii). Debris removals Contractor shall obtain Trischele EHS and HR - Administration approvals prior to dispatc
iv). Debris removals notifications will be issuing by HOE or his representative in any official media inwriting an
TFPL HOE will authorized to remove any debris from site and the chargers will apply as below.
Original Debris removal Chargers from TFPL Cleaning
/ Engineering Team / third-party contractors Original
charge
⁼ TFPL ORIGINAL DEBRIES REMOVAL CH
TFPL
⁼
ADMINSTRATION
CHARGERS APPLIED TO CONTRACTOR NEXT
CHARGERS Rs.
IMMIDIATE CLAIM
20,000 PER
INCIDENT
PROGRESS PAYMENT
Sl. NO WORK DESCRIPTION CLEARANCE INSTR
%
NOTE: CONSUMABLES MEANS :Welding electrodes, welding plants, tools and equipment, Paint brushes, grinding w
ADVANCE
1 WORK MOBILIZATION
PAYMENT
DAYS DAYS
RESPONSIBILITY MATRIX
3 LABOUR
2.11.01 Retention
Retention amount
⁼ 5% from total bill value
Retention Period
⁼ ……. Months
NOTE: CONSUMABLES MEANS :Welding electrodes, welding plants, tools and equipment, Paint brushes, grinding w
2.12
The Contractor shall send to the HOE of TFPL once a week an account giving particulars of all claims for any
expenses which the Contractor may consider itself entitled to under Clause 5 and of all extra additional wor
HOE of TFPL which has been executed by the Contractor during the preceding week. Payments for any such
considered only if the claim has been made within two weeks from the date of the Contract becomes entitle
additional payments.
2.13
The Contractor shall at all times keep the premises, access roads etc. free from accumulation of waste mate
caused by its operations. At the completion of the work he shall remove all his waste material and rubbish f
workplace as well as its tools, equipment machinery and surplus material and shall ensure that the site is cle
debris until which time the Company shall have the right to withhold any final payments due to the Contrac
2.14 No employee and or worker engaged by the Contractor shall enter areas other than those demarcated for th
2.15
The Contractor shall rectify all defects pointed out by the HOE of TFPL within seven days of such defects bei
2.16
A Performance Bond in favor of the Company for an amount equal to 10% of the Contract Sum shall be issue
Company from any other bank accepted by TFPL Finance department until the end of twenty four months fr
issuing the Completion Confirmation Certificate by the HOE of TFPL . This performance bond shall be uncond
irrevocable and payable on demand and issued by any other bank accepted by company Finance departmen
2.17 The contractor shall obtain and maintain a Contractors’ Insurance Policy, Workmen’s Compensation and Pub
Insurance policies for the construction period and keep the Company freed and indemnified at all times aga
arising in connection with such risks.
2.18 Risk and title to the work shall pass only upon handing over of same to the Company and the Contractor sha
carried out by the Contractor at the site up to such point.
2.19 The Contractor shall repair immediately any damage to the Company’s property or property/is of third parti
performance of the work at site at the Contractors cost and expense.
2.2 The contract sum includes the cost of material. The Company shall have the right to supply material directly
and deduct the amount quoted from the contract sum on agreed rates for such supply.
2.21 The quantity of excavation, concrete, formwork and steel reinforcements etc. must be certified by the HOE
payment. Joint measurement sheets shall be maintained for this purpose.
2.22
The Contractor shall ensure that all Labor Laws are complied with, necessary safety gear is provided, food/ d
accommodation is provided, necessary insurance covers obtained, safety training is provided for all labor de
site and ensure accident free workflow.
2.23
The Contractor shall not use the canal/s to dispose refuse items such as oil, cement, chemicals, soap, waste
appropriate arrangements should be made to collect such items and dispose in appropriate locations outsid
2.24 Taking/ publishing photographs, videos of the project or any other place, item, bridging competitors employ
premises is prohibited.
2.25 The Company shall supply electricity for the project only upon the Contractor supplying cables, standard dis
and other accepted/ recognized electrical accessories by HOE of TFPL.
2.26 All machinery, tools, equipment etc. necessary for the construction project to be supplied, maintained, insu
Contractor.
2.27
Company will not provide, Food, Tea, Drinking water to Contractors and Thulhiriya park Central Kitchen or a
shall be use for contractors facilities. Internal Transportations are contractors scope. Contractors Vehicles ar
Central Kitchen or ATHENA park, Trischele will not provide space to park contractors Vehicles.
2.28
A list of machinery, tools, equipment etc. brought into the TFPL premises with prior notification, declared to
and Head of Security (HOS) TFPL , and removal of such items to be made only with approval of the said offic
2.29 All quantities of construction material/ consumables for the project shall be declared to the HOE of TFPL an
(HOS) TFPL with Delivery Notes in duplicate.
2.30
CONTRACTOR shall comply with all terms and conditions stipulated in the document titled “SAFETY REQUIRE
PROCEDURES TO BE FOLLWED BY CONTRACTORS” which will be issued to them at the time of signing this ag
2.31 All labor with necessary skills to be supplied and the Contractor. You are hereby requested to confirm your a
contents of this Awarded Agreement by returning to us one copy duly signed.
2.32 Contractor hall Submit As Built detailed Drawing before the final payment and it will comply 2.08
Construction drawings for this project are as per the following Drawings attached hereto:
Drawing No: :
5 OFFICIAL CONTACTS
5.02 CONTRACTOR
PAGE :
Alt :
DATE :19/05/2022
HOE of TFPL
em to ensure gravitational liquid flow or as per
FPL
d guidelines issued to contractor.
⁺
TFPL ORIGINAL DEBRIES
REMOVAL CHARGERS x
200%
CLEARANCE INSTRUCTIONS
Term 1.24,
Term 2.12
Term 2.08, 2.12, 2.21
Term 2.07, 2.09, 2.10, 2.12, 2.32
CHARGE
BILITY MATRIX
CONSUMABLES CONTRACTOR
LABOUR CONTRACTOR
5 < up to 10 Mn Rs 10 < up to 30 Mn Rs
ENGINEERING DEPARTMENT
Alt : 2.0
BOQ NUMBER : TFPL/ENG/BOQ/079
SHEET NAME : BILL OF QUANTITIES - CAR PARK
PROJECT NO : TFPL/ENG/RCXP/
PROJECT : CAR PARK DATE :19/05/2022
PRELIMINARIES
1.00 i).Contractors All Risk Policy including personal accident covers Item 1.00
2.00 ii). Workman Compensation Item 1.00
Allow lump sum for making adequate provisions against air and noise
4.00 pollution of surrounding areas. Hoarding and dust screens shall be Item 1.00
provided to control dust escaping to surrounding areas.
page 13 of page 7
LABOUR TOTAL MATERIAL MATERIALS
ITEM DESCRIPTION UNIT QUANTITY AMOUNT (Rs)
RATE/ RS LABOUR/ RS RATE / RS / RS
Sign boards and Name Board
All the payments are done accordinng to "Measure and Pay Basis"
The Employer has the right to define / adjust, the scope / quantity of
work to be carried out by the contractor time to time as required.
A DEMOLISION WORKS
Allow sum for demolision Steel structures and RCC structure, Removing
A.0 Item 1.00
debris out of factory premises.
Removing the damaged concrete surface of the road access to car park,
A.0.1 sq.m 30.00
Level the surface and remove debris out of factory Premises
page 14 of page 7
LABOUR TOTAL MATERIAL MATERIALS
ITEM DESCRIPTION UNIT QUANTITY AMOUNT (Rs)
RATE/ RS LABOUR/ RS RATE / RS / RS
Cuting 500 mm wide drain 300mm depth along the perimeter line to
A.5 l.m 325.00
have RR masonary Foundation.
Supply and placing 150mm Dia. 1000 gauge Weap holes along the RR
B.2 l.m 90.00
masonary Wall
Supplying & fixing PVC coated G.I. chain link fence (2"x2")of gauge 10,
1.8m height on GI pipe and flat iron frame complete with tension J bolts
and tension cords.Rate Shall Include Supplying and fixing 3" dia. X
2.9mm thick Medium quality GI pipe @ 2.4m intervals upto 1.9m clear
height above R/R masonary wall and 2'-0" length inserted in a 8 "x 8"
B.3 l.m 325.00
x2'-0" cement concrete base 1:2:4 (3/4") with 1/2" dia. MS rod welded to
bottom of G.I. Pipe, Supplying and fixing 1"dia. 2mm thick GI pipe
horizontal bracings top and bottom welded to GI vertical pipes., supply
and fixing of top cap on vertivcal pipes and applying two coats of enemal
paint with approved color over one coat of anticorosive paint.
page 15 of page 7
LABOUR TOTAL MATERIAL MATERIALS
ITEM DESCRIPTION UNIT QUANTITY AMOUNT (Rs)
RATE/ RS LABOUR/ RS RATE / RS / RS
B.4 Supply and Placing Concrete curb Along the Access to Car Park l.m 22.00
Allow sum for make a trench connecting to MFP trench, Laying of 100
mm Dia, 1000 gauge pipe , Back filling and Concreting the surface.
B.5 Item 1.00
Trench length 2m , Width 400 mm Depth 250 mm. Rate shall include for
1 Nos of ELBOW. Only pipe will be supplied by Trischel
Supply and fixing of 50 mm Dia, 3mm thick GI pipes along the fence
B.6 line to height of 1.8 m . Rate Include appling of anticorrosive paint and l.m 77.00
two coats of enemal paint with approved color
Concrete the car park and access road to match with car park entrance
level with G25 concrete, Appling of A142 mesh, Making expansion
joints with 12.5 mm regiform at every 3m intervals. Concrete thickness
C.1 100 mm. Rate Shall include placing of 1000gauge polythene, Concrete sq.m 1500.00
mixing, placing, compacting, curing and form work. Slope should be to
the perimeter. Keep 300mm spaces in 5m distance to discharge rainwater
along with fence concrete.
D ELECTRICAL WORKS
Supply and installation of 24W LED Lamp Poles 5m Height with 3 years
warranty. Rate include supply and laying of underground armoured
cables through GI, Lamp point wiring, Excavtion for bases, Concreting
works, Suppling and fixing of Distribution board (IP 68 Outdoor type )
and Gang Switch. Under ground cable shoud be covered with 300mm
thick layer of dense sand and concrete slabs of 50mm thick should be
D.1 Nos 20.00
places along the trench over sand layer. approximate length is about
500m. sealing all expose joints and connections with approved materials
to prevent water leaking to electrical system. All equipments should be
IP68 rated. Main cable to distribution board should be installed
underground from Chiller room (5Cx10mm2 CU/PVC/SWA/PVC -
maximum length 50m). Use necessary GI pipes.