Professional Documents
Culture Documents
General
required. Items or parts of items against which no price is entered shall be deemed to be covere
A elsewhere by the Contractor.
The Bid is to be inclusive of all Preliminaries for all the Works whether measured in full or covere
Provisional Sums.
Name of Parties
B The term "Employer" shall mean Nkhotakota District Council, P.O. Box 48, Malawi
The term "Project Manager" shall mean Directorate of Public Works, P.O. Box 48, Nkhotakota, M
C shall be represented by: The Director of Public Works.
.
D The Architect and Quantity Surveyor shall be represented by: Project Quantity Surveyor (Team l
Description of Works
The works comprise the Construction of 1No School Block, 2No Semi detached house and 4no
E all associated External Works
Bills of Quantities
Measurement of Building Works in Malawi, Metric Edition, and dated January 1982. Any diverge
F Standard Method of Measurement will generally be in order to provide further more detailed infor
These Bills of Quantities must not be used for the purpose of ordering materials and no liability w
by the Employer for any loss or expense incurred in this respect.
CARRIED TO COLLECTION
1.1
ITEM PRELIMINARIES
Plant
A Provide for all plant necessary for the proper execution of the Works comprising:-
D Provide all necessary measures for the safety of the public for the duration of the Contract.
Insurances
E Provide for insurance as outlined in Clause 13 of Conditions of Contract and Contract Data
Advance Guarantee/Bond
F Provide for Advance Guarantee Bond as outlined in Clause 50.1 of the Conditions of Contract
Performance Guarantee/Bond
ITEM PRELIMINARIES
Programme of Operations
Notice Board
be allowed on or adjacent to the site unless authorized by the Architect/Supervising Officer. All s
C be removed and disturbed areas made good upon completion of the works.
Temporary Buildings
Provide, erect and maintain the following buildings in positions approved by the Architect/Superv
D paying rates and other charges in connection therewith.
Suitable office accommodation for site agent, foreman and other supervisory staff
CARRIED TO COLLECTION
1.3
ITEM PRELIMINARIES
A All necessary mess room and living accommodation sufficient for all workpeople employed on th
Separate fly-proof latrine accommodation including washing facilities for all workpeople employe
be maintained in a sanitary condition whilst in use. After removal, the ground shall be disinfected
All workshops necessary for the preparation of joinery, servicing of plant, vehicle and equipment
B work carried on therein is directly related to the execution of the Works.
All covered and open yards for the preparation and storage of reinforcing steel and for pre-castin
components and the like to be used upon the Works.
The Contractor shall make his own arrangements for any temporary living accommodation requir
C shall abide by all national and local regulations in connection therewith.
D The following shall be provided by the Contractor as soon as possible after possession of the site
drawers, drawing racks and benches, pin boards and other like facilities which may be required.
E and in good order for the duration of the Contract.
Laws of Malawi
The contractor and his employees shall be subject to all laws of Malawi including taxation set in t
F Malawi
Value
The Added Tax
contractor shall provide Tax Payer Identification Number in the summary showing that paym
G Revenue Authority. Contractors without TPIN shall include Value Added Tax in their rates.
Supervision
ITEM PRELIMINARIES
Clause 34 Materials, Goods and workmanship to conform to description, testing and inspection
shall pay all costs in connection with any necessary testing thereof except testing charges only o
A be offset against the provisional sum included hereunder
B Allow a Provisional sum of MK 1000,000 in respect of testing of materials (for successful tests on
C Daywork Prices allowable in accordance with Clause 52 of the General Conditions of Contract sh
to cover foreman’s supervision, overheads and profits. The net amount of wages shall mean the
wages prescribed under the Regulations of Minimum Wages and Conditions of the Contract.
workmen engaged in that particular trade. Non productive time shall be chargeable net but only i
Architect/ Supervising Officer. Traveling expenses and Subsistence allowances paid to workmen
(2) Materials – materials used in carrying out dayworks shall be charged at invoice cost less all tr
profit and handling.
(3) Plant - Plant hire charges shall be at rates agreed with the Architect/Supervising Officer.
CARRIED TO COLLECTION
1.5
ITEM PRELIMINARIES
summaries or form of tender or any palpable pricing error by the tenderer shall be corrected duri
A tender.
B the price (such as misplacement of the decimal point) in that case the total amount as quoted sh
shall be corrected.
b) In cases where there is a discrepancy between the amounts in figures and words, the amou
c) In such cases the priced bills shall be amended to correct such errors and the corrected tota
adjusted with the agreement of the bidder.
The tender amount stated on the tender form shall be adjusted in accordance with the above pro
upon the tender. If the bidder rejects the corrected sum, then the tender shall be rejected.
Where any items remain unpriced, the work covered by those items will be deemed to be include
CARRIED TO COLLECTION
1.6
ITEM PRELIMINARIES
Temporary screens
D Provide, erect and maintain such temporary screens and the like as may be necessary.
Temporary Telephone:
ITEM PRELIMINARIES
General Scaffolding
A
Provide and erect all scaffolding including all stages, trestles, planks, guard rails, barrow runs an
execution of the Works and maintain, alter and adapt as necessary and remove when no longer
All scaffolding shall be in accordance with the provisions of the Factories Act and current Buildin
Welfare) Regulations
all charges in connection therewith, provide all temporary wiring connections, leads, fittings and t
make good upon completion of the works. All temporary electrical installations shall be to the ap
Tenderers shall note that although some sites are described as having water/electricity, this is ge
D and as such, Tenderers should ascertain for themselves which sites (if any) will have reliable wa
enable construction of the works and allow additional costs that might be incurred.
CARRIED TO COLLECTION
1.8
ITEM PRELIMINARIES
General
Works which are required to be carried out by nominated sub-contractors are dealt with elsewhe
A
cost sums included accordingly.
"Attendance", which will be treated as a lump sum and not subject to adjustment save for substa
the works, is given as an item in each case and shall be deemed to include for providing the follo
sub-contractor to carry out his work:
(i) Use of mess rooms, sanitary accommodation and welfare facilities.
(x) Obtaining full particulars in respect of making the position of holes, mortises, chases and th
CARRIED TO COLLECTION
1.9
ITEM PRELIMINARIES
(i) Obtaining full particulars of any special conditions imposed by any Sub-contractors Trade A
with such conditions when not opposed to this contract and when reasonably practical
Builders work in connection with works carried out by nominated sub-contractors is dealt with els
General
Goods and materials which are required to be obtained from nominated suppliers are dealt with e
Provisional Sums included accordingly.
Fixing only goods and materials is dealt with elsewhere and shall be deemed to include the follow
(i) Checking the quantity, quality and condition of all items before taking delivery. Any goods
found to be missing or damaged shall be replaced at the Contractor's own expense.
(ii) Taking delivery, loading and transporting around and adjacent to the site.
(iii) Unloading, unpacking, storing, returning pickings, handling, assembling (whether or not sp
lowering and fitting and fixing in position
(iv) Making and following up any claims upon the transporters, insurers and the like in the even
CARRIED TO COLLECTION
1.10
ITEM PRELIMINARIES
B
The Contractor shall be responsible for the adequate drying out of the Works and for maintaining
temperature and humidity until handed over.
C
Remove all rubbish and debris from the site both as it accumulates from time to time and upon c
shall not bury or otherwise conceal the same upon the site.
Clean the Works internally and externally upon completion to the satisfaction of the Architect/ Su
glazing and sanitary fittings
CARRIED TO COLLECTION
1.11
ITEM PRELIMINARIES
COLLECTION
CARRIED TO COLLECTION
1.12
INARIES
K t
x 48, Malawi
P.O. Box 48, Nkhotakota, Malawi. The District Council
comprising:-
9,000,000.00
2,000,000.00
e Conditions of Contract
ES
K t
2,000,000.00
ervisory staff -
2,600,000.00
ES
K t
ES
K t
ct/Supervising Officer.
100,000.00
ES
K t
ES
K t
fficer
as may be required to enable the Architect/Supervising
orks as and when he may wish to do so.
rvising Officer of items of equipment required for the
w:
may be necessary.
200,000.00
3,200,000.00
ES
K t
guard rails, barrow runs and the like required for the
3,000,000.00
nd remove when no longer required.
ries Act and current Building (Safety, Health and
ections, leads, fittings and the like and clear away and
tallations shall be to the approval of the
g water/electricity, this is generally a future provision,
if any) will have reliable water/electricity services to
be incurred.
3,300,000.00
RIES K t
ies.
ation
es, mortises, chases and the like.
-
RIES K t
o the site.
RIES K t
RIES K t
Page No.
1.1
1.2 13,000,000.00
1.3 2,600,000.00
1.4 -
1.5 100,000.00
1.6
1.7 3,200,000.00
1.8 3,300,000.00
1.9
1.10
1.11 600,000.00
22,800,000.00
BILL NO.2 CLASSROOM BLOCK (1NO)
SUBSTRUCTURE (PROVISIONAL)
Description Quantity Unit Rate K t
EXCAVATION -
-
Excavating -
-
Trenches; to receive foundations; starting -
from reduced level -
-
A not exceeding 1.50m deep 70 m3 3,000.00 210,000.00
Ditto; attached piers -
Extra over all kinds of excavations -
irrespective of depth for -
-
B excavating in rock 8 m3 10,000.00 80,000.00
-
Surface treatment -
-
Surfaces of earth subgrade -
-
C Compacting to 93% MOD AASHO 168 m2 3,000.00 504,000.00
-
Disposal -
-
Imported Gravel Type 1 material -
-
backfilling; depositing and compacting -
D to 93% MOD AASHO in 150mm layers 41 m3 9,500.00 389,500.00
-
Surplus excavated material -
-
E removing from site 37 m3 1,500.00 55,500.00
-
DISPOSAL OF WATER -
-
Keeping excavations free from -
-
F general water 1 item -
-
PLANKING AND STRUTTING -
-
Sides of all kinds of excavations -
irrespective of depth -
-
G generally 1 item -
-
HARDCORE-GRAVEL TYPE 1 MATERIAL -
-
H 200mm thick compacted to 95% MOD -
AASHO well compacted and rolled 168 m2 2,800.00 470,400.00
To Collection 1,709,400.00
2.1
To Collection 11,774,400.00
2.2
FORMWORK GENERALLY -
-
Formwork; sawn -
-
Edges, sides or risers 2,200.00 -
-
D edge of slab; 100mm wide 74 m 22,000.00 1,628,000.00
-
E edges of external seat; over 300mm girth 4 m2 2,200.00 8,800.00
-
F extra over for round edges of slab 13 m 22,000.00 286,000.00
-
BLOCKWORK -
-
Hollow precast cement sand blocks; filled -
solid with concrete (Grade 15/20) in -
cement mortar (1:4) -
-
200mm thick; in stretcher bond and -
reinforced with 'brickforce' reinforcement -
every third course -
-
G walls 106 m2 32,000.00 3,392,000.00
To Collection 6,581,600.00
2.3
-
-
To Collection 924,400.00
2.4
2.1 1,709,400.00
2.2 11,774,400.00
2.3 6,581,600.00
2.4 924,400.00
-
D 50 X 75 mm Purlins 610 m 3,800.00 2,318,000.00
-
E 50 x 75 mm Strut 350 m 3,800.00 1,330,000.00
-
F 50 x 100mm Wall Plate 60 m 4,500.00 270,000.00
-
G 50 x 150mm Rafter 595 m 5,500.00 3,272,500.00
-
-
To Collection 15,869,000.00
To Collection 247,500.00
2.7
2.6 15,869,000.00
2.7 247,500.00
ROOF
TO SUMMARY 16,116,500.00
2.8
To Collection 4,943,200.00
2.9
COLLECTION Page
2.9 4,943,200.00
2.10 9,551,800.00
TO SUMMARY 14,495,000.00
2.10
To Collection 1,304,440.00
2.11
-
A 970 x 2400mm; type D1 4 No 279,360.00 1,117,440.00
-
-
Door frames; 1.2mm pressed steel; -
purpose made primed before delivery -
-
960 x 2400mm high overall for 200mm -
thick wall; pair 100mm steel butt -
B hinges; building in; D2 4 No 120,000.00 480,000.00
-
To Collection 1,597,440.00
2.12
-
-
To Collection 1,902,400.00
2.13
2.11 1,304,440.00
2.12 1,597,440.00
2.13 1,902,400.00
IRONMONGERY
TO SUMMARY BILL NO.2 236,000.00
2.15
To Collection 2,316,000.00
2.15
To Collection 932,000.00
2.16
To Collection 694,000.00
2.17
2.15 2,316,000.00
2.16 932,000.00
2.17 694,000.00
WALL FINISHES
TO SUMMARY 3,942,000.00
2.18
FLOOR FINISHES
TO SUMMARY 1,038,400.00
2.19
-
-
-
SHELVING
TO SUMMARY 202,905.72
2.20
To Collection 2,101,050.00
2.21
To Collection 2,510,950.00
2.22
2.21 2,101,050.00
2.22 2,510,950.00
SUMMARY Page
FOR
C Supply and install 10mm sq 2 core amoured cable from the main Distribution board to 7,500.00 262,500.00
school block Sub distribution board M 35
-
DISTRIBUTION BOARD -
Supply and install double door 4Ways single phase Distribution board complete with the
-
following:
-
1 No. 63A RCB with 30mA sensitivity as Wintrip, Crabtree /Legrand or equally approved
-
by the supervising engineer.
Earthing shall be provided for the whole electrical installation where all metal frameworks
E shall also be bonded. Provide 2400mm earth electrode clamped to 4mm² green cable, 50,000.00 50,000.00
grounded in an earth pit of 300x300mm and concrete cover.
Item 1
-
LIGHTING CIRCUITS (ROOM 1) -
-
FITTINGS AND ACCESSORIES -
Supply and install 34w, 220VAC 1500mm T8 LED fittings complete with tubes as
L 55,000.00 880,000.00
Glowlite/philips or equally approved by the supervising engineer (Internal lights)
No 16
-
Supply and install wall mounted weather proof round bulkhead fittings complete with 12w
M 55,000.00 330,000.00
LED bulbs
No 6
-
-
-
-
-
A Supply and install 1gang 1way weatherproof flush mounted switch 6,500.00 13,000.00
No 2
-
B Suply and install 5A 1gang 2way flush mounted switch No 2 6,500.00 13,000.00
Rate Amount
5,500.00 55,000.00
7,500.00 75,000.00
9,500.00 47,500.00
400.00 480,000.00
800.00 640,000.00
3,200.00 2,080,000.00
1,800.00 126,000.00
1,800.00 176,400.00
2,500.00 2,500,000.00
1,800.00 810,000.00
9,000.00 9,000.00
6,998,900.00
NKHOTAKOTA DISTRICT COUNCIL
CONTRACT NAME :CONSTRUCTION OF SCHOOL BLOCKS AND TEACHER HOUSES AT KHWAPHU PRIMAR
SCHOOL
CONTRACT NO:
SUMMARY OF BILLS
No. DESCRIPTION
UNDED BY GOVERNMENT OF
CLASSROOM BLOCK
Amount (MK)
6,998,900.00
66,436,885.72
2,162,500.00
75,598,285.72
BILL NO 3: SEMI DETACHED TEACHERS HOUSE
EXCAVATION (Provisional)
FILLING (Provisional)
DISPOSAL (Provisional)
SAND BLINDING
ANT TREATMENT
CONCRETE WORK
SAWN FORMWORK
BLOCKWORK (Provisional)
E 50 x 75 mm Strut m 0 3,800.00 -
CONCRETE WORK
METALWORK
WINDOW FRAMES
GLULAM
G 25 x 50 mm Batten m 0 2,800.00 -
SUNDRIES
GLAZING
CONCRETE WORK
REINFORCEMENT
SAWN FORMWORK
BLOCKWORK
JOINERY
HARDWOOD WINDOW FRAMES
PLASTERWORK
FILLING
CONCRETEWORK
SAWN FORMWORK
JOINERY
B 50 x 50 mm Rail m 0 5,500.00 -
FITTINGS
CONCRETE WORK
A Plain in-situ concrete (class 14N/mm2/20mm) in
100 x 150 mm kerb m² 0 18,000.00 -
B Sawn formwork to sides of kerb, 75 to 150 mm wide m 0 3,300.00 -
PLASTERWORK
S Form hole in one block wall for small pipe and make
good No 0 2,000.00 -
Rates for all bends, tees, valves and fittings shall include
for the corresponding screwed/flanged joints to adjoining
pipework
RETICULATION TO FITTINGS
K 20 mm Ditto No 0 35,000.00 -
TESTING
CHLORINATION
BUILDERS WORK
Z Form hole in one block wall for small pipe and make
good No 0 -
HOSEREEL SERVICE
RETICULATION TO FITTINGS
HOSEREELS
F "Angus" swinging arm (Model 3) hosereel to BS 5306
Part 1 and BS 5274, completet with wall mounting
brackets fixed to brick / concrete walls with and
including 8 No 10 mm diameter rawbolts, 25 mm
shut-off valve, lead-off shackle, 20 mm diameter x
30 metre length of non-kinkable fire hose and shut-off
nozzle and connect to pipework No 0 125,000.00 -
FIRE EXTINGUISHERS
G 4.5kg water/CO2 fire extinguisher, complete with
brackets fixed to block/concrete walls No 0 65,000.00 -
SUNDRIES
I Allow for testing the foregoing fire fighting services
including pipework to twice the working pressure Item -
EARTHING
C Supply, install and connect 2400 mm electrode
complete with clamps, to 70 sq mm bare
copper conductor Item 1 100,000.00 100,000.00
LIGHTING CIRCUITS
D 1 lighting point to a switch ( Spec WC, & Exam room ) No 2 33,000.00 66,000.00
POWER CIRCUIT
Circuit # 3 (2.5 sq mm )
E Radial to Extractor fan ( shower/wc-labour ) No 1 48,000.00 48,000.00
Circuit # 4 (2.5 sq mm )
F Radial to Extractor fan ( shower/wc- staff ) No 1 48,000.00 48,000.00
Circuit # 5 (2.5 sq mm )
G Radial to Extractor fan ( shower/wc- corridor ) No 1 48,000.00 48,000.00
Circuit # 6 (2.5 sq mm )
H Radial to Extractor fan ( shower/wc- reception corridor) No 1 48,000.00 48,000.00
Circuit # 7 (2.5 sq mm )
I Radial to Extractor fan ( shower/wc- staff ) No 1 48,000.00 48,000.00
Circuit # 8 (4.0 sqmm)
J Radial to water heater with 20A double pole switch
with neon indicator - ( labour & delivery WC ) No 1 75,000.00 75,000.00
Circuit # 9 (4.0 sqmm)
K Radial to water heater with 20A double pole switch
with neon indicator - ( Staff & corridor WC ) No 1 75,000.00 75,000.00
Circuit # 10 (4.0 sqmm)
L Radial to water heater with 20A double pole switch
with neon indicator - ( SPEC WC ) No 1 75,000.00 75,000.00
ACCESSORIES
FIXED APPLIANCES
A SUBSTRUCTURE
Refer SMM paragraph F19(a). It has been
assumed that strip footings, bases, beds and the
like within the ground will be poured against natural
ground. If formwork is required to such surfaces, the
contractor must include for same in his
excavations/concrete rates
EXCAVATION
Excavation/Filling (provisional)
Excavate trench from reduced level for strip footing from 0 to 4000 mm deep
18 m³ 3,000.00 54,000.00
Selected earth filling, deposited, spread and compacted in 150mm layers around
foundations 8 m³ 1,800.00 14,400.00
Disposal
Surplus excavated material from excavations, transporteda distance average 100
linear metres from excavations anddeposit in spoil heaps on site 9 m³ 1,600.00 14,400.00
150mm Thick (consolidated) filling well compacted and rolled 5 m² 2,800.00 14,000.00
Sand blinding
50mm Bed of sand on hardcore rolled to receivedamp proof membrane 5 m² 2,200.00 11,000.00
Ant treatment
Saturate surface of hardcore and top of block wallswith approved ant repellant 10 m² 1,300.00 13,000.00
CONCRETE WORK
BLOCKWORK (PROVISIONAL)
Blockwork with 1:4 cement sand mortar with brickforce wire at every fourth
course
200mm Thick brick wall in stretcher bond and reinforcedwith one layer of
"brickforce" reinforcement every third course 18 m² 32,000.00 576,000.00
B SUPER STRUCTURE
BLOCKWORK
Load bearing bricks built in sand and cement mortar 200mm thick; wall in Stretcher
bond; reinforced with one layer of 'brickforce' reinforcement every fourth course
Walls 24 m² 32,000.00 768,000.00
Sundries
Form a hole size 600 x 450mm through 200mm block wall including forming rough
arch over and plastering around internally in cement mortar (1:4) and make good 1 No 2,000.00 2,000.00
3 Ply malthoid damp proof course, over 140mm wide, laid under blockwork 6 No 1,200.00 7,200.00
C ROOF STRUCTURE
"IBR roofing"
0.55mm (28 gauge) IBR steel cladding, laid with one flute side laps and 300mm
minimum end laps fixed to timber purlins with and including 75mm long drive screws
(purlins generally at 1050mm centres) and side laps with 6 x 25mm sheet bolts at
600mm centres. All fixing to be complete with bitumen and flat galvanised steel
washers 10 m² 22,000.00 220,000.00
CARPENTRY
Unframed
50x150 mm softwood timber for Rafters (2" x 6'' x18") 9 m 5,500.00 49,500.00
50 x 75mm softwood timber for Purlins (2" x 3'' x18") 18 m 3,500.00 63,000.00
Fascia Board
Sundries
Two strand 4mm Diameter high tensile steel wire tie 1500mm girth with one end built
into block wall and other end around roof timber 3 No 4,000.00 12,000.00
Prepare, knot, stop, prime and apply one undercoatand two finishing coats of
gloss paint on
To collection 442,900.00
Doors
Framed, ledged, braced and battened doors shall be constructed having 45 x 100mm
stiles top, centre, bottom rail and bracing, grooved, morticed, tenoned and glued
together clad one side with 25 x 100mm tongued and grooved "v" jointed boarding
700 x 2050mm High framed, braced and battened door 2 No 125,000.00 250,000.00
Door frames
Rates shall include for lugs welded to back, building into blockwork and filling
cavity with cement and sand (1;3) Prior to delivery on site, the whole to be treated at
works with one coat red oxide primer
Standard metal door frame, size 750 x 2110mm overall, suitable for 140mm
blockwall, complete with one pair 2 No 100,000.00 200,000.00
Prepare, knot, stop, prime and apply one undercoat and two finishing coats of
gloss enamel on
Timber framed, ledged, braced and battened doors (measured overall) 6 m² 5,500.00 33,000.00
Prepare, prime and apply one undercoat and twofinishing coats of gloss enamel
on
General surfaces, exceeding 200mm and not exceeding 300mm girth Unless
otherwise stated, fixing is to timber 10 m² 5,500.00 55,000.00
To Collection 538,000.00
E IRON MONGERY
"Union AL643-24-77" 3 lever lockset and furniture set 1 No 25,000.00 25,000.00
"Union AL 8730" rubber door stop, fixed to floor screed 1 No 7,500.00 7,500.00
To Collection 32,500.00
PLASTERWORK
15mm Rendering (1:4) cement and sand, finished with a wood float
15mm Rendering (1:4) cement and sand, finished with a wood float
100mm High skirting with small cove at bottom and "V" joint to junction of rendering 7 m 400.00 2,800.00
Prepare and apply one water thinned coat and two coats of internal quality wash
"n" wear silk white on
EXTERNAL
BRICKKWORK
Point in cement and sand mortar (1:4) recessed jointsof blockwork 15 m² 2,800.00 42,000.00
Prepare and apply two coats styrene acrylic emulsion clear sealer on
Prepare, prime and two coats of external quality wash "n" wear silk white on
To Collection 221,400.00
G FLOOR FINISHES
POWER FLOATING FLOOR
Form sleeved opening through iron sheets for 110mm diameter pipe 1 no 2,000.00 2,000.00
Wooden drop hole cover 1 no 2,200.00 2,200.00
H EXTERNAL WORKS
SUMMARY
A SUBSTRUCTURE 1,958,400.00
Item
10 5,500.00 55,000.00
10 7,500.00 75,000.00
5 9,500.00 47,500.00
70 1,800.00 126,000.00
98 1,800.00 176,400.00
1 9,000.00 9,000.00
6,278,900.00
NKHOTAKOTA DISTRICT COUNCIL
CONTRACT NAME :CONSTRUCTION OF CLASSROOM BLOCKS AND SEMI DETACHED HOUSES AT KHWAPHU
PRIMARY SCHOOL
CONTRACT NO:
SUMMARY OF BILLS
CONTRACT NAME :CONSTRUCTION OF SCHOOL BLOCKS AND TEACHER HOUSES AT KHWAPHU PRIMARY SC
CONTRACT NO:
SUMMARY OF BILLS
No. DESCRIPTION
D VAT 16.5%(C)
ARY OF BILLS
284,150,238.52
42,622,535.78
326,772,774.29
53,917,507.76
3,267,727.74
3,267,727.74
387,225,737.54