Professional Documents
Culture Documents
CONTENTS
1 PURPOSE 3
2 SCOPE 3
3 EXCLUSION 3
4 APPLICABILITY 3
5 EQUIPMENTS 3
6 CONSTRUCTION SEQUENCE 3
7 ACCEPTANCE CRITERIA 7
10 COMPACTION CRITERIA 11
1) PURPOSE:
This document describes the step wise work procedure to carry out the Site Clearance, Land
development, Excavation and Filling , Compaction for Plot in planned and controlled manner
with reference to the drawings, technical specification and standards.
2) SCOPE :
It includes Site Clearance, Land development, Excavation and Filling , Compaction for Plot in all
types of soil. The work shall be carried out in accordance with the specification and
corresponding approved drawings.
3) EXCLUSION :
In case of very specific & mandatory customer’s need their processes & formats can be followed
as a part or in full. However in case of any conflict most stringent norms must be followed.
4) APPLICABILITY :
5) EQUIPMENTS :
Total Station
Measurement Tape
Water Level Gauge
Compactor
Tamper Plate
Hydraulic Excavator
Water Pumps
6) CONSTRUCTION SEQUENCE :
The work site shall be cleared of all materials and obstruction that may impede the site
activities. This requires the clearing of tree stumps and bushes and any other materials to
keep the area suitable for safe and proper placement of construction material and provide a
safe area for performing the foundation activities.
Clearing includes the removal of all trees and other vegetation, rubbish, stumps, pipes,
fences, stone walls, surface boulders, or other material that is not required.
Certain trees may be designated for saving, and these shall be carefully preserved. The
landscaper land architects approval must be obtained prior to removal of any trees.
Clearing shall include all the area affected by excavation and filling together with sufficient
additional area on which to stockpile stripped topsoil, and may also include further areas as
shown on the plans within the area of the development or subdivision.
Cleared material may be burnt on site unless otherwise directed, and provided such burning
is allowed by the relevant Authorities and carried out in compliance with their
requirements. The Contractor is responsible for obtaining a fire permit, and for any costs
relating to such. All ash and residual material from burning shall be removed from the site.
The Contractor is responsible for establishing a tipping point for all other rubbish, and for
any fees relating to such.
The area on which the fill is to be placed and the area from which the cut is to be removed
should be stripped of all vegetation and of such soils as are deemed by the Consultant
Engineer to be unsuitable to support the proposed loadings or for incorporation in fills.
Topsoil will need to be stripped to spoil as unsuitable material or stockpiled in positions as
required for subsequent re-vegetation. Any material which the Consultant Engineer
considered will inhibit or prevent the satisfactory placement of subsequent fill layers will not
be allowed to remain in the foundations of fills or will be treated as directed as directed by
the Consultant Engineer.
All trees up to a girth (perimeter) of 30 cm measured at one meter above the ground level
shall also be cut and useful portion of the trees so cut shall be stacked at a suitable place as
directed by the Engineer-in-Charge and shall be considered incidental to clearing and
grubbing operations.
The roots of trees shall be dug up to 60 cm below the ground level or 15 cm below
formation level whichever is deeper and after removal of all vegetable and organic matter
from the holes so formed by removal of the roots, holes and hollows shall be filled with
good earth in layer of 20 cm, well rammed, consolidated and levelled.
Stockpile locations will be subjected to the approval of the Consultant Engineer, and
regardless of this approval will be chosen so that they are unlikely to initiate instability of
either the stockpile or the natural ground. Stockpile sites will also be chosen so that the
stockpile does not inhibit natural drainage of the area.
b) EXCAVATION
Excavation shall be carried out in a phased manner to suit the construction schedule.
Excavation shall be by means of scrapers, bulldozers, hydraulic excavators, loaders, and
trucks or other self-propelled bulk earth-moving machinery.
Excavation shall be executed manually or hydraulic excavator shall be used to excavate the
earth and to off load onto the sides of Pits maintaining angle of repose distance. While
excavating, the earth is cut vertically / tapered / in steps as per the soil conditions at site to
avoid any kind of mishap caused by collapsing of the pit sides during the course of
excavation and foundation work.
The excavated earth is to be kept at a sufficient distance so that it does not create any
burden on the sides of excavated earth pits.
Cutting shall be done from top to bottom & also in tapper formation.
During excavation in sandy soil or water bearing strata, and particularly in black cotton soil
where there is every likelihood of collapsing of the sides of the pits, shoring and shuttering
made of wooden planks of sufficient thickness or steel frames of adequate strength to meet
the requirement are to be provided.
No undercutting of side of excavation shall be allowed.
Excavation in soft rock is done with the help of chisels (in case of manual excavation). Some
types of soft rock soils need to be soaked in water before excavation can be carried out. It is
not recommended to use blasting for excavation in soft rock.
Considering the quantum of excavation involved sufficient number of ramps with enough
road width for the movement of Hydraulic excavators / dumpers / tractor considered. Also
the slope of excavation shall be established.
The movement of equipment, trucks and storage of excavated materials, shall be such that
it shall not obstruct any construction activities of adjacent structures.
Material suitable for Fill shall be stored near the site at designated area.
Ensure that a suitable drainage arrangements to prevent surface water from any source
entering the foundation pits.
Ensure the arrangements lighting, fencing and others suitable measures for protection
against risk or accidents due to open excavation.
c) BENCHING
Shall be carried out where fill is to be placed on sloping ground (generally steeper than 6
horizontal to 1 vertical) These benches shall be cut nearly horizontally with fall towards the
fill area and shall be free draining. The width and height of the bench will depend on the
original ground slope. The rear batter of the bench shall have a slope of about 1 horizontal
to 2 vertical, unless otherwise approve by the Consultant Engineer.
d) LIMITS OF EXCAVATION
Care shall be taken that ground beyond the limits of the work shown on the plans is not
disturbed by excavation procedures.
Excavation shall be carried out to the lines, levels, dimensions and slopes shown in the
Drawings. The excavated faces shall be neatly trimmed and the top edges of the cuttings
neatly rounded. Under cutting of slopes will not be permitted under any circumstances.
Excavation shall be carried out in such a manner as to prevent erosion or slips, working faces
shall be limited to safe heights and slopes, and surfaces shall be drained to avoid ponding
and erosion.
Overhanging, loose or unstable material likely to slip should be cut back removed or
stabilized.
Rock cuttings and exposed rock surfaces shall be excavated so as to obtain smooth,
uniformly trimmed surfaces. Batters in cuttings shall be carried around curves in an even
and regular manner. Finished batters shall not have a slope steeper than that specified.
e) TOPSOIL
Topsoil shall be removed over the area which will be occupied by the complete works plus a
clearance of 2 metres. Topsoil shall be placed in a stockpile clear of the work to enable its
re-use in landscaping and re-vegetation.
Unsuitable material includes topsoil, peat and other highly organic soils, logs, stumps,
perishable material, rubbish, material susceptible to spontaneous combustion, free draining
susceptible to scouring, very fine sand, silt and organic clay and material with a CBR<1. Such
material shall be excavated and disposed off-site except for top soil required for vegetation.
Dispersive soils can be used only in accordance with guidelines provided by a Geotechnical
Engineer. Where unsuitable material exists in excessive depths the advice of a Geotechnical
Engineer is required. The Contractor shall lightly scarify the surface of the areas to receive
topsoil to a depth of 50 mm. This shall be achieved by use of a rigid fine harrow making at
least 3 passes or an approved alternative method.
Topsoil shall be spread over the prepared surface in sufficient quantity to result in a
compacted thickness 100 mm or thicker to make use of all topsoil stripped from the site.
The placed topsoil shall be lightly harrowed to give a uniform appearance and compacted by
flat rolling.
Before any loose layer of fill is compacted, the material and its moisture condition should be
as uniform as practicable throughout its depth.
The maximum particle size of any rocks or other lumps within the layer after compaction
should not exceed 100 mm.
Each layer being leveled, wetted and tamped properly before the succeeding layer is laid.
Each layer of earth shall be consolidated by ramming with approved mechanical compaction
machines.
Compaction of the back fill shall be conducted evenly throughout the excavation area.
Compaction from one corner or one side of an excavation hole shall not be allowed.
The Fill shall be compacted to the maximum while filling the layers one over other.
Manual compaction by tampers shall be allowed in some cases.
Mechanized rollers / plate compactors shall be used for compaction to achieve the required
compaction. At site moisture content shall be checked with the help of rapid moisture
meter or by drying in oven in lab (as required by client).
If there is a delay in the placement of subsequent layers, previously accepted layers which
have wetted up or dried out, shall be tined, moisture conditioned and again compacted to
the requirements of this Specification.
Where fill is to be placed over wet or boggy areas, a heavy grade non-woven geotextile such
as Bidim A34 or equivalent shall be placed directly onto the prepared Pit.
site is to be left unattended, the surface of the fill shall be sealed with rubber-tire or
smooth-wheeled plant and graded to prevent ponding.
7) ACCEPTANCE CRITERIA
Ensure person works only after proper fixing of wooden/steel sheets along the sides of pit
wall.
Excavated materials / other construction material shall not be kept at the edge of the
excavation pit. The excavated earth need to be dumped at least 1-2 m away from the edge
of the excavation.
Dewatering from excavated pit ‐ Moving parts of Dewatering pump shall be guarded. Power
supply for the pump shall be through ELCB and the pump shall be earthed. PPE’s, like safety
helmets, hand gloves, gumboots / safety shoes etc. shall be used.
The fitness of the equipment (JCB which is going to be used) and driver to be checked by the
concerned engineer/ supervisor and safety supervisor. In any case if the safety supervisor
could not reach the spot on the same day, the work can be started after the concerned site
supervisor is satisfied after checking the equipment. It must be ensured that the operator is
having the valid license to operate the equipment.
Before starting filling ensure that area is clear from construction utility material.
Before starting the filling ground condition and stability shall be checked.
Don’t stand near to the earth moving equipment in operation.
Use stoppers for not letting filler machine to go near the edge of the pit.
No one other than operator shall be allowed to sit in operator’s cabin.
Filling shall be done layer by layer after confirming proper compaction in each layer.
Proper access to the area to be Filled shall be ensured.
Ramps should not have more than 15‐degree angle.
Ramps should be free from obstruction.
Fill shall be compacted to a minimum dry density ratio of 98% Standard Proctor (NZS4402)
unless otherwise specified, or shown on the Drawings. Testing shall be undertaken by the
Contractor as required by the Engineer, in accordance with the guidelines presented in
NZS4402, to confirm that the fill has been compacted to these specified minimum criteria.
The achieved compaction may also be checked using a dynamic cone penetrometer
(NZS4402), but this will only be undertaken after a correlation between dry density ratio and
penetration resistance has been established for the particular site and for each of the typical
materials encountered. Where a dispute exists as to the achieved compaction, the results of
direct measurements of dry density ration (NZS4402) shall be deemed to apply.
The upper layer of filling immediately below road sub-grade level shall be compacted to a
minimum dry density ratio of 98% Standard Proctor. This may be carried out at the time of
pavement construction. The Contractor must allow in the lump sum tender price for
compaction tests as required by the Engineer.
All fill layers have to be compacted, tested and approved by the Engineer prior to filling
upper subsequent layers. Contractor to allow compaction testing at a rate of 1 test per
100m2 (10x10m grid).