ELECTRICAL (C-10)
Content of the Examination • Selection and use of electrical testing
equipment
The Electrical (C-10) Examination is divided into five
• Energy production and storage system
major sections:
performance (photovoltaic, wind, generators,
batteries, capacitors)
1. Planning and Estimating (24%)
• Existing system evaluation
5. Safety (20%)
• Plan and specification interpretation
• Lockout/tagout procedures
• Electrical calculations
• Personal protective equipment (PPE)
• Code requirements
• Tools/equipment
• Material selection
• Hazardous materials and job site
• Energy production and storage project
environments
planning (photovoltaic, wind, generators,
batteries, capacitors) *Percentages are approximate*
Below are three typical examination questions. Publisher information for reference books and code
The correct answer is underlined. is provided below. Other sources for reference
books may be found online. California code books
1. Which of the following applies to solar panels, can be viewed online: www.dgs.ca.gov/bsc
metal frames, and metal mounting equipment on a
roof-mounted PV system? 2019 California Building Code. California Code of
Regulations, Title 24. International Code Council.
a. They must be weatherproof. PHONE: (800) 786-4452
b. They must be wind resistant. INTERNET: www.iccsafe.org
c. They must be anodized aluminum.
d. They must be bonded and grounded. 2019 California Electrical Code. California Code
2. Which of the following regulations applies to of Regulations, Title 24. BNI Publications, Inc.
service-entrance conductors that are supplying PHONE: (888) 264-2665
service to a building or structure? INTERNET: www.bnibooks.com
a. The conductors may not pass through the 2019 California Energy Code. California Code of
interior of another building or structure. Regulations, Title 24. International Code Council.
b. The conductors are permitted if the buildings or PHONE: (800) 786-4452
structures are close together. INTERNET: www.iccsafe.org
c. The conductors are only permitted when
approved construction drawings show the 2019 California Fire Code. California Code of
conductor routing. Regulations, Title 24. International Code Council.
d. The conductors are only permitted when PHONE: (800) 786-4452
service cannot be installed in any other way. INTERNET: www.iccsafe.org
3. A contractor needs 13 receptacles that cost $3.56 American Electricians’ Handbook. McGraw-Hill
each plus sales tax of 7.25%. The supplier states Professional.
that for every 10 receptacles that are purchased, PHONE: (877) 833-5524
the contractor will get one free of charge. What is INTERNET: www.mhprofessional.com
the total cost of the receptacles?
State of California General Industry & Electrical
a. $42.02 Safety Orders (Cal/OSHA) and State of California
b. $42.72 Construction & Electrical Safety Orders
c. $45.82 (Cal/OSHA). 2019. California Code of Regulations,
d. $49.66 Title 8. Mancomm.
PHONE: (877) 626-2666
INTERNET: www.mancomm.com
*All questions are written and reviewed by licensed
contractors who are actively working in the trade* VIEW ONLINE:
www.dir.ca.gov/dosh/LawsAndRegulations.htm
13E-10