Professional Documents
Culture Documents
A Multi-National Perspective
Introduction th th
From the 15 to 17 century shafts grew in
This paper will review vertical shaft sinking dimension to 3m diameter and 60 m in depth with
methods by conventional drill and blast methods the introduction of early pumping technologies
in Canada and South Africa. There are many th
and in the 17 century the application of
areas of study such as mechanical excavation gunpowder.
methods and inclined shafts, and special
applications such as freezing and tubbing, which With the industrial revolution and the advent of
have not been addressed in this paper. Since this steam power the mechanization of hoisting plants
is a broad overview of shaft sinking practices in and the availability of iron and steel tools meant
that there was a much greater demand for certain The Project Process & Contractor Selection
metals, as well as the means to access them. The project process includes a number of steps
Shafts grew to 4m diameter and up to 300m in that have substantial impact on the cost,
depth. In South Africa in 1897 a 4 compartment schedule and makeup of the final product. From
timber shaft was sunk to a depth of 727m. the concept and feasibility studies, through to
(Thompson, 1970) evaluation of options and a decision on the path
forward, the process of initial engineering is
critical to the success of the project.
The use of drill jumbos in the USA attracted By 1990 drill jumbos had been used on a number
interest from both Canada and South Africa. The of shaft projects in South Africa, and although
concept of a sling down drill jumbo was of they were a proven technology, were not the
interest, however in South Africa the jumbo predominant method. These jumbos were sling
productivity would have to better 25 drills and down units and the number of drills on a jumbo
would have to pay for itself in a market with a was limited by the ability of the hoist to lift the
relatively low labour cost in relation to North unit, and by the physical size of the openings in
America. The capital for the initial units was the stage through which the unit would have to
relatively high as well. South African shaft sinking pass. By the 1990s it was recognized that
first used drill jumbos on a major shaft excavation jumbos provided enhanced productivity per
in the late 1970s where a 4 boom sling down manshift and reduced costs per metre sunk. The
pneumatic unit was used to sink the Cooke drilling depth of 3m matched well with cycling two
No.2A 6m diameter vent shaft. Stage mass 3m deep rounds per day. One of the main
limitations at depth to keep within rope load constraints was the capital requirement, where
factors favored sling down units. The simpler the initial cash outlay for the equipment was
pneumatic drifters were preferred as the air was substantially more than the plugger method.
already at the shaft bottom for the cactus grabs
and blowover. Following this experiment a 6 Today the drill jumbo has by and large
boom Gardner Denver unit was employed on the superseded hand held drill sinking methods in
Cooke No.3 shaft, a 9m diameter shaft of 1373m South Africa. Drill jumbos of 7 booms and
in depth. The crew size for this job was reduced capable of 6m drilled rounds are in use.
from 57 sinkers per shift to 24 sinkers per day. Pneumatic drills with hydraulic booms are the
(Chadwick, 1983) Despite the drastic reduction norm, and well suited for the often wet conditions
in manpower, the savings in labour costs may not encountered in South African shafts.
have offset the capital cost of the drill rig at that
time. With much higher labour costs, and much smaller
shafts, Canadian and North American shaft
drilling evolved differently to the South African
industry. The typical drilling equipment for many
years in the industry was the plugger, a single
man jack hammer style drill that is still in use
today. Where the shafts were mainly rectangular
timber shafts, a benching technique was used to
drill half the shaft bottom to a depth of 2.4m,
resulting in an equivalent break of 1.2m of shaft
per blast. With less room for drills, and more
expensive labour, shaft drilling crews would be
anywhere from 4 men up to 9 men per shift.
The lining serves a number of purposes, the main In South Africa the concrete supply is usually
ones being: from a batch plant on site, often adjacent to the
• To provide passive local support of the shaft shaft itself. Batch plants of 20 to 30m3 per hour
wall; are typical. Placement is through a slick line, a
• To seal the shaft walls; vertical pipe in the shaft dedicated to concrete
• To produce a smooth shaft wall of low transport. The pipe is a 150mm diameter heavy
aerodynamic resistance and; wall pipe that is connected by flanges and
• To provide a precisely located surface to fix aligned with a plumb line to be vertical. Often two
services and shaft furnishings to. lines will be present to provide some contingency
for a plugged line. Concrete falling in a pipe
Although many timber shafts have been sunk in undergoes some segregation and a remix is
Canada, it is recognized that a concrete lining attached to the bottom of the line to allow the
reduces shaft maintenance, especially for deeper concrete to remix before being distributed into
shafts and may eliminate critical down time in the two distribution hoses. The hoses feed a
main shaft access. distribution system on the work stage that
provides hose feed into the forms.
The lining is usually a 20 to 30MPa 28 day
compressive strength concrete. Design thickness The concrete required for a slickline placement
of 250mm to 300mm is a typical specification and method usually requires a spread of 500 to
is more a requirement of the physical installation 600mm. Super plasticisers are employed to
and excavation techniques and embeddments improve flowability and cohesion of the mix and
than of any ground control requirements. Pour to achieve early setting of the curb ring. Calcium
heights are often determined by set spacing, chloride is a common additive for this purpose.
which ranges from 5 to 6m in most shafts sunk Aggregate grading is critical and usually specified
today. within an envelope having a maximum of 20mm.
Ground Support
Although horizontal stresses do vary
considerably from region to region in South
Africa, the stress differential encountered is
typically less than that experienced in the
Canadian Shield. Deeper shafts in Canada and
particularly in the Canadian Shield are more
prone to bursting ground at depth. INCO shafts in Ground Support Installation in Canada
the Sudbury area (Creighton No.9 Shaft and
Victor) became active at depth of about 1000 In Canada the deeper shafts are sometimes
metres, and destressing methods were subject to rock bursting. Various methods of
employed. The Macassa shaft in the Kirkland destressing have been employed, the most
Lake area was particularly active (as was the common being drilling of destress holes. Usually
mine), and this is most likely due to the very high a hole is drilled twice the length of the round and
stress differential in this area. the toe of the hole is blasted with the round, to
destress the area directly below of the round.
Temporary or permanent ground support over
and above the concrete lining is often required. More common in South Africa is the requirement
Usually the shaft walls will require a certain time for cover drilling to encounter and deal with
period to relax before applying the concrete potential water inflows prior to exposing a water
lining. The grab system of mucking requires the bearing structure. For both destress drilling and
shaft concrete to be back approximately 15m cover drilling the shaft jumbo has reduced time
from the bottom, providing ample time for the and effort required to drill these holes.
shaft walls to incur any initial movements prior to
concreting. This means that there is 15m of Equipping
unsupported ground above the shaft bottom. The The installation of shaft furnishings and services
ground conditions may dictate bolts, screen or is a critical part of the shaft sinking process. The
other support techniques. In some cases fine alignment required for shaft steel requires
shotcrete has been applied and may see more engineered systems and a controlled and
applications in shaft sinking in the near future. systematic approach to checking, jigging, aligning
and rechecking shaft steel installations. Typical
The main method for installing ground support in alignment requirements are to accuracy of +/-
both countries is by hand with hand held drilling 3mm in plan and elevation.
equipment.
During sinking certain services are required for
In difficult ground some projects have gone to the shaft sinker, including a concrete line,
pouring to the bench, however this method is not compressed air, service water, and ventilation
generally conducive to jumbo drilling. ducting. These services are installed during
sinking to maintain service to the work stage.
Ground support is part of the sinking cycle,
although with shaft jumbos requiring less than a In South Africa most shafts are equipped after
full crew, additional crew can bolt concurrent with the shaft excavation and lining is completed. The
shaft sinking equipment is brought up to surface
and any ducting or services no longer required It is recognized that the continuity provided by
are stripped out. Although the option exists to equipping after sinking is beneficial, however
equip from the bottom up, the majority of equipping during sinking is a method that has
installations are from the top down. Special certain applications.
equipping decks are installed and suspended in
the shaft for the crews to work from. Certain In Canada shaft steel fabrication and jigging is
installations require a brattice wall, these are most often done by a fabricator as opposed to
precast concrete panels that form a wall to the Contractor or the mine Owner.
separate the shaft into two distinct Comprehensive quality assurance programs are
compartments, allowing the shaft to be a fresh air applied at site to ensure the tolerances required.
and return air system. Installation of a brattice
wall is most effectively done from the bottom up. Labour Utilization
Once the brattice wall is installed crews come Historically the South African mining industry has
back down with separate equipping decks to had low labour costs in relation to North
complete the shaft furnishings. Certain projects American operations, and still does. It is
have installed brattice wall and steel recognized that the gap is shrinking, the cost of
simultaneously from the bottom up. Although not labour on a South African project is more
common, the approach is feasible. significant than in the past. Past practices have
been labour intensive, and operations like
In South Africa, a significant part of the shaft cleaning the bench have not be an issue with
steel fabrication, jigging and drilling is done by large crews to hand muck the clean up. Large
sinking crews on site. drilling crews are being reduced as shaft jumbos
become more commonplace.
In Canada there are two methods for equipping.
The first is to sink the shaft unequipped, as is In South Africa the call out system is sometimes
done in South Africa and installation methods are used to schedule shaft crews. Crews are trained
quite similar. Shaft steel is installed from the top as specialists and are called out as required to
down. work on the part of the cycle that they specialize
in. The mucking crew will be called out when
required and will muck until their work is
complete. The drilling crew will only drill. This
method allows faster and better training of
miners, and allows groups to perfect their areas
of specialty.
Deeper shafts which will require more powerful As we mechanize our shaft operations we also
hoists, and advanced rope technology. The create the opportunity for remote operating and
problems experienced to date with sinking ropes automation. If automation and remote operations
(particularly bucket ropes) in ultra deep shafts can remove men from the shaft bench temporary
have not yet been definitively resolved. ground support can be eliminated, and
(Wakefield, Wallace,& Davidtsz, 2000) concurrent activities that would in the past
created risk for crews would become feasible.
In North America a number of advances and
innovations in shaft sinking have been through
the drive and commitment of the Mine Owners. Conclusions
One would expect the shaft sinkers to be driving “The subject of shaft sinking, the most
the innovation process, however without the complicated of all mining problems….”, is the
support and commitment of the Owners, new statement that Mr. J.W. Brough uses to preface
ideas don’t get a chance to be applied in long the book “Shaft Sinking in Difficult Cases”
term operational settings. When a Mine Owner (Riemer, J. 1907).
has many shafts to sink the potential gains from
investing in innovation are evident, however What complicates shaft sinking is the many
major shaft projects happen so seldom in intangibles that many other engineering and
Canada that it is often difficult for Mine Owners to construction disciplines do not encounter. As we
see long term benefits from “experimentation” on continually go deeper the rules of thumb and
their project. experience of yesterday sometimes do not apply,
and we constantly deal with new situations. We
In South Africa the industry recognized that have a mix of sinking methods, which date back
regulations had to expand to recognize the 50 years or more, in combination with constant
degree of sophistication of current and future innovation and new technologies.
technologies. This trend has come to Canada,
where Quebec has made legislative revisions for Within any contracted project, the goals and
deep shafts, and Ontario will follows this year. relationship between the Owner and the
The next step is to define the intent of those Contractor can be the difference between a
revisions as they apply to shaft sinking. South fluently executed project or a struggle to
Africa has taken that step, and Canada is about complete it successfully.
to initiate the process.
As projects become more complex and the rules
The development of non-explosive methods of of thumb change, successful performers of
excavation will result in a continuous system of yesterday do not guarantee success today. The
excavation for shafts. Experimental products old style project manager has given way to a new
breed with skills in various areas and a focus on
satisfying the requirements of all the CHADWICK, J. 1983. State-of-the-art shaft
stakeholders. sinking at Cooke No.3. World Mining Magazine,
February 1983, p. 31-33
Shaft sinkers must foster and reward pride in
workmanship. This comes from recognizing that ROSCOE, R. 1983. In-House Shaft Sinking, Past
the work we do is very special and that very few and Present, at St.Joe Minerals New Lead Belt,
groups around the world who can carry out the Southeast Missouri. SME-AIME Annual Meeting,
projects that our Clients have entrusted us with. 1983, Paper No. 83-58
We need to recognize that we must continually McLAUGHLIN, B. 2000. Productivity from Deep
improve. Each successful project should be a Shafts, Using Technology to Lower the Rope
platform to build from. Each difficult project will Safety Factor,
provide lessons for future success. We need to
develop a knowledge base and some continuity WAKEFIELD,T.E., WALLACE,I.J., & DAVIDTSZ,
to benefit from past experiences. With the volume P.J. 2000. Rope experience gained from sinking
of work in South Africa, there is a wealth of the South Deep main and ventilation shafts. Mine
knowledge and experience that will be of benefit Hoisting 2000 SAIMM, p. 139-146
to Canadian operators in the future. And as DOUGLAS, A.B. 1989. Planning for Productivity
South Africa continues to mechanize operations, in Shaft Sinking. SAIMM Colloquium: Shaft
Canadian operators can make contributions as Sinking: Current Practices & Future Trends,
well. With every project we gain experience and Paper 11
see new techniques and methods that may help
us to operate safer, faster and more efficiently. RIEMER,J. 1907. Shaft Sinking in Difficult Cases
(Translated by J.W. Brough), Published by
The Art of Shaft Sinking is the successful Charles, Griffin and Company Ltd. London
combination of engineering and experience with England.
an understanding of the human element of the
work. It comes from a passionate pursuit of
accident free workplaces. It comes from a pride
in the work we do and a realization that we are
among the few in the world that can do this.
Knowing that despite all of our excellent systems
and designs, that the perfect process won’t be
successful without the people who believe in
what we are doing and are committed to
achieving our goals.
References
STRINGER, N., 2002. Ultra Deep Shaft Sinking,
Presentation to the Institute of Civil Engineers –
London. Unpublished