Customer continental engines pvt ltd Quantity reported Receive date Quantity returned
49 18/07/2018
D1 Team members Serial Numbers
Jagdeep singh solar
Ankur nehra
Omveer singh
D2 Description of problem Assigned to Effective Date
Lekage problem
Customer notified
D3 Interim Containment actions
Visual check 100 % for crack and dot marking in component after checking.
Penetration test implemented after every 2 hour. Ankur Nehra 18/07/2018
Customer notified
D4 Define the root cause
Sharp corners at joints .
Omveer 18/07/2018
Customer notified
D5 Choose and verify permanent corrective actions
Provided 0.5 radius in all sharp corners for strength and better flow of material.
Omveer 19/07/2018
0.5 Radius
Customer notified
D6 Validate permanent corrective actions
Radius provided in tool.
Ankur Nehra 19/07/2018
Customer notified
D7 Prevent reoccurrence of the problem
Radius provided.
Omveer/Sunil 19/07/2018
Customer notified
D8 Congratulate the Team
Leakage level reduced to much extent.
Initials Date Update N / Y / NA