METHOD STATEMENT & RISK ASSESSMENT

FOR INSTALLATION OF Bucket Elevator Steel Structure Tower


Above Silo 1 Roof Before Casting the Roof concrete

Related parties Comments Signature Date

Prepared
CDI
by

Reviewed
AP
by

Approved
QCC
by
A) Modification to the existing roof.

1. Existing detail of the support beams of the steel tower Before


modification.

2. In order to be able to install the steel tower before casting we will add some
reinforcements to the beams .
2.1. Modification 1: Weld a bracket to the bottom flange of the beam
as shown in the drawing to prevent the bending in X-Direction.

2.2. Modification 2: Weld stiffeners to the beam as shown in the


drawing to prevent the bending in Y-Direction.

Modification.pdf
3. Install and fully weld the wend bracing to the beam.

B) Lifting plan.

1- Divide the steel tower into two Parts and lifting with the tower crane, the
tower crane height will be increased to 73.4m,it is not exceed the
maximum height.
- Part 1:

Crane: tower crane


Height: 50.883+8.391=59.274 m
Radius: 28.3 m
Weight: 6.8 Ton
Weight*1.15: 7.82
Boom length: 65 m
Crane capacity: 8.7 Ton Safe
- Part 2:

Crane: tower crane


Height: 50.883+8.391+6.015= 65.289 m
Radius: 28.3 m
Weight: 6.5 Ton
Weight*1.15: 7.5
Boom length: 65 m
Crane capacity: 8.7 Ton Safe
7m
MC 310 K12

71,7 m
H1 = H + 10,7 m

70 m
4,3 m

20,5 m 12 t 3,2 t

3m 65 m

3,85 t
60 m

4,25 t H (m)
55 m
57,5
4,7 t
50 m

5,4 t
45 m

6t
40 m

6,7 t
35 m

18 m 7,95 t
30 m

12 m 9,6 t
2x2m

MCB 1 6m

TÜV FEM 1.001-A3


ISO 9001
Masts / 2m H(m)
Reactions H(m)
12 57,5
30 m ➡ 70 m 11 54,5
MCB 1
12 52,4 10 51,5
11 49,4 9 48,5 H(m)
10 46,4 8 45,5
9 43,4 P 21 A 7 42,5 VB 21 A 12 38,8 BA 66 A
8 40,4 F2 148 t 6 39,5 11 35,8

3m
5 36,5 F1 99 t 10 32,8 30 m ➡ 45 m
7 37,4 147 t
6 34,4 4 33,5 98 t 9 29,8
3m

H
5 31,4 F3 90 t 3 30,5 88 t 8 26,8
4 28,4 97 t 2 27,5 7
3 25,4 75 t 1 24,5 6

3m
2 22,4 5 50 m ➡ 70 m

7,5 m 7,5 m
1 19,4 4
3
7,5 m 7,5 m

2
1

12,8 m

0,32 m
0,15 m

1,5 m
6m
F2 F3 F1

TOPKIT
MC 310 K12

Climbing crane
MCB 1
BA 66 A

30 m ➡ 45 m

2m
A H1 P
H1 (m) (m) (t)

R 16 38,8 96,1
A
15
R 35,8 94,6
14
P 13 32,8 93

12
29,8 91,5
11
1500 1300
10 26,8 90
2170

20 22 24 26 28 30 R (t)

TOPKIT
MC 310 K12

GB
Reactions in service
Reactions out of service
Without load, ballast (or transport axles), with maximum jib and maximum height.
Consult us
See climbing crane
Load diagrams
70 m 3,1 21,4 22 25 27 30 32 35 37 37,4 41,9 45 47 50 52 55 57 60 62 65 67 70 m
MCB 1 12 10 9,1 8 7,3 6,5 6,1 6 6 5,5 5,2 4,9 4,6 4,3 4,2 3,9 3,7 3,5 3,4 3,2 t
12 11,6

65 m 3,1 22,8 25 27 30 32 35 37 39 40,4 44,7 47 50 52 55 57 60 62 65 m


12 10,8 9,8 8,7 8 7,2 6,7 6,3 6 6 5,7 5,3 5 4,7 4,5 4,2 4,1 3,85 t

60 m 3,1 22,8 25 27 30 32 35 37 39 40,4 44,7 47 50 52 55 57 60 m


12 10,8 9,8 8,7 8 7,2 6,7 6,3 6 6 5,7 5,3 5 4,7 4,5 4,25 t

55 m 3,1 22,8 25 27 30 32 35 37 39 40,4 44,7 47 50 52 55 m


12 10,8 9,8 8,7 8 7,2 6,7 6,3 6 6 5,7 5,3 5 4,7 t

50 m 3,1 23,3 25 27 30 32 35 37 40 41,2 45,7 47 50 m (t)


12 11,1 10,1 8,9 8,2 7,4 6,9 6,2 6 6 5,8 5,4 t
12
6 - 0,75 t
45 m 3,1 23,8 25 27 30 32 35 37 40 42 45 m
12 11,3 10,3 9,1 8,4 7,6 7,1 6,4 6 6 t (m)
= - 0,75 t
40 m 3,1 24,7 25 27 30 32 35 37 40 m
12 11,8 10,8 9,5 8,8 7,9 7,4 6,7 t

35 m 3,1 24,8 25 27 30 32 35 m
12 11,9 10,8 9,6 8,9 7,95 t

30 m 3,1 24,9 25 27 30 m
12 11,9 10,9 9,6 t

TOPKIT
MC 310 K12

Counter-jib ballast 4 200 - 700 kg


4 600 - 4 200 - 2 300 kg
MCB 1

(kg) (kg)

70 m 20,5 m 24 500 20,5 m 24 500


65 m 20,5 m 23 700 20,5 m 23 800
60 m 20,5 m 21 800 20,5 m 21 700
55 m 18 m 24 900 18 m 24 500
50 m 18 m 22 600 18 m 22 400
45 m 18 m 19 500 18 m 18 900
40 m 18 m 17 200 18 m 16 800
35 m 18 m 14 900 18 m 14 000
30 m 12 m 20 700 12 m 20 300

Base ballast H (m) 57,5 54,5 51,5 48,5 45,5 42,5 39,5 36,5 33,5 30,5 27,5 24,5 21,5
2m VB 21 A
MCB 1 (t) 84 72 72 72 72 72 72 60 60 60 60 60 60

GB
Anchorages Reactions in service 139,4 m
MCB 1
Reactions out of service 118,4 m

Without load, ballast (or transport axles), with maximum jib and maximum
97,4 m height.
Consult us P21A
76,4 m
106,65 m

52,4 m
See climbing crane
85,65 m
64,65 m
40,65 m

TOPKIT
MC 310 K12

GB
A Distance between collars
H1 Crane height
P Crane weight (in service)
R Horizontal reaction
Mechanisms hp kW
MCB 3

m/min 0 ➞ 40 0 ➞ 80 0 ➞ 20 0 ➞ 40
70 RCS 30 70 51 523 m
t 6 3 12 6

GB 75 LVF 30 m/min 0 ➞ 44 ➞ 56 ➞ 80 ➞ 114 0 ➞ 22 ➞ 28 ➞ 40 ➞ 57


75 55 570 m
Optima t 6 4,5 3 1,5 12 9 6 3
Reactions in service
Reactions out of service 6 D3 V4 m/min 15 - 50 (12 t) 100 (6 t) 7,4 5,4
Without load, ballast (or transport axles), with maximum jib and maximum height.
Consult us RVF 162 rpm 0 ➞ 0,7 2 x 7,5 2 x 5,5
Optima
See climbing crane
VB 20A RT 544
VB 21A A1 2V m/min 13,5 - 27 4 x 7 4 x 5,2
R ≥ 13 m

CEI 38 IEC 38 kVA

GB 70 RCS : 100 kVA


400 V (+6% -10%) 50 Hz 75 LVF : 100 kVA
A Distance between collars
H1 Crane height 75 LVF 30 Optima
m/mn
P Crane weight (in service)
R Horizontal reaction 114 + 25%
80
44

1,5 3 6 t
TOPKIT
MC 310 K12

GB
Hoisting
Trolleying
Slewing
Travelling

This commercial document is not legally binding.


! For any technical information, please refer to the corresponding instructions.

4 Kwong Min Road


Singapore 628707
Americas Tel: +65 6264 1188
Tel : +1 888 479 7278 Fax: +65 6862 4040
www.manitowoccranegroup.com
Tel : +1 717 593 2000

Europe – Middle East – Africa


Réalisation Sedoc

Tel : +33 (0) 4 72 81 50 00


Tel : +44 (0) 191 522 2000

Asia – Pacific
Tel : +65 6264 1188
Fax : +65 6862 4040
MC 310 K12
www.manitowoccranegroup.com
Réf. 2004 45 MCB 3

Copyright.Reproduction interdite © POTAIN 2004

Subject to modification