Date: 28.11.2021
1. Current Activities
- Continue cable pulling of MV and LV cables from substation no. [410] to Urea Plant.
- Official inspection after electrical work completion for Overhead Crane no. [3121] in NA plant.
- Continue installation work of secondary cable tray in unit no [8310].
- Continue installation work of main cable trays in trench of unit no [3412].
- Inspection of main earth grid beside pipe rack no. [0513].
- Start installation of lighting fixtures above deck level & stairs of [Cooling tower] as agreed with NCIC (Eng. Ayman).
- Continue installation of lighting fixtures in unit no. [8352].
- Continue cable pulling & dressing in main/Secondary cable tray route of pipe rack no. [1501 &1040].
2. Upcoming Activities
3. Area of concern
- Missing terminal lugs different sizes for a lot of safety switches & motors [ supplied by Petrojet].