You are on page 1of 2

Daily Works Report

Date: 07.12.2021

Manpower and Equipment


Manpower
2 Engineers 3 Supervisors
4 fitters & Technicians 17 Helpers
Equipment (Plant)
NA

1. Current Activities

- Continue installation work of secondary cable tray & conduits in unit no [1020].
- Continue cable pulling & dressing in main/Secondary cable tray route of pipe rack no. [1501 &1040].
- Continue modification work of LCS & safety switches locations in units no. [3130 & 8310].
- Preparing to start installation of neutral & line terminal boxes of the Generator no. 8851GM01 in unit no. [1020].
- Preparing to start installation work of lightning system of Cooling Tower.
2. Upcoming Activities

- Continue Lighting installation & termination works in Utility area.


- Continue secondary cable trays installation works in Ammonia & Utility plant.
- Preparing to complete cable pulling for unit no. [1020] in Compressors house.
- Preparation to start installation work of heat tracing system in all areas.
- Preparation to start installation work activity of Overhead crane in unit no. [1071].
- Continue Earthing installation work activity in [Utility & Ammonia plant].
- Continue cable pulling activity in [utility, Ammonia & Urea plant].
- Continue modification work of LCS & safety switches locations in unit no. [8310].
- Preparing to start installation of neutral & line terminal boxes of the Generator no. 8851GM01 in unit no. [1020].
- Preparing to start installation work of lightning system of Cooling Tower.

3. Area of concern

- Missing terminal lugs different sizes for a lot of safety switches & motors [ supplied by Petrojet].