Professional Documents
Culture Documents
1 of 7
DOCUMENT NO. :
P-T3109-EI-014
INSTALLATION PROCEDURE ISSUED DATE :
FOR 21-2-2009
UPS & DC SYSTEM
INSTALLATION PROCEDURE
FOR
UPS & DC SYSTEM
3X330 MW POWER PLANT PROJECT
INDRAMAYU- WEST JAVA.
DOCUMENT NO : P-T3109-EI-017
- SDCC : Original
- CNEEC : Copy
- All Dept. : Copy
00 09/2/21 09/2/21
1. TITLE
2. SCOPE
3. OBJECTIVE
4. REFERENCE
5. RESPONSIBILITY
5.1 The Electrical Engineer at site shall be responsible for the planning
scheduling and coordination, record and monitor progress of electrical
works. To guide the supervisors in the field in terms of engineering
and technical problems.
DOCUMENT NO. :
P-T3109-EI-014
INSTALLATION PROCEDURE ISSUED DATE :
FOR 21-2-2009
UPS & DC SYSTEM
6. WORK PROCEDURE
6.1 GENERAL
6.2 General
7. Safety
7.1 Before installation work, supervisor have to make coordination with
safety department. JSA/HIERAC shall be available on site when job is
on going.
7.2 Workmen wear proper PPE. (helmet, safety shoes, full body
hardness/safety belt etc.)
7.3 Check crane condition before mobilize to lifting area.
7.4 Check rigging tools & accessories condition such as slings, shackles
etc.
7.5 No activity to be allowed in and around lifting area.
7.6 Battery shall be handling carefully, must not capsize top and bottom.
7.7 Smoking in the battery room is not allowed.
DOCUMENT NO. :
P-T3109-EI-014
INSTALLATION PROCEDURE ISSUED DATE :
FOR 21-2-2009
UPS & DC SYSTEM