Professional Documents
Culture Documents
STAMP
OWNER
OWNER’S ENGINEER
CONTRACTOR
PROJECT
CONTROL OF MODIFICATIONS
Issue Modifications
1 N/A
DISTRIBUTION
External 1. Electronic
edition
Uzbek Scaling 100MW PV EPC Document No.: Owner Document No.
Project N0579-TJN-ET-MS0001 N0579-SEP-ET-MS0001
Page
Method Statement for Grounding installation
3/13
Rev. 02
Table of content
1. PURPOSE.................................................................................................................4
2. SCOPE......................................................................................................................4
3. PROJECT OVERVIEW.............................................................................................4
4. RESPONSIBILITIES.................................................................................................5
5. REFERENCE............................................................................................................8
6. OPERATION CONDITION........................................................................................9
7. WORK PROCEDURE.............................................................................................10
8. HSE.........................................................................................................................14
9. QUALITY CONTROL..............................................................................................16
10. ATTACHMENT.....................................................................................................16
Uzbek Scaling 100MW PV EPC Document No.: Owner Document No.
Project N0579-TJN-ET-MS0001 N0579-SEP-ET-MS0001
Page
Method Statement for Grounding installation
4/13
Rev. 02
1. PURPOSE
The purpose of this procedure is to define how Lightning and Grounding works shall be
carried out under controlled condition.
2. SCOPE
This procedure covers the general requirements of the Lightning and Grounding works
only for Construction of Uzbek Scaling 100MW PV Project.
3. PROJECT OVERVIEW
4. RESPONSIBILITIES
1) Controls adherence of all workers the rules and norms of HSE, daily inspection of
application conditions of HSE Standards.
2) Controls provisions of conditions of ensuring safety of works at the stage of
Uzbek Scaling 100MW PV EPC Document No.: Owner Document No.
Project N0579-TJN-ET-MS0001 N0579-SEP-ET-MS0001
Page
Method Statement for Grounding installation
7/13
Rev. 02
5. REFERENCE
6. OPERATION CONDITION
6.1. Machinery /Equipment and tools
6.2. Material
7. WORK PROCEDURE
7.2. General
Location and method of identification shall not affect the function or quality of
materials.
Material certificate shall be prepared, if required or specified on related
specifications.
Receiving and storing of the materials will be done as per manufacturer
recommendations.
1) Check that the rod is free from non-conductive coating such as paint or
enamel prior to being driven to the ground.
Uzbek Scaling 100MW PV EPC Document No.: Owner Document No.
Project N0579-TJN-ET-MS0001 N0579-SEP-ET-MS0001
Page
Method Statement for Grounding installation
12/13
Rev. 02
2) Verify the marking points for installation of the grounding rod as per the
construction drawings to ensure the correct positioning.
3) Each grounding rod shall be installed vertically to the required depth driven
into the soil.
4) Install grounding rods by inserting grounding rods to a depth of 19mm dia.
5) Upper end of the rod shall be flushed with or below ground level unless the
above ground end and the grounding electrode conductor are protected
against physical damage.
6) Prior to backfilling, it shall be ensured that the pits are barricaded (rebar) with
barricade warning tape to protect the electrode from heavy vehicle or
construction equipment during construction stage.
7) After backfilling electrodes around the substation (deep-well and transformer
neutral, etc. as per grounding philosophy diagram) shall be preserved in a
concrete ground inspection pit, with a concrete cover. Provide identification
marks for all ground pits as per grounding layout drawing.
1) Verify that the section of excavation is completed in depth and width as per the
construction drawings.
2) Verify correct size of conductor.
3) Verify that grounding conductor is properly installed and supported.
4) Verify that protective pipes for grounding conductors rising through paved or
concrete area are adequately installed and sealed.
1) Equipotential bar will be installed inside the room, the grounding for indoor
equipment will connect to the equipotential bar. The equipotential bar will be
mounted at the height of 0.3m from the finished floor level (FFL), The conductor for
LV SWGR room will be hot dipped galvanized flat steel of 60x8mm2. Conductor for
other room shall be hot dipped galvanized flat steel of 40x6mm2.
2) If there are more then 5 connections, two pcs. Equipotential Bar will be installed.
4) The single core 33kV cable will be grounded at one point, the 33kv three core cable
will be grounded at both terminals of cable.
5) The crossing of grounding through wall (if applicable) will be protected by PVC
conduit of relevant size.
6) The crossing of grounding through floor will be protected by PVC conduit of relevant
size.
8. HSE
1) Pre-work checklist and toolbox talk shall be discussed and filled prior to start the
job.
2) Notice will be raised when any unsafe behavior observed on site.
Uzbek Scaling 100MW PV EPC Document No.: Owner Document No.
Project N0579-TJN-ET-MS0001 N0579-SEP-ET-MS0001
Page
Method Statement for Grounding installation
15/13
Rev. 02
3) The emergency evacuation shall be explained to work force during toolbox talk and
proper barricade and sign boards to warn the people shall be placed, the exit
pathway shall be free for access.
4) Covid-19 pre-control.
The works must be conducted under the appropriate weather conditions for respective
type of works. In case the weather conditions create unsafe working conditions, the
countermeasures must be taken to provide safety of manpower, material and environment.
If risk is assessed high still after taking countermeasures the work must be hold or
stopped.
All the waste material will be segregated and disposed of from the site as per “Waste
management procedure – N0579-SEP-HS-PS0013”
Diesel & Oil:
Diesel and oil shall be restricted within drip trays to prevent contamination of the sand.
Bulk storage fuel tanks shall be bounded to contain waste or spillage.
Housekeeping:
All vehicles and plant will be kept in clean conditions. The working area will be kept clean
and clear of trip hazards. Any spillages will be cleared and reported immediately. All waste
Uzbek Scaling 100MW PV EPC Document No.: Owner Document No.
Project N0579-TJN-ET-MS0001 N0579-SEP-ET-MS0001
Page
Method Statement for Grounding installation
16/13
Rev. 02
will be deposited to the spill kits provided for disposal. All plant will carry a comprehensive
spill kit. For safety gas cylinders will be transported and stored in dedicated frames.
8.5emergency procedures
In all cases, the first contact shall be to the TIEJUN Site Management on site. After further
assessment of the situation, site management will take necessary actions/communications
to the related authority.
Identify the person and describe the incident
Provide nearest ambulance point/ emergency point location number
Nominate one person to stand at ambulance / assembly point to escort the ambulance or
fire truck to the incident locations.
EHS Representative TIEJUN Mr. Wang Yanwei+998 902335588
Emergency Number103
9. QUALITY CONTROL
10.ATTACHMENT
Risk Assessment
Risk Assessment
Project Name: Uzbek Scaling 100MW PV
Project
Date: 30.01.2021 Method Statement Reference: N0579-TJN-ET-MS0001
Risk Matrix
Likelihood(L)
Severity(S)
1 2 3 4 5
Happens
Heard of Incident has Happens several several times
Never heard of in
incident in occurred in our times a year in the a year at
Rating(R)
Electrical work Fatality Short circuit 3 5 15 Proper selection, installation, insulation, used 2 5 10
Personnel Injury
Electric shock and maintenance to avoid electrical hazards
Property damage
Visual inspection of cables for any damage prior to use.
Proper arrangement of tools and materials
Keep work access free from obstruction
Cables shall not cross to the doors or access way, recoil
excess cable if not required
Use right tools for the right job.
Protect sharp edge as much as possible
Fire hazard Appropriate PPE shall be provided
Environmental-
Impacts Related injuries Proper maintenance of the equipment shall be conducted
Use the appropriate fire extinguisher and easily accessible
/visible.
Proper housekeeping all time.
Make sure the power supply properly turn off or isolated
before doing work on live wire.
Apply appropriate first-aid and immediately summon/get
medical assistance in case of accident/injury.