Professional Documents
Culture Documents
Shailesh Chauhan
Shell Project &Technology
Stavanger
Norway
Over a period of years the site developed a robust The verification dossier is required as per above standard
competency development process, overcame resources to ensure that any installation complies with the relevant
and access issues to deliver a high quality Ex inspection equipment certificate as well as with IEC 60079-14
campaign. The journey includes some experiments to standard and any other requirements specific to the plant
overcome the access issues for the Ex equipment on which the installation takes place.
installed at an inaccessible height without installing
expensive scaffolding. An interesting use of abseilers to The “detailed” grade inspection of an Ex equipment
execute Ex close inspections and prepare Ex register is requires the equipment to be opened/dismantled for a
discussed with details. thorough inspection and checks. The equipment needs to
be in a de-energized state for the reasons of safety.
Various experiences and lessons learned during the four Significant numbers of the lighting and electric heat
year journey are shared in this paper. tracing equipments are installed at an inaccessible height.
They require scaffolding or other means to safely reach
Index Terms — Ex equipments, Rope Access, the equipment for detailed inspections.
Abseiling, Ex Inspection, Ex Maintenance.
If detailed inspections are planned after the plant is in
I. INTRODUCTION operation, then to de-energize and take an equipment out
of service (e.g. process critical heat tracing) could be
In the Oil & Gas Industry, during the project development challenging. To install scaffolding for Ex inspections in a
phases a careful consideration is given to the layout of running plant would be much more expensive and
electrical/instrument equipment. However, it is not always dependent on operations clearance.
technically feasible to install all equipment in a non-
hazardous area (Safe Areas). Thus for this reason risk The ideal opportunity for detailed inspections for Ex
mitigating measures are undertaken which mainly equipment is available during construction &
includes installation of “Ex” type equipment in hazardous commissioning phase of a project as part of the initial
areas, the special design of this type of equipment inspections. The equipment is easily available in a de-
minimizes the risk of it becoming an ignition source energized state. The means of access used for
causing an explosion. equipment installation are still available.
It is therefore essential for reasons of process safety that, The future Ex inspections become efficient and effective if
throughout the life of such installations, the integrity the initial inspections are carried out thoroughly and
associated with the special design is preserved by regular inspection records are properly transferred and
inspections & maintenance. maintained. Once the equipment state is known, the
optimal equipment inspection strategy could be decided
The IEC standards 60079-14 and 60079-17 provide per the guidance available in IEC 60079-17.
guidance and requirements for installation, inspection and
maintenance of electrical equipment in explosive gas
atmospheres. The latest revision of IEC 60079-14 (Nov
2013 edition) standard contains the following newly added
specific requirements related to initial Ex inspection.
II. CHALLENGES FACED AT A NEW NON-ATEX carrying out Ex visual inspection in each shift (12 hours)
SITE along with his normal operations tasks.
A. Background
The detailed inspections were embedded into corrective
A new Oil & Gas project was completed and the facility maintenance activities plans as opportunity maintenance.
was handed over to operations. When the electrical E.g. during lamp replacement the Ex lighting fixture were
maintenance team took over the electrical installations, no subjected to the detailed inspections. Similarly during
initial inspections records were available for the Ex bearing replacement activities the motors would undergo
equipment. The Ex register containing total inventory list the detailed inspection activities.
of Ex electrical equipment of the site was even not
available. During the project design phase, the initial Ex C. Ex Competency
inspections and relevant record keeping requirements
were not properly defined in the EPC contract scope of In order to address the competency issues all electrical
work. Hence the EPC contractor did not give proper persons involved in Ex inspections activities were sent to
attention to initial Ex inspection planning and execution. the local government-approved Ex training center. The
When the issue was identified during the operation supervisors & engineers were sent overseas for an
handover it was too late for EPC to act on. Ultimately the international recognized Ex training.
project failed to deliver good quality initial Ex inspections
and the inspections records along with an Ex register. To sustain continuous development of Ex competency on
a long term basis a contract was awarded to train the
Most of the electrical maintenance staff was hired from a local electrical trainers on – an internationally recognized
local market with gaps in their Ex competency. Ex course. An international recognized training service
provider delivered a “Train the Trainer” programme. The
B. Ex Maintenance Strategy package included supply of theory class training material
and Ex booths for the practical training. The training
A Computerized Maintenance Management System service provider first provided Ex training to the local
(CMMS) was being used by the organization to manage electrical trainers. Once they passed assessment they
all maintenance activities. To confirm that the state of all started delivering in-house Ex training program.
electrical Ex equipment installed at site met the required
integrity standards, Ex close inspections for 100% D. Access issues for Ex equipments installed at an
population of electrical Ex equipments were planned. The inaccessible height
plan included preparation of the Ex register along with the
Ex close inspection activities. Once the 100% population The close inspections activities were progressing very
is inspected and the state of equipment is known, the plan well for the Ex equipments installed at accessible height
is to continue with only sample close inspections, per the and ground locations. The main challenge was associated
requirements of IEC 60079-17. with the access to the equipments installed at
inaccessible heights. This includes mostly lighting fixtures
A dedicated team of 3 competent persons (supervisor + 2 and Electric Heat Tracing (EHT) equipment. Erections of
electrical technicians) was approved by the site scaffolding seem to be the only option to access this
management for the task. In absence of an Ex equipment equipment. The estimates indicated the need for huge
inventory, the Ex inspections were planned per each scaffolding structures throughout the process area would
process unit areas in the plant. The Ex inspections be required to complete the Ex inspection activities.
activities were planned such as to cover 100% Ex
installations (Electrical) in a period of 3 years. The task of In the meantime an incident was reported at the site
planned 100% close inspections for about 22000 where a top cover fell down from an energized power
electrical equipments required about 3 years to complete. point (EHT) installed at inaccessible height. Normally the
power point cover is tied to the body with a wire string and
In the meantime to mitigate the risk of ignition due to a can only be opened with a special tool. The plant
defective Ex equipment the continuous supervision vibrations cannot make it loose. This incident raised a
requirements per IEC 60079-17 were implemented at site serious concern about the Ex inspection process during
in addition to the normal periodic inspections. The the commissioning phase.
operations staff members were trained for Ex visual
inspections. The training package included some basic The incident increased the urgency of inspections for
theory on Ex equipment design features, type of Ex equipments installed at a height and implementation of
inspections, real life photographs (from other Oil & Gas corrective actions if any required.
facilities) of different kind of Ex defects they were
expected to see in the field. Any defects noticed during A local rope access contractor was working at the site for
the operator round were recorded in the CMMS and mechanical activities. They were asked if they can carry
operator field round log book. Once the defects were in Ex inspections at inaccessible height. On further
CMMS it will be prioritized for corrective maintenance discussions confirmed that there were a few rope access
based on the nature of defect observed. They were also persons in the team with an electrical background.
trained to implement the immediate risk reduction However they did not have the required Ex competency
measures e.g. for lighting fixtures or junction boxes for the Ex inspections.
observed with a water ingress, the power circuit will be
isolated immediately until the repair job is completed. For
each process area one operations field operator was
Resources, time and cost comparison we ere made for the
scaffolding and rope access options. The
e rope access or LE II
TABL
abseiling was a clear winner based on the comparison.
The man-hour comparison is shown below w in TABLE I. TYPE OF EX DEFE
ECTS OBSERVED
FIGURE I
Missing blanking
plugs on a power
point & a lighting
fixture
IV. REFERENCES
V. VITA